A study of causes of delay and cost overrun in office construction projects in the eThekwini Municipal Area, South Africa
View through CrossRef
On-time completion and conformity with assigned cost of every project are the most important factors in the success of project plans. Cost overruns and time overrun (delays) have been critical problems of many projects around the world in general and in South Africa in particular. The main objectives of this research are to assess the dominant causes of cost and time overruns, identifying possible and practical measures that can minimize overruns in office building construction projects around eThekwini Municipal area of Kwazulu-Natal. These objectives are achieved through the implementation of the research methodologies that are mainly literature review and questionnaire survey conducted to identify and evaluate the significant factors contributing to delay and cost overruns within the projects of interest. A review of literature identified eighty-five variables for delay, grouped in nine major categories and nine variables for cost overruns ranked in their order of importance in three sets based on the responses from the professionals working for the client, consultants and contractors. The agreement among the sets of rankings for delay and cost overruns has also been tested using statistical methods. The result indicates that there is strong agreement on ranking the importance of the individual variables of delay and cost overruns between parties. From each of the three sets of rankings, the twenty most important variables of delay and the three most important variables of cost overrun are identified as critical. Based on overall results, the top five most important causes are contractor’s cash flow problems, delay in progress payments by the client, poor site supervision and management by contractor, inefficient quality control by the contractor during construction leading to rework due to errors, and contractor’s difficulties in financing the project. Out of the 20 most important delay causing variables, three are found to be common between all parties. These are delay in progress payments by the client, delay in delivery and late ordering of material, and insufficient skill of labour. Furthermore, the study reveals that all stakeholders of construction parties are deeply involved in contributing to the causes of the problems. Thus, in order to eliminate or minimize cost and time extension of office construction projects in the eThekwini Municipal area, a joint effort based on teamwork is essential through effective project planning, controlling and monitoring which boils down to putting in place best practice construction project management.
Title: A study of causes of delay and cost overrun in office construction projects in the eThekwini Municipal Area, South Africa
Description:
On-time completion and conformity with assigned cost of every project are the most important factors in the success of project plans.
Cost overruns and time overrun (delays) have been critical problems of many projects around the world in general and in South Africa in particular.
The main objectives of this research are to assess the dominant causes of cost and time overruns, identifying possible and practical measures that can minimize overruns in office building construction projects around eThekwini Municipal area of Kwazulu-Natal.
These objectives are achieved through the implementation of the research methodologies that are mainly literature review and questionnaire survey conducted to identify and evaluate the significant factors contributing to delay and cost overruns within the projects of interest.
A review of literature identified eighty-five variables for delay, grouped in nine major categories and nine variables for cost overruns ranked in their order of importance in three sets based on the responses from the professionals working for the client, consultants and contractors.
The agreement among the sets of rankings for delay and cost overruns has also been tested using statistical methods.
The result indicates that there is strong agreement on ranking the importance of the individual variables of delay and cost overruns between parties.
From each of the three sets of rankings, the twenty most important variables of delay and the three most important variables of cost overrun are identified as critical.
Based on overall results, the top five most important causes are contractor’s cash flow problems, delay in progress payments by the client, poor site supervision and management by contractor, inefficient quality control by the contractor during construction leading to rework due to errors, and contractor’s difficulties in financing the project.
Out of the 20 most important delay causing variables, three are found to be common between all parties.
These are delay in progress payments by the client, delay in delivery and late ordering of material, and insufficient skill of labour.
Furthermore, the study reveals that all stakeholders of construction parties are deeply involved in contributing to the causes of the problems.
Thus, in order to eliminate or minimize cost and time extension of office construction projects in the eThekwini Municipal area, a joint effort based on teamwork is essential through effective project planning, controlling and monitoring which boils down to putting in place best practice construction project management.
Related Results
The impact of the local government support on the sustainability of co-operatives and its role on poverty alleviation in the eThekwini Municipal region
The impact of the local government support on the sustainability of co-operatives and its role on poverty alleviation in the eThekwini Municipal region
It has been accepted that sustainable co-operatives create job opportunities and have become a source of income for many people worldwide. The concept and philosophy of co-operativ...
Time and Cost Overrun in the Saudi Arabian Oil and Gas Construction Industry
Time and Cost Overrun in the Saudi Arabian Oil and Gas Construction Industry
Many construction projects exceed time and budget. The Saudi Arabian construction projects are not an exception to this phenomenon. However, the causes of time and cost overrun of ...
A BESPOKE APPROACH FOR RELATING MATERIAL WASTE TO COST OVERRUN IN THE CONSTRUCTION INDUSTRY
A BESPOKE APPROACH FOR RELATING MATERIAL WASTE TO COST OVERRUN IN THE CONSTRUCTION INDUSTRY
The problems of material waste and cost overruns are common in the construction industry. These problems occur at different stages of a construction project, from planning, design ...
The influence of emerging technologies on small and medium manufacturing enterprises in eThekwini District Municipality of KwaZulu-Natal
The influence of emerging technologies on small and medium manufacturing enterprises in eThekwini District Municipality of KwaZulu-Natal
Manufacturing Small and Medium Enterprises (SMEs) in South Africa (SA) contribute meaningfully to economic growth, poverty reduction, social stability and job creation. Research on...
Cost control and operational performance at eThekwini human settlement unit
Cost control and operational performance at eThekwini human settlement unit
Government municipalities have encountered notable challenges due to their inability to undergo necessary revitalisation and keep pace with the ongoing modernisation of the contemp...
Effective monitoring of vehicle utilization : a case study of eThekwini Municipality FMSs
Effective monitoring of vehicle utilization : a case study of eThekwini Municipality FMSs
The effective monitoring of vehicle utilisation in real time in the eThekwini Municipality pose a challenge in service delivery. There is no linkage between the service that is bei...
Afrikanske smede
Afrikanske smede
African Smiths Cultural-historical and sociological problems illuminated by studies among the Tuareg and by comparative analysisIn KUML 1957 in connection with a description of sla...
Evaluation of water resource management systems in eThekwini Municipality
Evaluation of water resource management systems in eThekwini Municipality
Water is an essential and critical resource for human, animal and plant survival and our continuing existence on planet earth. Water is increasingly becoming a scarce resource, and...