Mitigation of Delays and Cost Overruns on Private Sector Projects in South Africa

View through CrossRef
PURPOSE This study aims to examine methods to mitigate delays and cost overruns that can be effectively implemented in private sector construction projects. DESIGN / METHODOLOGY / APPROACH An empirical study was undertaken using a questionnaire survey among randomly selected respondents in construction in the Gauteng province, south Africa. FINDINGS The key findings indicate that the main causes of cost overruns were poor estimation and project delays caused mainly by poor planning. Two methods ranked first as cost overrun mitigation methods include familiarising oneself with site conditions and the appointment of an experienced project manager to manage costs. Two methods ranked first as delay mitigation methods were timely approval of site records and payment of suppliers or contractors on time. RESEARCH LIMITATIONS / IMPLICATIONS The study focused on one province; it could extend to other regions, with a bigger sample to better generalise the results. PRACTICAL IMPLICATIONS To effectively implement methods to mitigate project delays and cost overruns, it is important that both the client and the project team ensure that they play their respective roles effectively. When planning for a project, it is important to focus on how to implement the methods and involve the whole construction team. ORIGINAL / VALUE OF PAPER This paper contributes to the literature on the implementation methods to mitigate the persistent delays and cost overruns within the construction industry in South Africa.This study is important as it provides a basis for effective and efficient project delivery by improving the implementation of project management methods and techniques regarding delays and cost overruns.
Association of Schools of Construction of Southern Africa, Postnet Suite 107, Private Bag X5516, Scottburgh 4180
Title: Mitigation of Delays and Cost Overruns on Private Sector Projects in South Africa
Description:
PURPOSE This study aims to examine methods to mitigate delays and cost overruns that can be effectively implemented in private sector construction projects.
DESIGN / METHODOLOGY / APPROACH An empirical study was undertaken using a questionnaire survey among randomly selected respondents in construction in the Gauteng province, south Africa.
FINDINGS The key findings indicate that the main causes of cost overruns were poor estimation and project delays caused mainly by poor planning.
Two methods ranked first as cost overrun mitigation methods include familiarising oneself with site conditions and the appointment of an experienced project manager to manage costs.
Two methods ranked first as delay mitigation methods were timely approval of site records and payment of suppliers or contractors on time.
RESEARCH LIMITATIONS / IMPLICATIONS The study focused on one province; it could extend to other regions, with a bigger sample to better generalise the results.
PRACTICAL IMPLICATIONS To effectively implement methods to mitigate project delays and cost overruns, it is important that both the client and the project team ensure that they play their respective roles effectively.
When planning for a project, it is important to focus on how to implement the methods and involve the whole construction team.
ORIGINAL / VALUE OF PAPER This paper contributes to the literature on the implementation methods to mitigate the persistent delays and cost overruns within the construction industry in South Africa.
This study is important as it provides a basis for effective and efficient project delivery by improving the implementation of project management methods and techniques regarding delays and cost overruns.

Related Results

Analysis of Cost and Time Overruns for Major Public Building Construction Projects in Dire Dawa City, Ethiopia
Analysis of Cost and Time Overruns for Major Public Building Construction Projects in Dire Dawa City, Ethiopia
Cost and time overruns are the critical challenges for construction projects. The consequences can extend beyond just monetary losses, causing project delays and even project cance...
A study of causes of delay and cost overrun in office construction projects in the eThekwini Municipal Area, South Africa
A study of causes of delay and cost overrun in office construction projects in the eThekwini Municipal Area, South Africa
On-time completion and conformity with assigned cost of every project are the most important factors in the success of project plans. Cost overruns and time overrun (delays) have b...
Identifying Factors Influencing Time and Cost Overruns in Public Construction Projects in Bhutan
Identifying Factors Influencing Time and Cost Overruns in Public Construction Projects in Bhutan
Construction industries worldwide are impacted by time and cost overruns, resulting in significant financial loss and failure to complete projects on time. Clients, contractors, an...
Afrikanske smede
Afrikanske smede
African Smiths Cultural-historical and sociological problems illuminated by studies among the Tuareg and by comparative analysisIn KUML 1957 in connection with a description of sla...
Mitigation Approach for Significant Causes of Contractor’s Delays in Construction Projects in Sri Lanka
Mitigation Approach for Significant Causes of Contractor’s Delays in Construction Projects in Sri Lanka
The construction industry has a dynamic and complex environment. The successful completion of a construction project depends on various factors. Accordingly, construction delay is ...
Factors predicting treatment delays in endometrial cancer
Factors predicting treatment delays in endometrial cancer
Background: Women diagnosed with type I endometrial cancer have a favorable prognosis and are often cured with surgery alone when treated in a timely manner at an early stage. Howe...
Cost Overrun Factor of Toll Road Project Construction
Cost Overrun Factor of Toll Road Project Construction
Abstract Results in more than 45 studies of infrastructure projects in 20 countries that ran overestimate. For rail projects, they predict average cost increases of ...