Analisis Penjadwalan Proyek Pembangunan dengan Menggunakan Metode CPM Dan PERT
View through CrossRef
Rama Engineering is one of the companies that is moving in the field of construction that is currently working on the construction project of the University of Pamulang campus 3 Witana Harja. In the implementation of such construction projects there is usually a deadline every week, but the actual delay from the planning of 9 months to 11 months requires the calculation of the project scheduling. Project scheduling is one of the planning elements that can provide information about the schedule of plans and the progress of ongoing projects. To find out the optimal time of the project is done analysis using the CPM method and for the most possible duration in the acceleration of the building construction project is analyzed using the PERT method. The results of the analysis using the CPM method showed a 3-week acceleration where the initial project duration of 35 weeks was 32 weeks with a 3% accelerated presentation score with a critical path A – B – C – D – E – R – S – U, whereas the analysis with the PERT method saw a 1-week 6-day accelerations where the project initial duration for 35 weeks became 33.17 weeks with an accelerating presentation score of 1.87% with a Critical Path A - B - C - D - E - R - S - U. In conclusion, in order to minimize the completion time of the project as a whole, a combination of similar activities is carried out.
.
Keywords: CPM, Project Management, PERT
Universitas Pamulang
Title: Analisis Penjadwalan Proyek Pembangunan dengan Menggunakan Metode CPM Dan PERT
Description:
Rama Engineering is one of the companies that is moving in the field of construction that is currently working on the construction project of the University of Pamulang campus 3 Witana Harja.
In the implementation of such construction projects there is usually a deadline every week, but the actual delay from the planning of 9 months to 11 months requires the calculation of the project scheduling.
Project scheduling is one of the planning elements that can provide information about the schedule of plans and the progress of ongoing projects.
To find out the optimal time of the project is done analysis using the CPM method and for the most possible duration in the acceleration of the building construction project is analyzed using the PERT method.
The results of the analysis using the CPM method showed a 3-week acceleration where the initial project duration of 35 weeks was 32 weeks with a 3% accelerated presentation score with a critical path A – B – C – D – E – R – S – U, whereas the analysis with the PERT method saw a 1-week 6-day accelerations where the project initial duration for 35 weeks became 33.
17 weeks with an accelerating presentation score of 1.
87% with a Critical Path A - B - C - D - E - R - S - U.
In conclusion, in order to minimize the completion time of the project as a whole, a combination of similar activities is carried out.
.
Keywords: CPM, Project Management, PERT.
Related Results
FAKTOR-FAKTOR YANG MEMPENGARUHI MORTALITAS PADA PASIEN DENGAN FRAKTUR COSTA: Literature Review
FAKTOR-FAKTOR YANG MEMPENGARUHI MORTALITAS PADA PASIEN DENGAN FRAKTUR COSTA: Literature Review
FAKTOR-FAKTOR YANG MEMPENGARUHI MORTALITAS PADA PASIEN DENGAN FRAKTUR COSTA: Literature Review Anna Tri Wahyuni1), Masfuri2), Liya Arista3)1,2,3 Fakultas Ilmu Keperawatan Univers...
A67-15 Impact of Initiation of a Pulmonary Embolism Response Team (PERT) on Outpatient Pulmonary Follow-up
A67-15 Impact of Initiation of a Pulmonary Embolism Response Team (PERT) on Outpatient Pulmonary Follow-up
Abstract
Rationale
Pulmonary Embolism Response Teams (PERT) provide in-hospital risk stratification and management of acu...
ANALISIS METODE NETWORK PLANNING DAN S-CURVE PROYEK KONSTRUKSI DI BOGOR
ANALISIS METODE NETWORK PLANNING DAN S-CURVE PROYEK KONSTRUKSI DI BOGOR
<p>Hasil pengujian reliabilitas dan validitas instrumen penelitian maka didapatkan nilai pengujian reliabilitas untuk atribut-atribut variabel CPM sebesar 0,944, variabel PDM...
ANALISA PENJADWALAN PROYEK PEMBANGUNAN APARTEMEN MENGGUNAKAN METODE CPM (CRITICAL PATH METHOD)
ANALISA PENJADWALAN PROYEK PEMBANGUNAN APARTEMEN MENGGUNAKAN METODE CPM (CRITICAL PATH METHOD)
Peningkatan peduduk di Kota Tangerang berbanding terbalik dengan ketersedian lahan pada kota ini, oleh karena itu proyek permbangunan tempat tinggal dibuat menjadi kearah vertikal ...
Penerapan Manajemen Proyek dengan Metode CPM dan PERT pada Pembangunan Gedung Operasi RSUD Dr. H. Kumpulan Pane Kota Tebing Tinggi
Penerapan Manajemen Proyek dengan Metode CPM dan PERT pada Pembangunan Gedung Operasi RSUD Dr. H. Kumpulan Pane Kota Tebing Tinggi
Keterlambatan menyelesaikan suatu proyek adalah masalah yang sering muncul dan berdampak pada semua pekerjaan yang telah direncanakan dalam proyek tersebut. Sangat penting untuk me...
Evaluasi Penjadwalan Proyek Kapal Penyeberangan RO-RO 500 GT Melalui Pendekatan Metode CPM Dan PERT Studi Kasus PT. XYZ
Evaluasi Penjadwalan Proyek Kapal Penyeberangan RO-RO 500 GT Melalui Pendekatan Metode CPM Dan PERT Studi Kasus PT. XYZ
PT. XYZ yang merupakan galangan yang memiliki peluang yang besar untuk menjadi galangan maju ini didukung oleh tenaga tenaga Engineering yang berkualitas dan professional dan keter...
Implementasi Model Jaringan dan Critical Path Method Pada Perencanaan dan Penjadwalan Proyek Bendungan PT. ABC
Implementasi Model Jaringan dan Critical Path Method Pada Perencanaan dan Penjadwalan Proyek Bendungan PT. ABC
Intisari—Proyek Bendungan “Y” yang saat ini dikerjakan oleh PT. ABC terdiri dari dua aktivitas besar, yaitu Proyek Pabrikasi dan Proyek Instalasi. Saat ini proyek Pabrikasi sudah t...
Studi Rencana Anggaran Biaya Dan Penjadwalan Pekerjaan Dengan Metode Pert Pada Pekerjaan Perkuatan Tebing Jembatan Terusan Bojonegoro – Tuban (Kanor – Semambung) Kec. Kanor
Studi Rencana Anggaran Biaya Dan Penjadwalan Pekerjaan Dengan Metode Pert Pada Pekerjaan Perkuatan Tebing Jembatan Terusan Bojonegoro – Tuban (Kanor – Semambung) Kec. Kanor
Permasalahan umum dalam pelaksanaan proyek konstruksi adalah adanya keterlambatan dan ketidaksesuaian antara pelaksanaan di lokasi dengan jadwal yang telah ditentukan sehingga memp...