Analisis Perhitungan Volume Beton Metode Konvensional dan BIM Autodesk Revit pada Proyek Jembatan Tipe Lengkung terhadap Efektivitas Biaya
View through CrossRef
Concrete volume calculation is a crucial factor in preventing cost overruns when preparing the Budget Plan (RAB) for construction projects. In arch bridge projects, the complex structural geometry often makes conventional volume calculation methods complicated and prone to errors, particularly due to the geometric complexity of the arch beams. This study aims to analyze the comparison of concrete volume calculation results between the conventional method and the Building Information Modeling (BIM) method using Autodesk Revit in terms of cost-effectiveness. The case study was conducted on the Short Span II Pulau Balang Bridge Duplication Project in the Nusantara Capital City (IKN), Penajam Paser Utara Regency, East Kalimantan. The research objects include substructures (bore piles, pile caps, abutments, piers, and wing walls) and superstructures in the form of arch beams. The research method employs a quantitative approach by calculating concrete volumes conventionally using AutoCAD and Microsoft Excel, as well as calculating with BIM Autodesk Revit through three-dimensional modeling and Quantity Take-Off (QTO) exports. The results indicate that the BIM Autodesk Revit method generates a larger concrete volume compared to the conventional method, resulting in a higher total cost based on the BIM volume. The total cost for the conventional method amounted to IDR 142,613,245,996.12, while the BIM Autodesk Revit method amounted to IDR 143,127,208,186.60. These differences are influenced by the level of calculation detail, the simplification of shapes in the conventional method, and the precision of modeling in Autodesk Revit.
Politeknik Pratama Purwokerto
Title: Analisis Perhitungan Volume Beton Metode Konvensional dan BIM Autodesk Revit pada Proyek Jembatan Tipe Lengkung terhadap Efektivitas Biaya
Description:
Concrete volume calculation is a crucial factor in preventing cost overruns when preparing the Budget Plan (RAB) for construction projects.
In arch bridge projects, the complex structural geometry often makes conventional volume calculation methods complicated and prone to errors, particularly due to the geometric complexity of the arch beams.
This study aims to analyze the comparison of concrete volume calculation results between the conventional method and the Building Information Modeling (BIM) method using Autodesk Revit in terms of cost-effectiveness.
The case study was conducted on the Short Span II Pulau Balang Bridge Duplication Project in the Nusantara Capital City (IKN), Penajam Paser Utara Regency, East Kalimantan.
The research objects include substructures (bore piles, pile caps, abutments, piers, and wing walls) and superstructures in the form of arch beams.
The research method employs a quantitative approach by calculating concrete volumes conventionally using AutoCAD and Microsoft Excel, as well as calculating with BIM Autodesk Revit through three-dimensional modeling and Quantity Take-Off (QTO) exports.
The results indicate that the BIM Autodesk Revit method generates a larger concrete volume compared to the conventional method, resulting in a higher total cost based on the BIM volume.
The total cost for the conventional method amounted to IDR 142,613,245,996.
12, while the BIM Autodesk Revit method amounted to IDR 143,127,208,186.
60.
These differences are influenced by the level of calculation detail, the simplification of shapes in the conventional method, and the precision of modeling in Autodesk Revit.
Related Results
BIM implementation in architectural practices : towards advanced collaborative approaches based on digital technologies
BIM implementation in architectural practices : towards advanced collaborative approaches based on digital technologies
We are at a stage where Building Information Modelling (BIM) has reached a maturity level to be widely adopted by the professionals and organizations within the Architectural, Engi...
BIM implementation: an empirical validation for a four-wheel model
BIM implementation: an empirical validation for a four-wheel model
Purpose Because BIM adoption is still afflicted by various types of hurdles, a complete BIM implementation model is required to provide the necessary methods for driving BIM adopti...
ANALISIS KUAT TARIK BELAH BETON PADA STANDAR KUAT TEKAN K.250 DENGAN MENGGUNAKAN LIMBAH PECAHAN BETON SEBAGAI PENGGANTI AGREGAT KASAR
ANALISIS KUAT TARIK BELAH BETON PADA STANDAR KUAT TEKAN K.250 DENGAN MENGGUNAKAN LIMBAH PECAHAN BETON SEBAGAI PENGGANTI AGREGAT KASAR
Beton merupakan bahan konstruksi yang sangat penting dan paling dominan digunakan pada struktur bangunan. Beton sangat diminati karena bahan ini merupakan bahan konstruksi yang mem...
Implementasi BIM dengan Autodesk Revit 2025 pada quantity take-off material struktur Gedung Plaza Airlangga (Unair) tahap 1 terhadap volume
Implementasi BIM dengan Autodesk Revit 2025 pada quantity take-off material struktur Gedung Plaza Airlangga (Unair) tahap 1 terhadap volume
Perkembangan pesat dalam sektor konstruksi sangat dipengaruhi oleh fungsinya yang krusial dan efisien. Hal ini mendorong sektor konstruksi menuju integrasi yang lebih baik. Saat in...
ANALISIS PERHITUNGAN QUANTITY TAKE-OFF MENGGUNAKAN BUILDING INFORMATION MODELING (BIM) PADA PROYEK JALAN TOL INDRALAYA-PRABUMULIH
ANALISIS PERHITUNGAN QUANTITY TAKE-OFF MENGGUNAKAN BUILDING INFORMATION MODELING (BIM) PADA PROYEK JALAN TOL INDRALAYA-PRABUMULIH
Penerapan BIM pada proyek Pembangunan Jalan Tol merupakan upaya Kementrian PUPR dalam peningkatan daya produktifitas dan daya guna perencanaan dan pembangunan proyek konstruksi jal...
ANALISIS PENURUNAN MUTU BETON STRUKTURAL AKIBAT PENGARUH AIR LAUT PADA MASA PEMELIHARAAN
ANALISIS PENURUNAN MUTU BETON STRUKTURAL AKIBAT PENGARUH AIR LAUT PADA MASA PEMELIHARAAN
Air laut memiliki kandungan garam yang tinggi yang dapat menggerogoti kekuatan dan keawetan beton. Hal ini disebabkan klorida yang terdapat pada air laut yang merupakan garam yang ...
Analisis Estimasi Penyelesaian Proyek Konstruksi terhadap Waktu dan Biaya
Analisis Estimasi Penyelesaian Proyek Konstruksi terhadap Waktu dan Biaya
Proyek konstruksi merupakan kegiatan yang memiliki tingkat kompleksitas tinggi, sehingga sering terjadi keterlambatan penyelesaian proyek maupun pembengkakan biaya akibat sistem ma...
ANALISIS PERBANDINGAN VOLUME PEKERJAAN STRUKTUR ANTARA PERHITUNGAN MANUAL DENGAN BIM AUTODESK REVIT PADA PROYEK GEDUNG OLAHRAGA TAMBAKREJO KABUPATEN BOJONEGORO
ANALISIS PERBANDINGAN VOLUME PEKERJAAN STRUKTUR ANTARA PERHITUNGAN MANUAL DENGAN BIM AUTODESK REVIT PADA PROYEK GEDUNG OLAHRAGA TAMBAKREJO KABUPATEN BOJONEGORO
Penelitian ini membahas tentang perbandingan hasil perhitungan volume pekerjaan struktur pada proyek pembangunan Gedung Olahraga tambakrejo, Kabupaten Bojonegoro, dengan menggunaan...