ACG Topsides Design and Fabrication
View through CrossRef
Abstract
The ACG Project concept basis was to deliver as few platforms with as many wellslots as possible, resulting in the delivery of four new drilling topsides facilities having a total weight of the order of 15,500 tonnes each, plus two injection support platforms weighing approximately 13,000 tonnes each. Integrated topsides for this size had never been fabricated in Azerbaijan.
The project was also challenged due to limited and out-of-date fabrication infrastructure and no in-country proven fabrication contractor capability for such topsides construction.
The solution was to establish a topsides production line approach to delivery, with the design being cloned from deck to deck underpinned by simplistic layouts for drilling and injection support topsides, respectively. Further, the installation of these decks would be via floatover installation method, thereby allowing the maximum amount of onshore commissioning with a minimum of offshore commissioning. All topsides fabrication would occur at two in-country fabrication yards, with the exception of the drilling facilities and the living quarters.
This paper describes the development of the topsides layouts, supporting engineering design, fabrication yard upgrades, cloning benefits and decisions associated with where and how fabrication could optimally be achieved.
The ACG topsides production line was successfully established and six topsides have been delivered offshore since start of fabrication in November 2001. As a result, similar production lines are being established on other developments.
The information in the paper will be of use to others who have similar large field offshore developments where full cycle delivery - from start of engineering design to start of production - can be optimised.
The production line approach, underpinned by standardisation of design, fabrication processes and people, proved capable of delivering deck-on-deck reductions in cost and schedule. The delivery can be improved further through the rigorous use of lessons learned feedback.
This project demonstrates the benefits of developing innovative solutions to overcome specific problems. These solutions were relevant in a part of the world that has not traditionally delivered facilities to shareholder standards.
Introduction
The ACG Full Field Development (FFD) Project began in 1997, but, due to a variety of economic and geopolitical reasons, the first phase of project sanction did not occur until September 2001. The chosen offshore development strategy involved three phases of incremental development - two large fixed offshore platforms for each phase (see Figure 1 at end of paper).
Title: ACG Topsides Design and Fabrication
Description:
Abstract
The ACG Project concept basis was to deliver as few platforms with as many wellslots as possible, resulting in the delivery of four new drilling topsides facilities having a total weight of the order of 15,500 tonnes each, plus two injection support platforms weighing approximately 13,000 tonnes each.
Integrated topsides for this size had never been fabricated in Azerbaijan.
The project was also challenged due to limited and out-of-date fabrication infrastructure and no in-country proven fabrication contractor capability for such topsides construction.
The solution was to establish a topsides production line approach to delivery, with the design being cloned from deck to deck underpinned by simplistic layouts for drilling and injection support topsides, respectively.
Further, the installation of these decks would be via floatover installation method, thereby allowing the maximum amount of onshore commissioning with a minimum of offshore commissioning.
All topsides fabrication would occur at two in-country fabrication yards, with the exception of the drilling facilities and the living quarters.
This paper describes the development of the topsides layouts, supporting engineering design, fabrication yard upgrades, cloning benefits and decisions associated with where and how fabrication could optimally be achieved.
The ACG topsides production line was successfully established and six topsides have been delivered offshore since start of fabrication in November 2001.
As a result, similar production lines are being established on other developments.
The information in the paper will be of use to others who have similar large field offshore developments where full cycle delivery - from start of engineering design to start of production - can be optimised.
The production line approach, underpinned by standardisation of design, fabrication processes and people, proved capable of delivering deck-on-deck reductions in cost and schedule.
The delivery can be improved further through the rigorous use of lessons learned feedback.
This project demonstrates the benefits of developing innovative solutions to overcome specific problems.
These solutions were relevant in a part of the world that has not traditionally delivered facilities to shareholder standards.
Introduction
The ACG Full Field Development (FFD) Project began in 1997, but, due to a variety of economic and geopolitical reasons, the first phase of project sanction did not occur until September 2001.
The chosen offshore development strategy involved three phases of incremental development - two large fixed offshore platforms for each phase (see Figure 1 at end of paper).
Related Results
Arthit Field Development: Float-over Hardware Design and Issues
Arthit Field Development: Float-over Hardware Design and Issues
Abstract
The 17,500 metric ton Arthit PP topsides was successfully installed in December of 2007 in the Gulf of Thailand after a short voyage from Batam Island, I...
Incidence, mortalité et facteurs pronostiques de l'artérite à cellules géantes (Horton)
Incidence, mortalité et facteurs pronostiques de l'artérite à cellules géantes (Horton)
L’Artérite à Cellules Géantes (ACG) est la plus fréquente des vascularites chroniques auto-immunes des gros et moyens vaisseaux des personnes âgées. Le spectre de la maladie semble...
Modular Topsides for Large Floating Production Platforms
Modular Topsides for Large Floating Production Platforms
1. ABSTRACT
Topsides for floating production systems are traditionally built as integrated decks. This paper describes the results of study work, conducted to det...
A follow up model for patients with atrophic chronic gastritis and intestinal metaplasia
A follow up model for patients with atrophic chronic gastritis and intestinal metaplasia
Aim:
To devise a follow up model for patients with gastric cancer associated lesions, such as atrophic chronic gastritis (ACG) and intestinal metaplasia (IM).
...
Modelling Iceberg-Topsides Impacts Using High Resolution Iceberg Profiles
Modelling Iceberg-Topsides Impacts Using High Resolution Iceberg Profiles
Abstract
Platforms operating in arctic and subarctic regions such as the Grand Banks, Labrador Sea, Barents Sea and offshore Greenland are exposed to the risk of ice...
Lucius Offshore Installation of Flowlines, Risers and Topsides
Lucius Offshore Installation of Flowlines, Risers and Topsides
Abstract
This paper provides an overview of the design, fabrication and installation of Anadarko's Lucius Development flowlines, risers and topsides including all an...
“We help people change harmful norms”: Working with key opinion leaders to influence MNCH+N behaviors in Nigeria.
“We help people change harmful norms”: Working with key opinion leaders to influence MNCH+N behaviors in Nigeria.
Abstract
Background: Nigeria’s Maternal, newborn, and child health and nutrition (MNCH+N) outcomes rank among the world’s poorest. Engaging traditional and religious leader...