Javascript must be enabled to continue!
Lucius Offshore Installation of Flowlines, Risers and Topsides
View through CrossRef
Abstract
This paper provides an overview of the design, fabrication and installation of Anadarko's Lucius Development flowlines, risers and topsides including all ancillary lifts required to fully complete the installation of the Lucius Spar.
The production flowlines, risers and associated structures were fabricated and installed by Heerema Marine Contractors US, Inc. utilizing the new build vessel DCV Aegir. At the time of contract execution the vessel was still under development and new vessel procedures as well as project installation procedures were required to perform the installation safely and within schedule. The export risers and flowlines were designed and fabricated by Technip USA, Inc. and installed using the Deep Blue reel installation vessel. The export risers were pulled in utilizing a custom built 1,000-ton capacity chain jack system designed, fabricated and installed by Versabar, Inc., The topsides installation was performed by Heerema Marine Contractors US Inc. utilizing the heavy lift vessel DCV Thialf for the 10,000-ton topsides lift and the heavy lift vessel DCV Balder for the ancillary lifts.
Some of the unique challenges addressed in this paper include some "firsts" which include the design and qualification of titanium stress joints on the export risers, the design and qualification of a diverless close in spool system as well as the design and qualification of a diverless pull head required to hang off the export risers. This paper also addresses the design and offshore installation of a 1,000-ton chain jack system which was designed late in the project life to install the export risers after the main topsides was installed. Additional firsts included the use of pile based riser base pipeline end manifolds which were designed to allow for a tight subsea architecture and sustain extensive bottom tension loads.
Title: Lucius Offshore Installation of Flowlines, Risers and Topsides
Description:
Abstract
This paper provides an overview of the design, fabrication and installation of Anadarko's Lucius Development flowlines, risers and topsides including all ancillary lifts required to fully complete the installation of the Lucius Spar.
The production flowlines, risers and associated structures were fabricated and installed by Heerema Marine Contractors US, Inc.
utilizing the new build vessel DCV Aegir.
At the time of contract execution the vessel was still under development and new vessel procedures as well as project installation procedures were required to perform the installation safely and within schedule.
The export risers and flowlines were designed and fabricated by Technip USA, Inc.
and installed using the Deep Blue reel installation vessel.
The export risers were pulled in utilizing a custom built 1,000-ton capacity chain jack system designed, fabricated and installed by Versabar, Inc.
, The topsides installation was performed by Heerema Marine Contractors US Inc.
utilizing the heavy lift vessel DCV Thialf for the 10,000-ton topsides lift and the heavy lift vessel DCV Balder for the ancillary lifts.
Some of the unique challenges addressed in this paper include some "firsts" which include the design and qualification of titanium stress joints on the export risers, the design and qualification of a diverless close in spool system as well as the design and qualification of a diverless pull head required to hang off the export risers.
This paper also addresses the design and offshore installation of a 1,000-ton chain jack system which was designed late in the project life to install the export risers after the main topsides was installed.
Additional firsts included the use of pile based riser base pipeline end manifolds which were designed to allow for a tight subsea architecture and sustain extensive bottom tension loads.
Related Results
Arthit Field Development: Float-over Hardware Design and Issues
Arthit Field Development: Float-over Hardware Design and Issues
Abstract
The 17,500 metric ton Arthit PP topsides was successfully installed in December of 2007 in the Gulf of Thailand after a short voyage from Batam Island, I...
The Development of Deepwater Riser Recovery Technology in Liuhua Oil Field
The Development of Deepwater Riser Recovery Technology in Liuhua Oil Field
Abstract
In the May of 2006, the three flexible risers of the FPSO " Nanhai Shengli?? at the Liuhua oil field in South China Sea were broken and dropped into seab...
ACG Topsides Design and Fabrication
ACG Topsides Design and Fabrication
Abstract
The ACG Project concept basis was to deliver as few platforms with as many wellslots as possible, resulting in the delivery of four new drilling topsides...
Reeled Risers: Deepwater and Dynamic Considerations
Reeled Risers: Deepwater and Dynamic Considerations
Abstract
Installation of steel pipelines and risers by the reel-lay method has been generating increasing interest, particularly for deepwater service. Reel-lay o...
Flow Assurance Management for Bijupira and Salema Field Development
Flow Assurance Management for Bijupira and Salema Field Development
Abstract
Bijupirá & Salema field is located in the Campos Basin offshore Brazil in water depths ranging from 600 to 800 meters. A consortium led by Enterpris...
T&I Engineering of Monopiles: Key Considerations – Bid to Execution
T&I Engineering of Monopiles: Key Considerations – Bid to Execution
Abstract
Monopiles remain the simplest and most widely adopted foundation solution for offshore wind farms. However, unlike onshore developments, offshore monopil...
Deepwater Achievements and Challenges on the Extra Roncador Pipeline Installation Project
Deepwater Achievements and Challenges on the Extra Roncador Pipeline Installation Project
Abstract
The scope of this paper is to describe challenges and achievements related to the deepwater installation of flowlines and umbilicals for Petrobras at Cam...
SS: Spar Technology- Developments in Deepwater spar installation
SS: Spar Technology- Developments in Deepwater spar installation
Abstract
During the last seven years Heerema Marine Contractors (HMC) has installed more than half of all Spars in the deep waters of the Gulf of Mexico. The dual...

