Search engine for discovering works of Art, research articles, and books related to Art and Culture
ShareThis
Javascript must be enabled to continue!

Lucius Offshore Installation of Flowlines, Risers and Topsides

View through CrossRef
Abstract This paper provides an overview of the design, fabrication and installation of Anadarko's Lucius Development flowlines, risers and topsides including all ancillary lifts required to fully complete the installation of the Lucius Spar. The production flowlines, risers and associated structures were fabricated and installed by Heerema Marine Contractors US, Inc. utilizing the new build vessel DCV Aegir. At the time of contract execution the vessel was still under development and new vessel procedures as well as project installation procedures were required to perform the installation safely and within schedule. The export risers and flowlines were designed and fabricated by Technip USA, Inc. and installed using the Deep Blue reel installation vessel. The export risers were pulled in utilizing a custom built 1,000-ton capacity chain jack system designed, fabricated and installed by Versabar, Inc., The topsides installation was performed by Heerema Marine Contractors US Inc. utilizing the heavy lift vessel DCV Thialf for the 10,000-ton topsides lift and the heavy lift vessel DCV Balder for the ancillary lifts. Some of the unique challenges addressed in this paper include some "firsts" which include the design and qualification of titanium stress joints on the export risers, the design and qualification of a diverless close in spool system as well as the design and qualification of a diverless pull head required to hang off the export risers. This paper also addresses the design and offshore installation of a 1,000-ton chain jack system which was designed late in the project life to install the export risers after the main topsides was installed. Additional firsts included the use of pile based riser base pipeline end manifolds which were designed to allow for a tight subsea architecture and sustain extensive bottom tension loads.
Title: Lucius Offshore Installation of Flowlines, Risers and Topsides
Description:
Abstract This paper provides an overview of the design, fabrication and installation of Anadarko's Lucius Development flowlines, risers and topsides including all ancillary lifts required to fully complete the installation of the Lucius Spar.
The production flowlines, risers and associated structures were fabricated and installed by Heerema Marine Contractors US, Inc.
utilizing the new build vessel DCV Aegir.
At the time of contract execution the vessel was still under development and new vessel procedures as well as project installation procedures were required to perform the installation safely and within schedule.
The export risers and flowlines were designed and fabricated by Technip USA, Inc.
and installed using the Deep Blue reel installation vessel.
The export risers were pulled in utilizing a custom built 1,000-ton capacity chain jack system designed, fabricated and installed by Versabar, Inc.
, The topsides installation was performed by Heerema Marine Contractors US Inc.
utilizing the heavy lift vessel DCV Thialf for the 10,000-ton topsides lift and the heavy lift vessel DCV Balder for the ancillary lifts.
Some of the unique challenges addressed in this paper include some "firsts" which include the design and qualification of titanium stress joints on the export risers, the design and qualification of a diverless close in spool system as well as the design and qualification of a diverless pull head required to hang off the export risers.
This paper also addresses the design and offshore installation of a 1,000-ton chain jack system which was designed late in the project life to install the export risers after the main topsides was installed.
Additional firsts included the use of pile based riser base pipeline end manifolds which were designed to allow for a tight subsea architecture and sustain extensive bottom tension loads.

Related Results

Arthit Field Development: Float-over Hardware Design and Issues
Arthit Field Development: Float-over Hardware Design and Issues
Abstract The 17,500 metric ton Arthit PP topsides was successfully installed in December of 2007 in the Gulf of Thailand after a short voyage from Batam Island, I...
ACG Topsides Design and Fabrication
ACG Topsides Design and Fabrication
Abstract The ACG Project concept basis was to deliver as few platforms with as many wellslots as possible, resulting in the delivery of four new drilling topsides...
Reeled Risers: Deepwater and Dynamic Considerations
Reeled Risers: Deepwater and Dynamic Considerations
Abstract Installation of steel pipelines and risers by the reel-lay method has been generating increasing interest, particularly for deepwater service. Reel-lay o...
SS: Spar Technology- Developments in Deepwater spar installation
SS: Spar Technology- Developments in Deepwater spar installation
Abstract During the last seven years Heerema Marine Contractors (HMC) has installed more than half of all Spars in the deep waters of the Gulf of Mexico. The dual...
Dynamic Behavior of a Flexible Line During Installation
Dynamic Behavior of a Flexible Line During Installation
ABSTRACT In order to get information about the forces on the connection between a flexible riser and a wet Christmas tree during a guide lineless lay-away operati...
Modular Topsides for Large Floating Production Platforms
Modular Topsides for Large Floating Production Platforms
1. ABSTRACT Topsides for floating production systems are traditionally built as integrated decks. This paper describes the results of study work, conducted to det...
Challenges of TLP Installation Offshore Brazil
Challenges of TLP Installation Offshore Brazil
Abstract Installation of a Tension Leg Platform comprises distinct phases, all of which can provide special challenges when considering locating a TLP in a fronti...
Failure Detection Monitoring System Qualification Through a Full-Scale Dynamic Test
Failure Detection Monitoring System Qualification Through a Full-Scale Dynamic Test
Abstract Flexible riser systems are widely adopted by the industry as solutions to interconnect subsea equipment and pipelines to floating production units. Their...

Back to Top