The Heidrun Field: TLP Global Performance and Hydrodynamics
View through CrossRef
Abstract
Heidrun, the first deep draft concrete TLP, was installed in July 1995 in a water depth of 345m on the Haltenbank of the Norwegian Continental Shelf. The TLP has a displacement of 290610 tomes and the hull was designed to support a total topsides weight of 64980 tomes on Module Support Beams (MSBS) weighing 18550 tonnes.
The TLP is a marine and structural system with complex interaction between the hull, topsides and the mooring system. This paper describe a the basis for the sizing of the hull and tether system. Key issues addressed include weight control, stability during installation, tether system loads and constraints from fabrication and installation. The relative merits of the use of concrete rather than steel for the hull construction are discussed from a hydrodynamic perspective.
Hydrodynamic model testing was used to resolve many critical design issues, including 'ringing' which has had significant consequences for other deep water offshore platforms. New criteria were established for tether pretension.
The Operational Expense of TLP Marine Control has been minimized by provision of the Marine Control and Data Acquisition system (MCDA), which is used for in-service control of tether tension and for acquisition of key environmental and performance data. Continuity of weight control during Engineering, Construction, Installation and Operation was successfully implemented. TLP Performance data is presented in sea states up to 10.5m significant.
Evaluation' by the Conoco Project Team of TLP performance, on-board training of Operators and provision of an automatic system for continuous shore-base monitoring of marine performance facilitated the timely handover of responsibility for TLP Marine Control to Statoil Operations.
Introduction
Early conceptual studies [1, 2] identified several advantages of the concrete hull which were key in concept selection. These include elimination of fatigue concerns at complex node intersections, high distance to impact loads, relatively simple and faster construction, low sensitivity to increases in topside a weight and low tether design loads.
Preliminary Engineering Contracts were awarded to two competing Contractors in February 1991 for development of a concrete hull TLP for the Heidrun Field Development. The Engineering, Procurement, Construction and Installation (EPCI) contract was awarded to Norwegian Contractors (NC) in December91. Following wind tunnel testing of the topsides in November91, the NC concept was model tested in January 1992 in order to accommodate the design freeze scheduled for the end of March 92.
Unexpectedly high loads were measured in the tether system due to 'ringing', the term given to the global vibration of the TLP at it a natural period in pitch and roll, coined during the model testing of the Hutton TLP in 1979-80. Ringing was previously considered for steel TLPs to be a minor load effect and its cause had never been clearly identified.
Title: The Heidrun Field: TLP Global Performance and Hydrodynamics
Description:
Abstract
Heidrun, the first deep draft concrete TLP, was installed in July 1995 in a water depth of 345m on the Haltenbank of the Norwegian Continental Shelf.
The TLP has a displacement of 290610 tomes and the hull was designed to support a total topsides weight of 64980 tomes on Module Support Beams (MSBS) weighing 18550 tonnes.
The TLP is a marine and structural system with complex interaction between the hull, topsides and the mooring system.
This paper describe a the basis for the sizing of the hull and tether system.
Key issues addressed include weight control, stability during installation, tether system loads and constraints from fabrication and installation.
The relative merits of the use of concrete rather than steel for the hull construction are discussed from a hydrodynamic perspective.
Hydrodynamic model testing was used to resolve many critical design issues, including 'ringing' which has had significant consequences for other deep water offshore platforms.
New criteria were established for tether pretension.
The Operational Expense of TLP Marine Control has been minimized by provision of the Marine Control and Data Acquisition system (MCDA), which is used for in-service control of tether tension and for acquisition of key environmental and performance data.
Continuity of weight control during Engineering, Construction, Installation and Operation was successfully implemented.
TLP Performance data is presented in sea states up to 10.
5m significant.
Evaluation' by the Conoco Project Team of TLP performance, on-board training of Operators and provision of an automatic system for continuous shore-base monitoring of marine performance facilitated the timely handover of responsibility for TLP Marine Control to Statoil Operations.
Introduction
Early conceptual studies [1, 2] identified several advantages of the concrete hull which were key in concept selection.
These include elimination of fatigue concerns at complex node intersections, high distance to impact loads, relatively simple and faster construction, low sensitivity to increases in topside a weight and low tether design loads.
Preliminary Engineering Contracts were awarded to two competing Contractors in February 1991 for development of a concrete hull TLP for the Heidrun Field Development.
The Engineering, Procurement, Construction and Installation (EPCI) contract was awarded to Norwegian Contractors (NC) in December91.
Following wind tunnel testing of the topsides in November91, the NC concept was model tested in January 1992 in order to accommodate the design freeze scheduled for the end of March 92.
Unexpectedly high loads were measured in the tether system due to 'ringing', the term given to the global vibration of the TLP at it a natural period in pitch and roll, coined during the model testing of the Hutton TLP in 1979-80.
Ringing was previously considered for steel TLPs to be a minor load effect and its cause had never been clearly identified.
Related Results
The Concerns and Benefits of Standardization on the Heidrun Subsea Water Injection System
The Concerns and Benefits of Standardization on the Heidrun Subsea Water Injection System
Abstract
Ms paper describes the process of standarzing the Heidrun Sub sea water injection system. The layout, basis of design and equipment utilized are presente...
Concrete Hulls For Tension Leg Platforms
Concrete Hulls For Tension Leg Platforms
ABSTRACT
This paper describes the main features of a concrete hull TLP concept developed for the Heidrun Field. The hydrodynamic response and the methods adopted ...
New Directions in TLP Technology
New Directions in TLP Technology
Abstract
Of the many deepwater platform concepts that were developed as deepwater platform technology matured, the TLP has been the most frequently selected for d...
The Heidrun Field - Marine Operations
The Heidrun Field - Marine Operations
ABSTRACT
The Heidrun Field development concept required an exceptional number of inshore and offshore marine operations to assemble the final product, Contained w...
The Heidrun Field: Global Structural Design and Analysis of the Heidrun TLP
The Heidrun Field: Global Structural Design and Analysis of the Heidrun TLP
Abstract
The structural analysis and design of the Heidrun tension leg platform presented many technical Challenge a that had to be overcome in a fast and efficie...
Auger TLP Well System Challenges and Innovations
Auger TLP Well System Challenges and Innovations
ABSTRACT
The Auger TLP well system has successfully employed novel features to satisfy challenging design requirements of drilling, completing, and producing near...
TLP Rigid Riser: A Case Study
TLP Rigid Riser: A Case Study
Abstract
This case study presents a Production/Injection rigid riser. The riser is designed for 300 meter water depth in compliance with Norwegian regulations. Em...
Challenges of TLP Installation Offshore Brazil
Challenges of TLP Installation Offshore Brazil
Abstract
Installation of a Tension Leg Platform comprises distinct phases, all of which can provide special challenges when considering locating a TLP in a fronti...