Javascript must be enabled to continue!
The Heidrun Field - Marine Operations
View through CrossRef
ABSTRACT
The Heidrun Field development concept required an exceptional number of inshore and offshore marine operations to assemble the final product, Contained within the marine operations program were a number of innovations and advancements, such as subsea installation of heavy structures without the use of cranes, pre-installation of tethers, simultaneous leek-off of a TLP, and execution of pipeline bundle installation with a record tow length and water depth. In addition, the size of the structures, the remote field location, and a diverless philosophy in relatively deep water (345m) also contributed to making theconduct of successful operations a challenge.
This paper describe the major offshore marine operations, including the tether foundation, tether, and TLP installations, as well as those for the export pipeline and direct shuttle loading systems, Highlights of the TLP template, water injection system, and TLP inshore operations are also briefly mentioned.
INTRODUCTION
Development of the Heidrun Field required an extensive effort in the area of marine operations. The operations took place over three years, commencing with TLP pre-drilling template installation in August of 1992 and finishing with TLP installation in July 1995. The most intense period of operations was the summer of 1994. The total marine operations program comprised more than 130 main events (Table 1).
Supporting the operations were design, planning, contracting, and verification/testing activities, all coordinated by a Conoco Norway, Inc. (CNI) Project marine group which. at its peak, consisted of no more than 15 people.
The operations took place inshore, near-shore, and offshore. A total of approximately 60 vessels of all types contributed, through seven main contractors and numerous subcontractors. During the busy 1994 season, up to 14 vessels performing under several contracts were present simultaneously at Heidrun. A clear system of priority and field control was set up by CNI to ensure that vessel clashes and contractor downtime were avoided.
Throughout the operations, safety of personnel and equipment was given prime focus, with the result that only two Lost Workday Cases, both of a minor nature, were experienced in three years of offshore marine work.
This paper presents a brief technical overview of the majoroffshore operations, including a description of success factors and difficulties encountered.
A layout of the Heidrun Field is contained in Figure 1.
TETHER FOUNDATIONS
The four tether foundations were installed in July 1994. Their main particulars are given in Table 2, and their general arrangement is described in Reference 1 and Figure 2.
The installation of the tether foundations represented a significant breakthrough for installing large structures without the use of expensive heavy lift vessels. Each foundation unit, weighing over 20,000 tonnes in air. was wet-towed from the construction site at Hanoytangen near Bergen to Heidrun Field where the main installation spread awaited. After initial surface hookup and ballasting through the waterline, each foundation was lowered to near seabed by controlled sluicing of water.
Title: The Heidrun Field - Marine Operations
Description:
ABSTRACT
The Heidrun Field development concept required an exceptional number of inshore and offshore marine operations to assemble the final product, Contained within the marine operations program were a number of innovations and advancements, such as subsea installation of heavy structures without the use of cranes, pre-installation of tethers, simultaneous leek-off of a TLP, and execution of pipeline bundle installation with a record tow length and water depth.
In addition, the size of the structures, the remote field location, and a diverless philosophy in relatively deep water (345m) also contributed to making theconduct of successful operations a challenge.
This paper describe the major offshore marine operations, including the tether foundation, tether, and TLP installations, as well as those for the export pipeline and direct shuttle loading systems, Highlights of the TLP template, water injection system, and TLP inshore operations are also briefly mentioned.
INTRODUCTION
Development of the Heidrun Field required an extensive effort in the area of marine operations.
The operations took place over three years, commencing with TLP pre-drilling template installation in August of 1992 and finishing with TLP installation in July 1995.
The most intense period of operations was the summer of 1994.
The total marine operations program comprised more than 130 main events (Table 1).
Supporting the operations were design, planning, contracting, and verification/testing activities, all coordinated by a Conoco Norway, Inc.
(CNI) Project marine group which.
at its peak, consisted of no more than 15 people.
The operations took place inshore, near-shore, and offshore.
A total of approximately 60 vessels of all types contributed, through seven main contractors and numerous subcontractors.
During the busy 1994 season, up to 14 vessels performing under several contracts were present simultaneously at Heidrun.
A clear system of priority and field control was set up by CNI to ensure that vessel clashes and contractor downtime were avoided.
Throughout the operations, safety of personnel and equipment was given prime focus, with the result that only two Lost Workday Cases, both of a minor nature, were experienced in three years of offshore marine work.
This paper presents a brief technical overview of the majoroffshore operations, including a description of success factors and difficulties encountered.
A layout of the Heidrun Field is contained in Figure 1.
TETHER FOUNDATIONS
The four tether foundations were installed in July 1994.
Their main particulars are given in Table 2, and their general arrangement is described in Reference 1 and Figure 2.
The installation of the tether foundations represented a significant breakthrough for installing large structures without the use of expensive heavy lift vessels.
Each foundation unit, weighing over 20,000 tonnes in air.
was wet-towed from the construction site at Hanoytangen near Bergen to Heidrun Field where the main installation spread awaited.
After initial surface hookup and ballasting through the waterline, each foundation was lowered to near seabed by controlled sluicing of water.
Related Results
The Concerns and Benefits of Standardization on the Heidrun Subsea Water Injection System
The Concerns and Benefits of Standardization on the Heidrun Subsea Water Injection System
Abstract
Ms paper describes the process of standarzing the Heidrun Sub sea water injection system. The layout, basis of design and equipment utilized are presente...
The Heidrun Field:Oil Offtake System
The Heidrun Field:Oil Offtake System
Abstract
Off take of oil from the Heidrun field is achieved through a Direct Shuttle Loading (DSL) system. This approach eliminates the need for an intermediate s...
Norne-Heidrun: Closing "The Loop" With Diverless Flanged Connections
Norne-Heidrun: Closing "The Loop" With Diverless Flanged Connections
Abstract
Subsea completions in deep waters are becoming more and more frequent around the world. This entails the use of innovative technology, remote interventio...
The Heidrun Field - Heidrun TLP Tether System
The Heidrun Field - Heidrun TLP Tether System
ABSTRACT
The Heidrun TLP was installed in July, 1995. The tether system was developed to meet the following requirements preinstall the tether strings before plat...
The Heidrun Field: Global Structural Design and Analysis of the Heidrun TLP
The Heidrun Field: Global Structural Design and Analysis of the Heidrun TLP
Abstract
The structural analysis and design of the Heidrun tension leg platform presented many technical Challenge a that had to be overcome in a fast and efficie...
The Heidrun Field - Development Overview
The Heidrun Field - Development Overview
ABSTRACT
Heidrun an oil and gas field lying in 345 meters of water off the coast of Norway. has been developed using the world's first concrete Tension Leg Platfo...
The Heidrun Field - Challenges in Resetvoir Development and Production
The Heidrun Field - Challenges in Resetvoir Development and Production
Abstract
Geological, reservoir and well-technology related challenges have been overcome in the planning and pre-drilling phases of Heidrun and, although addition...
Research on the dynamic co-evolution of the complex system of economy-innovation-environment of the marine industry in China
Research on the dynamic co-evolution of the complex system of economy-innovation-environment of the marine industry in China
IntroductionIn the context of accelerating the construction of a marine power, relying on scientific and technological innovation to drive the high-quality growth of the marine eco...

