Search engine for discovering works of Art, research articles, and books related to Art and Culture
ShareThis
Javascript must be enabled to continue!

TOGI Service Lines and Cable Installation: Concept Selection and Field Experience

View through CrossRef
ABSTRACT This paper presents the concept for the TOGI service lines and cable bundle used to provide hydraulic and electric power and chemical injection fluid for the TOGI Subsea Station. The paper also presents the fabrication and installation methods used and some of the technical challenges experienced during the fabrication and installation phases. The paper includes descriptions of MSV "Regalia" used as the laying vessel and the water jetting system CAPJET 500 used for trenching. INTRODUCTION The TOGI service lines and cable bundle consists of three 34 mm ID duplex steel service, and one 75 mm OD electrical cable. The length of the service lines and cable bundle is 48km equal to the distance between the Subsea Station at Troll and the Oseberg Field Center. The waterdepth at the end points is 303m and llOm, respectively. See Fig. 1. The four bundle elements were all prefabricated onshore in their full lengths and stored on three service line installation reels, and one carousel type basket for the cable. During the summer of 1990 the TOGI service lines and cable bundle were successfully installed between the TOGI Subsea Station and the Oseberg Field Centre. The laying and later trenching of the three duplex service lines and the electrical cable marked the completion of four years period of engineering, fabrication and installation efforts, starting with the conceptual engineering in mid 1986 and ending up with the fabrication and installation contract which in spring 1989 were awarded to Ugland Coflexip A/S (UCAS), a joint venture between Ugland Offshore and Coflexip Norge. The work included new installation methods and equipment not earlier used in the offshore pipeline industry. This paper is one in a series of six, which are presented at the OTC 1991. TOGI CONTROL BUNDLE CONCEPT The TOGI subsea wells are controled and monitored via a multiplexed electro-hydraulic system operated from the Oseberg A platform some 48 km away. The hydraulic supply and communication lines are gathered into a service line and cable bundle, consisting of three separate 34 mm ID duplex steel service lines and one 75 mm OD electrical cable, as shown in Fiq. 2. One of the service lines is used for chemical injection, and the other two for hydraulic pressure supply. The electrical power and signal cable consists of 12 pairs of conductor elements, where the control signals and power supply are transferred through common elements. The bundle concept was established in the basic engineering phase of the project, and the following principles were adopted for the specification of service lines:One dedicated high pressure line (345 bar) for the surface controlled subsurface safety valves (SCSSV's) and one separate medium pressure line (207 bar) for the X-mas tree valve functions.One chemical injection feeder line with distribution chokes to each tree.No hydraulic fluid return lines.No spare lines, neither for the chemical injection nor the hydraulic system.
Title: TOGI Service Lines and Cable Installation: Concept Selection and Field Experience
Description:
ABSTRACT This paper presents the concept for the TOGI service lines and cable bundle used to provide hydraulic and electric power and chemical injection fluid for the TOGI Subsea Station.
The paper also presents the fabrication and installation methods used and some of the technical challenges experienced during the fabrication and installation phases.
The paper includes descriptions of MSV "Regalia" used as the laying vessel and the water jetting system CAPJET 500 used for trenching.
INTRODUCTION The TOGI service lines and cable bundle consists of three 34 mm ID duplex steel service, and one 75 mm OD electrical cable.
The length of the service lines and cable bundle is 48km equal to the distance between the Subsea Station at Troll and the Oseberg Field Center.
The waterdepth at the end points is 303m and llOm, respectively.
See Fig.
1.
The four bundle elements were all prefabricated onshore in their full lengths and stored on three service line installation reels, and one carousel type basket for the cable.
During the summer of 1990 the TOGI service lines and cable bundle were successfully installed between the TOGI Subsea Station and the Oseberg Field Centre.
The laying and later trenching of the three duplex service lines and the electrical cable marked the completion of four years period of engineering, fabrication and installation efforts, starting with the conceptual engineering in mid 1986 and ending up with the fabrication and installation contract which in spring 1989 were awarded to Ugland Coflexip A/S (UCAS), a joint venture between Ugland Offshore and Coflexip Norge.
The work included new installation methods and equipment not earlier used in the offshore pipeline industry.
This paper is one in a series of six, which are presented at the OTC 1991.
TOGI CONTROL BUNDLE CONCEPT The TOGI subsea wells are controled and monitored via a multiplexed electro-hydraulic system operated from the Oseberg A platform some 48 km away.
The hydraulic supply and communication lines are gathered into a service line and cable bundle, consisting of three separate 34 mm ID duplex steel service lines and one 75 mm OD electrical cable, as shown in Fiq.
2.
One of the service lines is used for chemical injection, and the other two for hydraulic pressure supply.
The electrical power and signal cable consists of 12 pairs of conductor elements, where the control signals and power supply are transferred through common elements.
The bundle concept was established in the basic engineering phase of the project, and the following principles were adopted for the specification of service lines:One dedicated high pressure line (345 bar) for the surface controlled subsurface safety valves (SCSSV's) and one separate medium pressure line (207 bar) for the X-mas tree valve functions.
One chemical injection feeder line with distribution chokes to each tree.
No hydraulic fluid return lines.
No spare lines, neither for the chemical injection nor the hydraulic system.

Related Results

Reliability Management of Surface-Controlled Subsurface Safety Valves for the TOGI Project
Reliability Management of Surface-Controlled Subsurface Safety Valves for the TOGI Project
ABSTRACT This paper describes the combined efforts taken by Norsk Hydro and SINTEF on obtaining higher reliability of Surface Controlled Subsurface Safety Valves ...
TOGI Production Control System Challenges and Experiences
TOGI Production Control System Challenges and Experiences
ABSTRACT TOGI Production Control System is a multiplexed electrohydraulic system comprising features like acoustic sand and gas leak detectors. ...
TOGI Deepwater Gas Cluster Control Systems
TOGI Deepwater Gas Cluster Control Systems
ABSTRACT Development of the TOGI Project entails installation of a five well gas cluster on the Troll Field which will produce gas for injection into the Oseberg ...
At Sea Test: Hawaii Deepwater Cable Program
At Sea Test: Hawaii Deepwater Cable Program
ABSTRACT In order to investigate and demonstrate the technical feasibility of laying a Submarine power cable in the open ocean, in depths exceeding 6000 feet, ove...
Troll Oseberg Gas Injection (TOGI) Development
Troll Oseberg Gas Injection (TOGI) Development
ABSTRACT In 1986 the Oseberg partners decided to replace the planned water injection scheme by gas injection. Pressure maintenance by gas of the...
TOGI Subsea Station: Technical Overview
TOGI Subsea Station: Technical Overview
ABSTRACT The TOGI gas is produced from one subsea production station installed at 303 meter water depth in the Troll field. Initially 4 wells with a peak capacity...
TOGI: Multiphase Flow From Troll to Oseberg
TOGI: Multiphase Flow From Troll to Oseberg
ABSTRACT The TOGI 20" pipeline has been designed to transport unprocessed well fluid 48.5 Km from a subsea installation to an offshore production platform. ...
Deep Learning Training Model Construction and Optimization of Cable Size Features in 3D Point Cloud Data
Deep Learning Training Model Construction and Optimization of Cable Size Features in 3D Point Cloud Data
Cables are widely used in power transmission, and the measurement of key dimensions of cables is an indispensable part of the cable preparation process to help ensure their quality...

Back to Top