Javascript must be enabled to continue!
TOGI Subsea Station: Technical Overview
View through CrossRef
ABSTRACT
The TOGI gas is produced from one subsea production station installed at 303 meter water depth in the Troll field. Initially 4 wells with a peak capacity of 3.25 Sm3/day will deliver the required quantities of gas to the Oseberg field.
The TOGI subsea station has been designed for diverless installation and maintenance, and it is controlled from the Oseberg field over a distance of 48km.
This paper describes the TOGI Subsea Station layout and design philosophies. Experiences from the development of prototypes and from fabrication, testing and installation of the complete system are subsequently presented. Finally some ideas for future use of the TOGI technology are discussed.
INTRODUCTION
The decision taken in June 1986 to design, fabricate and install a unique subsea gas production system in the Troll field, represented at that time a major challenge for Norsk Hydro. Ideas, as listed below should then be transformed to prototypes and tested out in 303m water depth on live gas wells:Remote control and monitoring of subsea wells over a 48km distance with no surface support on the Troll field.Designing a subsea station where all active components are built into independently retrievable modules.Strict reliability requirements for all equipment permanently installed.All fluid supply to the subsea station through two hydraulic lines and one hydrate/corrosion inhibitor line. For special well kill purposes a kill hub installed within the manifold should be used, eliminating the need for a 48km kill line. Pressure bleed off by gas venting to the sea.Running of all the tools needed during installation/well completion operations by one common electrohydraulic intervention control system.All installations, including the pull-in and connection of a 20" pipeline to be performed without divers, only by assistance from tools and ROVIS remotely controlled from surface. This paper is one in a series of six which are presented at the OTC 1991.
SYSTEM LAY OUT AND DESIGN PHILOSOPHIES
Fig. 1 shows the TOGI P & ID. This drawing describes the system architecture in addition to the piping, valves and instrumentation. All connections between modules are made up by stroking the hubs horizontally after a retrievable seal plate has been landed in between the hubs. The seal plate is hanging in a hinged clamp. The retrievable modules sitting inside the 6 slot template structure that is piled to the sea bottom are the following:X-mas trees with individually retrievable control pods.Manifold module with production isolation valves (6"), gas header, chemical and hydraulic distribution headers with isolation valves, centrally located kill hub and cables for electrical distribution.Pig module with 12" and 20" isolation valves and with a hub for pig launcher connection. All the isolation valves are ROV operated. The chemical injection lines are routed via the control pods where an injection orifice with differential pressure measurement is included. For leak testing gas is vented through an orifice on the X-mas tree to the sea and pressure sensors in the production and annulus bores monitor any pressure build up.
Title: TOGI Subsea Station: Technical Overview
Description:
ABSTRACT
The TOGI gas is produced from one subsea production station installed at 303 meter water depth in the Troll field.
Initially 4 wells with a peak capacity of 3.
25 Sm3/day will deliver the required quantities of gas to the Oseberg field.
The TOGI subsea station has been designed for diverless installation and maintenance, and it is controlled from the Oseberg field over a distance of 48km.
This paper describes the TOGI Subsea Station layout and design philosophies.
Experiences from the development of prototypes and from fabrication, testing and installation of the complete system are subsequently presented.
Finally some ideas for future use of the TOGI technology are discussed.
INTRODUCTION
The decision taken in June 1986 to design, fabricate and install a unique subsea gas production system in the Troll field, represented at that time a major challenge for Norsk Hydro.
Ideas, as listed below should then be transformed to prototypes and tested out in 303m water depth on live gas wells:Remote control and monitoring of subsea wells over a 48km distance with no surface support on the Troll field.
Designing a subsea station where all active components are built into independently retrievable modules.
Strict reliability requirements for all equipment permanently installed.
All fluid supply to the subsea station through two hydraulic lines and one hydrate/corrosion inhibitor line.
For special well kill purposes a kill hub installed within the manifold should be used, eliminating the need for a 48km kill line.
Pressure bleed off by gas venting to the sea.
Running of all the tools needed during installation/well completion operations by one common electrohydraulic intervention control system.
All installations, including the pull-in and connection of a 20" pipeline to be performed without divers, only by assistance from tools and ROVIS remotely controlled from surface.
This paper is one in a series of six which are presented at the OTC 1991.
SYSTEM LAY OUT AND DESIGN PHILOSOPHIES
Fig.
1 shows the TOGI P & ID.
This drawing describes the system architecture in addition to the piping, valves and instrumentation.
All connections between modules are made up by stroking the hubs horizontally after a retrievable seal plate has been landed in between the hubs.
The seal plate is hanging in a hinged clamp.
The retrievable modules sitting inside the 6 slot template structure that is piled to the sea bottom are the following:X-mas trees with individually retrievable control pods.
Manifold module with production isolation valves (6"), gas header, chemical and hydraulic distribution headers with isolation valves, centrally located kill hub and cables for electrical distribution.
Pig module with 12" and 20" isolation valves and with a hub for pig launcher connection.
All the isolation valves are ROV operated.
The chemical injection lines are routed via the control pods where an injection orifice with differential pressure measurement is included.
For leak testing gas is vented through an orifice on the X-mas tree to the sea and pressure sensors in the production and annulus bores monitor any pressure build up.
Related Results
TOGI Production Control System Challenges and Experiences
TOGI Production Control System Challenges and Experiences
ABSTRACT
TOGI Production Control System is a multiplexed electrohydraulic system comprising features like acoustic sand and gas leak detectors.
...
Subsea Factory–Standardization of the Brownfield Factory
Subsea Factory–Standardization of the Brownfield Factory
Abstract
As part of the corporate technology strategy Statoil has launched a technology plan for the Subsea Factory concept. The plan describes how to combine subsea...
Troll Oseberg Gas Injection (TOGI) Development
Troll Oseberg Gas Injection (TOGI) Development
ABSTRACT
In 1986 the Oseberg partners decided to replace the planned water injection scheme by gas injection.
Pressure maintenance by gas of the...
Ormen Lange Subsea Production System
Ormen Lange Subsea Production System
Abstract
This paper presents the concept and the technical solutions developed and applied to the Ormen Lange subsea production system. First, the key technical c...
High Voltage Subsea Pump – A Low Cost Subsea Boosting Enabler
High Voltage Subsea Pump – A Low Cost Subsea Boosting Enabler
In a cost constrained scenario, technology driven solutions aiming at CAPEX reductions are crucial to make Subsea Processing (SSP) projects economically attractive. Subsea Processi...
Technology Focus: Subsea Systems (August 2025)
Technology Focus: Subsea Systems (August 2025)
_
From a broader and high-level perspective—considering importance, impact, significance, and criticality—subsea systems and advanced offshore engineering play an...
Subsea Facilities
Subsea Facilities
Abstract
This paper presents the system design and concept solutions selected for the Ormen Lange subsea facilities.
The field is located in a r...
TOGI: Multiphase Flow From Troll to Oseberg
TOGI: Multiphase Flow From Troll to Oseberg
ABSTRACT
The TOGI 20" pipeline has been designed to transport unprocessed well fluid 48.5 Km from a subsea installation to an offshore production platform.
...

