Search engine for discovering works of Art, research articles, and books related to Art and Culture
ShareThis
Javascript must be enabled to continue!

TOGI Production Control System Challenges and Experiences

View through CrossRef
ABSTRACT TOGI Production Control System is a multiplexed electrohydraulic system comprising features like acoustic sand and gas leak detectors. The system detailed design was presented at the annual OTC in Houston, May 1989. The TOGI scenario included challenges like:large offset from existing infrastructure (48 km)relatively deep waters (305 m)extensive monitoring requirements (sand detection and gas leak detection) Extensive development of new equipment and qualification of existing equipment was required. Even though we have experienced some difficulties in the manufacturing test and installation phase, the equipment was installed on schedule, within budget, and performing according to the requirements. The success of TOGI has set new standards for development of control systems for subsea production systems. INTRODUCTION TOGI Production Control System (PCS) must be regarded as an unique and relative complex control system. This as a result of:the inherent risk and cost involved when retrieving the large manifold module led to the decision to keep this module free of active components/equipment i.e. distributed functions.a challenging scenario with deep waters and large offset from existing infrastructure.redundancy requirements to reduce the probability for a needed intervention.specific monitoring requirements, such as sand detection, gas leak detection and requirements for very accurate well head production pressure monitoring (no downhole monitoring installed on TOGI). A simplified sketch indicating the main parts of the PCS is presented in fig. 01 as a reference for the discussions in the paper. The experiences so far are that the challenges have been solved and that the problems encountered were not larger than expected. There are however areas that could be improved to reduce the problems and consequently cost even further. The novelty and complexity of the system were the main contributing factors when the test strategy for the PCS was defined. The test program was defined to ensure that all subsystems and interfaces were tested prior to installation. In addition a commissioning program were defined to ensure correct installation prior to start up. This paper is one in a series of six which are presented at the OTC 1991. CHALLENGES AND EXPERIENCES There where numerous challenges when designing the TOGI Production Control System (PCS). Power and signal transmission Transfer of power and signal over 48 km had no track record in the business, and hence the system had to be customised for TOGI. The system was designed with signals superimposed on power lines. Such design requires filter systems which are very important both for signal transfer (impedance matching) and power transfer (power factor). Superimposing signals on power lines is a well proven technology, although it was not to our knowledge utilised on any subsea applications before TOGI. Because of this none of the potential contractors had systems that could meet our specifications. In order to reduce the inherent problems like crosstalk, attenuation and low signal/noise ratio, very strict requirements were given to the manufacturer of the electrical cable. As part of the development work a 50 km test core was manufactured.
Title: TOGI Production Control System Challenges and Experiences
Description:
ABSTRACT TOGI Production Control System is a multiplexed electrohydraulic system comprising features like acoustic sand and gas leak detectors.
The system detailed design was presented at the annual OTC in Houston, May 1989.
The TOGI scenario included challenges like:large offset from existing infrastructure (48 km)relatively deep waters (305 m)extensive monitoring requirements (sand detection and gas leak detection) Extensive development of new equipment and qualification of existing equipment was required.
Even though we have experienced some difficulties in the manufacturing test and installation phase, the equipment was installed on schedule, within budget, and performing according to the requirements.
The success of TOGI has set new standards for development of control systems for subsea production systems.
INTRODUCTION TOGI Production Control System (PCS) must be regarded as an unique and relative complex control system.
This as a result of:the inherent risk and cost involved when retrieving the large manifold module led to the decision to keep this module free of active components/equipment i.
e.
distributed functions.
a challenging scenario with deep waters and large offset from existing infrastructure.
redundancy requirements to reduce the probability for a needed intervention.
specific monitoring requirements, such as sand detection, gas leak detection and requirements for very accurate well head production pressure monitoring (no downhole monitoring installed on TOGI).
A simplified sketch indicating the main parts of the PCS is presented in fig.
01 as a reference for the discussions in the paper.
The experiences so far are that the challenges have been solved and that the problems encountered were not larger than expected.
There are however areas that could be improved to reduce the problems and consequently cost even further.
The novelty and complexity of the system were the main contributing factors when the test strategy for the PCS was defined.
The test program was defined to ensure that all subsystems and interfaces were tested prior to installation.
In addition a commissioning program were defined to ensure correct installation prior to start up.
This paper is one in a series of six which are presented at the OTC 1991.
CHALLENGES AND EXPERIENCES There where numerous challenges when designing the TOGI Production Control System (PCS).
Power and signal transmission Transfer of power and signal over 48 km had no track record in the business, and hence the system had to be customised for TOGI.
The system was designed with signals superimposed on power lines.
Such design requires filter systems which are very important both for signal transfer (impedance matching) and power transfer (power factor).
Superimposing signals on power lines is a well proven technology, although it was not to our knowledge utilised on any subsea applications before TOGI.
Because of this none of the potential contractors had systems that could meet our specifications.
In order to reduce the inherent problems like crosstalk, attenuation and low signal/noise ratio, very strict requirements were given to the manufacturer of the electrical cable.
As part of the development work a 50 km test core was manufactured.

Related Results

Troll Oseberg Gas Injection (TOGI) Development
Troll Oseberg Gas Injection (TOGI) Development
ABSTRACT In 1986 the Oseberg partners decided to replace the planned water injection scheme by gas injection. Pressure maintenance by gas of the...
TOGI Subsea Station: Technical Overview
TOGI Subsea Station: Technical Overview
ABSTRACT The TOGI gas is produced from one subsea production station installed at 303 meter water depth in the Troll field. Initially 4 wells with a peak capacity...
TOGI: Multiphase Flow From Troll to Oseberg
TOGI: Multiphase Flow From Troll to Oseberg
ABSTRACT The TOGI 20" pipeline has been designed to transport unprocessed well fluid 48.5 Km from a subsea installation to an offshore production platform. ...
GUA TOGI BOGI, HUNIAN BERCIRI MESOLITIK DI NIAS (PERBANDINGAN DENGAN SITUS GUA TOGI NDRAWA)
GUA TOGI BOGI, HUNIAN BERCIRI MESOLITIK DI NIAS (PERBANDINGAN DENGAN SITUS GUA TOGI NDRAWA)
Togi Bogi's one of the caves which located up to the hill around 75 metres from the surface of the sea. There was also an archaeological remains such as artefact and ecofact inside...
Nonlinear optimal control for robotic exoskeletons with electropneumatic actuators
Nonlinear optimal control for robotic exoskeletons with electropneumatic actuators
Purpose To provide high torques needed to move a robot’s links, electric actuators are followed by a transmission system with a high transmission rate. For instance, gear ratios of...
TOGI Pull-In and Connection Systems
TOGI Pull-In and Connection Systems
ABSTRACT A unique and prototype pull-in and connection system were developed for the TOGI project. The offshore pull-in of the 20" pipeline and service lines and ...
Teoria kontroli społecznej w kryminologii
Teoria kontroli społecznej w kryminologii
                "Social control" is one of thę most fundamental  concepts in sociology. Nevertheless, the meaning of that term has changed, parallel with the development of sociolo...
Application of Seismic Data and Sequence Stratigraphy for Constraining a Stochastic Model of Calcite Cementation
Application of Seismic Data and Sequence Stratigraphy for Constraining a Stochastic Model of Calcite Cementation
Abstract Calcite cemented sandstone layers are common heterogeneities in shallow marine reservoirs where they cause significant flow barriers. Field analogue studies...

Back to Top