Bonga FPSO: Asset Management Excellence
View through CrossRef
Abstract
Bonga field is located 120 km South-West of Warri, in the Southern Niger Delta of Nigeria, at water depth of 3300 ft. The field was discovered in 1993 and achieved first oil in November 2005 as the first deepwater development in the Gulf of Guinea. It was developed with subsea wells, production manifolds and water injection terminals connected via subsea flowlines and risers to a Floating Production, Storage and Offloading (FPSO) facility called the Bonga FPSO.
Bonga FPSO consists of oil and gas processing and export facilities, water injection facilities, oil storage facilities, and utility systems that support production operations and personnel onboard the vessel. Over a 17-year period, the FPSO has achieved cumulative oil production of 1.0 billion barrels, 815 Bscf of gas export and 1.5 billion barrels of water injected through a total 39 oil producer and 36 water injector wells.
This performance was delivered by disciplined implementation of a structured Asset Management framework with focus on work processes that deliver performance, a management system that define how the asset operates, and clear definition of the assets longer-term strategic intent, vision, value levers, and the choices required to deliver maximum business value.
Through the asset management framework, the FPSO has consistently delivered top quartile performance in safety and environment, production availability, asset integrity, equipment reliability, and turn around excellence. In 2022 the asset delivered a turnaround maintenance 8 days ahead of schedule with zero safety incident at a lower cost. In February 2023, Bonga achieved cumulative export of 1 billion barrels of oil and 815 Bscf of gas, and cumulative water injection of 1.5 billion barrels. The asset is on track to deliver a production availability greater 95% and a carbon emission reduction of 0.3million tCO2e through reliability improvements on gas compression system.
This paper presents the Asset Management excellence philosophy of Bonga FPSO
Ensure Safe Production: A structured process that enables cost-effective operation within defined operating envelopes. Manage Threats and Opportunities: A process that enables identification, prioritization and mitigation of threats and realization of opportunities. Perform Maintenance Execution and Manage Equipment care: Two frameworks for maintaining and improving the integrity, availability, and reliability of the asset through optimized maintenance strategies. Perform Turnaround: A structured framework to effectively plan, schedule, control and execute turnarounds to improve operational excellence and asset integrity.
This paper is one of a series of Bonga themed papers proposed for OTC 2024.
Title: Bonga FPSO: Asset Management Excellence
Description:
Abstract
Bonga field is located 120 km South-West of Warri, in the Southern Niger Delta of Nigeria, at water depth of 3300 ft.
The field was discovered in 1993 and achieved first oil in November 2005 as the first deepwater development in the Gulf of Guinea.
It was developed with subsea wells, production manifolds and water injection terminals connected via subsea flowlines and risers to a Floating Production, Storage and Offloading (FPSO) facility called the Bonga FPSO.
Bonga FPSO consists of oil and gas processing and export facilities, water injection facilities, oil storage facilities, and utility systems that support production operations and personnel onboard the vessel.
Over a 17-year period, the FPSO has achieved cumulative oil production of 1.
0 billion barrels, 815 Bscf of gas export and 1.
5 billion barrels of water injected through a total 39 oil producer and 36 water injector wells.
This performance was delivered by disciplined implementation of a structured Asset Management framework with focus on work processes that deliver performance, a management system that define how the asset operates, and clear definition of the assets longer-term strategic intent, vision, value levers, and the choices required to deliver maximum business value.
Through the asset management framework, the FPSO has consistently delivered top quartile performance in safety and environment, production availability, asset integrity, equipment reliability, and turn around excellence.
In 2022 the asset delivered a turnaround maintenance 8 days ahead of schedule with zero safety incident at a lower cost.
In February 2023, Bonga achieved cumulative export of 1 billion barrels of oil and 815 Bscf of gas, and cumulative water injection of 1.
5 billion barrels.
The asset is on track to deliver a production availability greater 95% and a carbon emission reduction of 0.
3million tCO2e through reliability improvements on gas compression system.
This paper presents the Asset Management excellence philosophy of Bonga FPSO
Ensure Safe Production: A structured process that enables cost-effective operation within defined operating envelopes.
Manage Threats and Opportunities: A process that enables identification, prioritization and mitigation of threats and realization of opportunities.
Perform Maintenance Execution and Manage Equipment care: Two frameworks for maintaining and improving the integrity, availability, and reliability of the asset through optimized maintenance strategies.
Perform Turnaround: A structured framework to effectively plan, schedule, control and execute turnarounds to improve operational excellence and asset integrity.
This paper is one of a series of Bonga themed papers proposed for OTC 2024.
Related Results
Competitive CVAR-FPSO concepts with Dry trees in ultra-deepwater; Weathervaning CVAR-FPSO for Brazil and Indonesia vs. Non-weathervaning for West Africa
Competitive CVAR-FPSO concepts with Dry trees in ultra-deepwater; Weathervaning CVAR-FPSO for Brazil and Indonesia vs. Non-weathervaning for West Africa
Abstract
A new FPSO concept termed CVAR-FPSO is under development by a JNOC headed Joint Industry Project (JIP). The concept, using Compliant Vertical Access Rise...
Bonga Main Life Extension Project: An In-Situ Life Extension of an FPSO Using FAIR+ER Methodology and Digital Twin Technology as Basis for Scope Identification and Definition
Bonga Main Life Extension Project: An In-Situ Life Extension of an FPSO Using FAIR+ER Methodology and Digital Twin Technology as Basis for Scope Identification and Definition
Abstract
Production commenced in 2005 from the Bonga Main Field, which is a Floating Production Storage and Offloading (FPSO) + subsea development situated in betwee...
FPSO EIS Results and Record of Decision
FPSO EIS Results and Record of Decision
Abstract
The United States Department of the Interior (DOI), Minerals Management Service (MMS) prepared an environmental impact statement (EIS)1 to evaluate poten...
The Challenges and Opportunities of FPSO Relocations
The Challenges and Opportunities of FPSO Relocations
Abstract
The first FPSO relocation project was completed 18 years ago (SBM's FPSO II), and since that time there has been a steady rise in the number and complexi...
FPSO's Today: What is the Optimum Concept?
FPSO's Today: What is the Optimum Concept?
ABSTRACT
FPSO technology over the past years has rapidly evolved from tanker based units with classical mooring systems to purpose-shaped new built vessels equipp...
The Sanha LPG FPSO
The Sanha LPG FPSO
Abstract
The FPSO industry will soon have the first LPG FPSO in operation. The SANHA LPG FPSO is the first gas related FPSO. With the installation of the LPG FPSO...
Bonga Northwest Subsurface Development – Planning, Execution and Uncertainty Management
Bonga Northwest Subsurface Development – Planning, Execution and Uncertainty Management
The Bonga North West (BNW) field is located in Shell operated Oil Mining Lease (OML) 118, a deepwater development in Nigeria. This paper presents the BNW subsurface development str...
Bonga-Flow Assurance Benchmarking via Field Surveillance
Bonga-Flow Assurance Benchmarking via Field Surveillance
Abstract
Bonga - the first Deepwater development in Nigeria - commenced production in Q4 2005. At an early stage of the project, flow assurance was identified a...