Application of earned value method and earned schedule method for a residential apartment
View through CrossRef
Abstract
Earned Schedule Management (ESM) gives an estimate of schedule and milestone achievement dates. Earned Value Management (EVM) assists to follow the project performance by giving the schedule variance, cost variance and their performance index. EVM &ESM helps the project manager to foresee cost and schedule for the real project. The objective of this study is to apply EVM & ESM to the real time residential apartment project which is upcoming in Bengaluru, Karnataka, India and then to compare the results of two deterministic forecasting methods EVM and ESM. The EVM and ESM parameters are generated by using the data procured from the planning department. It shows much fluctuation in the project performance but the last months (M10) results reveal that the project is behind schedule, unfavorable budget and needs more amelioration. The project has an unfavorable Cost Variance of -0.91(budget in crores of INR, 1 crore = 10millions)) and schedule variance of -6.71months. It is also observed from the results and actual project situations that Earned Value and Earned Schedule methods in conjunction gives more accurate interpretation than using each of them detachedly.
Title: Application of earned value method and earned schedule method for a residential apartment
Description:
Abstract
Earned Schedule Management (ESM) gives an estimate of schedule and milestone achievement dates.
Earned Value Management (EVM) assists to follow the project performance by giving the schedule variance, cost variance and their performance index.
EVM &ESM helps the project manager to foresee cost and schedule for the real project.
The objective of this study is to apply EVM & ESM to the real time residential apartment project which is upcoming in Bengaluru, Karnataka, India and then to compare the results of two deterministic forecasting methods EVM and ESM.
The EVM and ESM parameters are generated by using the data procured from the planning department.
It shows much fluctuation in the project performance but the last months (M10) results reveal that the project is behind schedule, unfavorable budget and needs more amelioration.
The project has an unfavorable Cost Variance of -0.
91(budget in crores of INR, 1 crore = 10millions)) and schedule variance of -6.
71months.
It is also observed from the results and actual project situations that Earned Value and Earned Schedule methods in conjunction gives more accurate interpretation than using each of them detachedly.
Related Results
PERHITUNGAN DURASI PROYEK JALAN TOL DENGAN METODE EARNED SCHEDULE
PERHITUNGAN DURASI PROYEK JALAN TOL DENGAN METODE EARNED SCHEDULE
The slower-than-anticipated progress of construction projects is a common complaint in Indonesia. Several methods have been developed to address this issue, and the Earned Schedule...
De gevel – een intermediair element tussen buiten en binnen
De gevel – een intermediair element tussen buiten en binnen
This study is based on the fact that all people have a basic need for protection from other people (and animals) as well as from the elements (the exterior climate). People need a ...
ANALISIS FAKTOR PERFORMA DENGAN METODE EARNED SCHEDULE
ANALISIS FAKTOR PERFORMA DENGAN METODE EARNED SCHEDULE
Every construction project contains a project implementation plan from the beginning to the end of the project. A proven method to determine the estimated project duration is the e...
AN EVALUATION OF APARTMENT DESIGN FLEXIBILITY PERTAINING TO APARTMENT AFFORDABILITY IN LSDPC ESTATES, LAGOS, NIGERIA
AN EVALUATION OF APARTMENT DESIGN FLEXIBILITY PERTAINING TO APARTMENT AFFORDABILITY IN LSDPC ESTATES, LAGOS, NIGERIA
Affordability of apartment design began with incorporation of flexibility attributes into the apartment design to accommodate the biosocial life of the urban dwellers. There was no...
Half of all out-of-hospital cardiac arrests in public occur in residential areas with lower rates of bystander intervention and survival
Half of all out-of-hospital cardiac arrests in public occur in residential areas with lower rates of bystander intervention and survival
Abstract
Background
Impressive survival rates have been achieved for public out-of-hospital cardiac arrest (OHCA) in selected ar...
Apartment Layouts of Social Housing for Tomsk Architecture
Apartment Layouts of Social Housing for Tomsk Architecture
Apartment layouts define the types of residential cells and their correlation with a multiapartment residential building or residential development. It is one of the main parameter...
Customer’s Perception on Building Management Systems in Residential Complexes at Chennai
Customer’s Perception on Building Management Systems in Residential Complexes at Chennai
Customers should aware about the building management system (BMS) and their requirements based on the location of the apartment, type of the apartment and number of floors in the a...
Study of factors influencing apartment prices in Prishtina, Kosovo
Study of factors influencing apartment prices in Prishtina, Kosovo
Purpose
The purpose of this study is to identify which are the main factors influencing the apartment prices in Prishtina, the capital of Kosovo, during the period 2018–2020. The f...