Search engine for discovering works of Art, research articles, and books related to Art and Culture
ShareThis
Javascript must be enabled to continue!

Installation of Fleet Moorings at Diego Garcia, B.I.O.T.

View through CrossRef
Abstract The installation of fleet moorings when using propellant embedment anchors is presented. Specifically, the installation of eleven fleet moorings-at the Diego Garcia coral atoll in the Indian Ocean is discussed, since this represents the largest use of propellant embedment anchors to date. The moorings themselves are original in their design and are described in terms of component size. seventeen mooring buoys and 88 legs of chain wereinstalled to produce these eleven moorings. Installation equipment and installation procedures are presented, explaining the anchor-first, buoy-last construction method. Background associated with prediction of anchor performance is used to assist in understanding performance and data produced by the actual use of propellant embedment anchors for this project. The 88 successful propellant embedment anchors installed provided designed holding capacities of 100,000 Ibs each (28 anchors) and 150,0001bs each (60 anchors) at a cost of only $10K - $15K for expendable materials per anchor using a total package for each anchor shot that had a deck load of less-than 15,000 Ibs. Each anchor was load tested vertically to its full design load. The data associated with the load tests and the eight anchors which pulled out during load testing is presented along with required solutions to pullout problems. The Fleet Mooring Project demonstrated the mobility and positive utility of propellant embedment anchors for a coralline seafloor similar to that found at Diego Garcia. Supporting data is presented, including results of load tests of some other 100,000 Ib propellant embedment anchors which held over 200,000 Ibs of vertical force after five years in the seafloor at Uiego Garcia. Introduction On 31 March, 1980, the Chesapeake Division, Naval Facilities Engineering Command, was tasked toprovide engineering and construction support for the design, procurement and installation of eleven fleet moorings in the lagoon at Diego Garcia, British Indian Ocean Territories. Diego Garcia is a coral atoll found in the Chagos Archipelago chain of islands in the middle of the Indian Ocean approximately 70 below the equator. These moorings were urgently required by the Commander-in-Chief, Pacific Fleet, and installation was completed 17 March, 1981. Due to the extremely rapid response required, maximum use was made of existing Navy inventories of chain and other mooring materials stockpiled on both coasts of the United States as well as at various overseas locations. Mooring designs and installation procedures were tailored to make use of these on-hand materials as well as anchoring methods previously shown to be satisfactory for the coralline seafloor found at Diego Garcia. The propellant embedment anchor (PEA) developed by the Naval Civil Engineering Laboratory was selected for use with these moorings due to its proven success on three previous buoy installation projects in the Diego Garcia lagoon. Traditional drag weight anchors were not determined to be the best choice for long term anchoring of moorings in the lagoon's coralline seafloor. The eleven moorings as designed by the Chesapeake Division's Ocean Engineering and Construction Project Office (FPO-1) required the use of seventeen mooring buoys and 88 legs of chain.
Title: Installation of Fleet Moorings at Diego Garcia, B.I.O.T.
Description:
Abstract The installation of fleet moorings when using propellant embedment anchors is presented.
Specifically, the installation of eleven fleet moorings-at the Diego Garcia coral atoll in the Indian Ocean is discussed, since this represents the largest use of propellant embedment anchors to date.
The moorings themselves are original in their design and are described in terms of component size.
seventeen mooring buoys and 88 legs of chain wereinstalled to produce these eleven moorings.
Installation equipment and installation procedures are presented, explaining the anchor-first, buoy-last construction method.
Background associated with prediction of anchor performance is used to assist in understanding performance and data produced by the actual use of propellant embedment anchors for this project.
The 88 successful propellant embedment anchors installed provided designed holding capacities of 100,000 Ibs each (28 anchors) and 150,0001bs each (60 anchors) at a cost of only $10K - $15K for expendable materials per anchor using a total package for each anchor shot that had a deck load of less-than 15,000 Ibs.
Each anchor was load tested vertically to its full design load.
The data associated with the load tests and the eight anchors which pulled out during load testing is presented along with required solutions to pullout problems.
The Fleet Mooring Project demonstrated the mobility and positive utility of propellant embedment anchors for a coralline seafloor similar to that found at Diego Garcia.
Supporting data is presented, including results of load tests of some other 100,000 Ib propellant embedment anchors which held over 200,000 Ibs of vertical force after five years in the seafloor at Uiego Garcia.
Introduction On 31 March, 1980, the Chesapeake Division, Naval Facilities Engineering Command, was tasked toprovide engineering and construction support for the design, procurement and installation of eleven fleet moorings in the lagoon at Diego Garcia, British Indian Ocean Territories.
Diego Garcia is a coral atoll found in the Chagos Archipelago chain of islands in the middle of the Indian Ocean approximately 70 below the equator.
These moorings were urgently required by the Commander-in-Chief, Pacific Fleet, and installation was completed 17 March, 1981.
Due to the extremely rapid response required, maximum use was made of existing Navy inventories of chain and other mooring materials stockpiled on both coasts of the United States as well as at various overseas locations.
Mooring designs and installation procedures were tailored to make use of these on-hand materials as well as anchoring methods previously shown to be satisfactory for the coralline seafloor found at Diego Garcia.
The propellant embedment anchor (PEA) developed by the Naval Civil Engineering Laboratory was selected for use with these moorings due to its proven success on three previous buoy installation projects in the Diego Garcia lagoon.
Traditional drag weight anchors were not determined to be the best choice for long term anchoring of moorings in the lagoon's coralline seafloor.
The eleven moorings as designed by the Chesapeake Division's Ocean Engineering and Construction Project Office (FPO-1) required the use of seventeen mooring buoys and 88 legs of chain.

Related Results

Death following pulmonary complications of surgery before and during the SARS-CoV-2 pandemic
Death following pulmonary complications of surgery before and during the SARS-CoV-2 pandemic
Abstract Background This study aimed to determine the impact of pulmonary complications on death after surgery both before and d...
Development of an Engineers' Design Guide for Deepwater Fiber Moorings
Development of an Engineers' Design Guide for Deepwater Fiber Moorings
Abstract Various operators are currently pioneering the use of synthetic fiber ropes for mooring platforms in deepwater. The first systems were installed in 1997 ...
Analisis Pemanfaatan Fleet Terhadap Produksi OB Removal di PT Bara Energi Lestari, Nagan Raya, Aceh
Analisis Pemanfaatan Fleet Terhadap Produksi OB Removal di PT Bara Energi Lestari, Nagan Raya, Aceh
Kegiatan operasi-produksi OB Removal di lokasi penelitian pada Bulan Maret 2024 mengalami ketidaktercapaian dengan hasil produksi OB Removal sebesar 660.961,56 bcm dari rencana seb...
Effective monitoring of vehicle utilization : a case study of eThekwini Municipality FMSs
Effective monitoring of vehicle utilization : a case study of eThekwini Municipality FMSs
The effective monitoring of vehicle utilisation in real time in the eThekwini Municipality pose a challenge in service delivery. There is no linkage between the service that is bei...
Mooring summary 1967
Mooring summary 1967
This report lists the moorings set in the 1967 which were not included in the "Surface Moorings, a Review of Performance" by H. Bertequx (1968). It includes 5 gasoline float moorin...
Independence Installation
Independence Installation
Abstract This Session paper will review the planning, preparation, and execution of the installation of the Independence Hub facility in Mississippi Canyon Block ...
SS: Spar Technology- Developments in Deepwater spar installation
SS: Spar Technology- Developments in Deepwater spar installation
Abstract During the last seven years Heerema Marine Contractors (HMC) has installed more than half of all Spars in the deep waters of the Gulf of Mexico. The dual...
Gryphon Alpha FPSO - Experience Gained During Moorings Replacement and Hook-Up
Gryphon Alpha FPSO - Experience Gained During Moorings Replacement and Hook-Up
Abstract In a North Sea storm during February 2011 the Gryphon Alpha FPSO broke four of her 10 mooring lines and moved partially off station, causing damage to su...

Back to Top