Search engine for discovering works of Art, research articles, and books related to Art and Culture
ShareThis
Javascript must be enabled to continue!

Monitoring of Beryl 'B' Platform Response to Pile Driving

View through CrossRef
ABSTRACT A monitoring program for investigation of jacket vibrations induced by plle driving on the Beryl 'B' platform in the North Sea is described. The objective of the program was to establish whether dynamic loads generated by large pile hammers could be damaging to various critical parts of the jacket or jacket appurtenances. Of particular concern were stress levels developed in pile sleeve-to-jacket connections, anode connections, and grout lines. Accelerometers were installed on pile sleeves and jacket legs prior to launch with a hardwire connection to deck level. After the jacket was mated to a subsea template, connections were completed to monitoring equipment aboard the vessel which tended the installation. Acceleration time histories from each of the measurement points were recorded during a test drive which employed the MRBS 12500 steam hammer on one- sleeve and the MHU1700 underwater hammer on the adjacent sleeve. Implications of the data in terms of current design practice are discussed. INTRODUCTION The Beryl ' ' platform is a fixed steel structure that was installed at a 120m (394 ft.) water depth location in Block 9/13 of the British sector of the North Sea during 1983. As described by Lenihan, et. al. (1984), the jacket was installed in record time, including time spent mating the jacket to a subsea template and driving the piling. Two pile driving systems were available during the installation. The first consisted of a series of steam hammers, operated above water, which drove the piles through followers. The largest available steam hammer was the Menck MRBS 12500. The second pile driving system utilized the Menck MHU 1700 hydraulic hammer. This hammer could operate underwater and drove the piles directly without the need of followers. The mechanical design and performance characteristics of these hammers have been documented by Heerema (1980). Prior to installation, there was concern that vibrations caused by the pile driving operation might reduce the life of connections between the jacket leg and pile sleeve and possibly overload certain appurtenance connections such as anode supports. This concern was supported by circumstantial evidence from two other recent North Sea installations that reportedly experienced anode support damage and grout packer failure as a result of stresses induced during pile installation. Two factors specific to the Beryl IBI installation suggested that the effects of pile driving vibrations should be seriously evaluated:Difficult pile driving with two of the world's largest hammers was expected due to heavily overconso1idated soils and the relatively large pile size of 1.83m (72 in.) diameter by 63.5mm (3 in.) wall thickness, andthe jacket would experience a large number of load cycles produced by the pile driving process since the foundation consisted of seven skirt piles on each of four jacket legs.
Title: Monitoring of Beryl 'B' Platform Response to Pile Driving
Description:
ABSTRACT A monitoring program for investigation of jacket vibrations induced by plle driving on the Beryl 'B' platform in the North Sea is described.
The objective of the program was to establish whether dynamic loads generated by large pile hammers could be damaging to various critical parts of the jacket or jacket appurtenances.
Of particular concern were stress levels developed in pile sleeve-to-jacket connections, anode connections, and grout lines.
Accelerometers were installed on pile sleeves and jacket legs prior to launch with a hardwire connection to deck level.
After the jacket was mated to a subsea template, connections were completed to monitoring equipment aboard the vessel which tended the installation.
Acceleration time histories from each of the measurement points were recorded during a test drive which employed the MRBS 12500 steam hammer on one- sleeve and the MHU1700 underwater hammer on the adjacent sleeve.
Implications of the data in terms of current design practice are discussed.
INTRODUCTION The Beryl ' ' platform is a fixed steel structure that was installed at a 120m (394 ft.
) water depth location in Block 9/13 of the British sector of the North Sea during 1983.
As described by Lenihan, et.
al.
(1984), the jacket was installed in record time, including time spent mating the jacket to a subsea template and driving the piling.
Two pile driving systems were available during the installation.
The first consisted of a series of steam hammers, operated above water, which drove the piles through followers.
The largest available steam hammer was the Menck MRBS 12500.
The second pile driving system utilized the Menck MHU 1700 hydraulic hammer.
This hammer could operate underwater and drove the piles directly without the need of followers.
The mechanical design and performance characteristics of these hammers have been documented by Heerema (1980).
Prior to installation, there was concern that vibrations caused by the pile driving operation might reduce the life of connections between the jacket leg and pile sleeve and possibly overload certain appurtenance connections such as anode supports.
This concern was supported by circumstantial evidence from two other recent North Sea installations that reportedly experienced anode support damage and grout packer failure as a result of stresses induced during pile installation.
Two factors specific to the Beryl IBI installation suggested that the effects of pile driving vibrations should be seriously evaluated:Difficult pile driving with two of the world's largest hammers was expected due to heavily overconso1idated soils and the relatively large pile size of 1.
83m (72 in.
) diameter by 63.
5mm (3 in.
) wall thickness, andthe jacket would experience a large number of load cycles produced by the pile driving process since the foundation consisted of seven skirt piles on each of four jacket legs.

Related Results

Analysis Of Three-Dimensional Pile Groups With Nonlinear Soil Response And Pile-Soil-Pile Interaction
Analysis Of Three-Dimensional Pile Groups With Nonlinear Soil Response And Pile-Soil-Pile Interaction
ABSTRACT Present methods of pile group analysis are either limited to special geometric cases or do not consider pile-soil-pile interaction. An analytical procedu...
Model Test of Jacked Pile Penetration Process Considering Influence of Pile Diameter
Model Test of Jacked Pile Penetration Process Considering Influence of Pile Diameter
In order to investigate the influence of different diameters on pile end resistance, pile side resistance, pile axial force and pile force transmission law of jacked pile penetrati...
Pile Driving Measurements On The Heather Platform Installation
Pile Driving Measurements On The Heather Platform Installation
Abstract The first leg piles of the Heather Platform were instrumented using strain transducers and accelerometers that were attached to the pile just below its t...
Simplified Heat Transfer Model for Spiral‐Coil Energy Pile Groups and the Pile–Pile Thermal Interference
Simplified Heat Transfer Model for Spiral‐Coil Energy Pile Groups and the Pile–Pile Thermal Interference
ABSTRACTThe spiral heat exchanger of the energy pile groups is divided into multiple segments. Each heat exchanger segment is regarded as a three‐dimensional spiral heat source of ...
Development Of The Beryl A Field
Development Of The Beryl A Field
Abstract Development drilling from the Beryl 'A' Platform has been in progress for over two years. A total of twelve wells nave been completed with two more neari...
Pile–Soil Interaction and Group Pile Effect in Composite Foundation Under Different Pile Length Conditions
Pile–Soil Interaction and Group Pile Effect in Composite Foundation Under Different Pile Length Conditions
With the rapid development of urbanization and infrastructure construction, the requirements for the foundation design of high-rise buildings and large bridges are increasing. Pile...
Contact between Prefabricated Pile and Pile Clamping Jaws under Pile Driving
Contact between Prefabricated Pile and Pile Clamping Jaws under Pile Driving
Pile clamping mechanism with hydraulic static pile driver has advantages of convenient for the design, improvement and use. The maximum transmission pile driving force of pile clam...
Underwater Pile Driving Test Offshore Louisiana
Underwater Pile Driving Test Offshore Louisiana
ABSTRACT This report presents results of an underwater pile driving test conducted at South Marsh Island Block 130, offshore Louisiana. A 24inch diameter tubular ...

Back to Top