Search engine for discovering works of Art, research articles, and books related to Art and Culture
ShareThis
Javascript must be enabled to continue!

Underwater Pile Driving Test Offshore Louisiana

View through CrossRef
ABSTRACT This report presents results of an underwater pile driving test conducted at South Marsh Island Block 130, offshore Louisiana. A 24inch diameter tubular pile was driven to 310 feet penetration with a submerged hydraulic hammer. The hammer drove the pile top from a position 33 feet above water to a point 175 feet below water. The test was performed as a part of technology development for constructing an offshore drilling structure in 1,050 feet water depth. PURPOSE AND SCOPE The pile foundation for platforms on the Louisiana Continental Shelf are currently installed with steam pile driving hammers, operated above the water. The purpose of this test was to demonstrate the feasibility of pile driving with the hammer underwater. Such a capability would make a significant impact on the cost of installing piling in very deep water because of the expense involved with extending the pile from the mud line to above water. Thus, the test was performed as a part of the design effort for the 1,050-foot water depth Cognac platform, since its concept included features which would allow the piling for the platform to be installed with (1) an underwater pile driver or (2) drilling and grouting methods. An early evaluation of these alternates indicated that the underwater pile driving would be several million dollars more attractive than cementing the piling in a drilled hole. HAMMER SELECTION After reviewing the status of several hammers with the potential capability of underwater pile driving, a hydraulic pile driver was selected for the test. It was the only hammer in field operational use which could be readily adapted for underwater use. Other available hammer designs were either in the conceptual or development stage. Also, the manufacturer had two similar but larger hammers (600,000 ft-lb energy rating) under construction at the time for use in the North Sea. Such a large hammer was considered adequate to drive the Cognac platform piling. Much development engineering work had been completed for adapting this hammer design for underwater use. Thus, this hydraulic hammer was chosen for the test because it presented the best alternate to test the underwater pile driving concept and provide a sufficiently large underwater pile driver in time for the platform installation. HAMMER MODIFICATIONS FOR THE UNDERWATER TEST Since the basic test objective was determining the ability of the hammer to drive at its rated energy while submerged in seawater, no attempt was made to solve the problems of positioning the hammer underwater. The hammer would be placed on the pile above water and pile driving would proceed until the mud line or refusal is reached. Divers would be used to reposition the hammer if it becomes necessary to remove it. Thus, the hammer was only equipped with devices for:holding it on the pile top,offsetting submerged buoyancy, andmaintaining a gas environment inside the hammer casing and a gas cushion around the pile top.
Title: Underwater Pile Driving Test Offshore Louisiana
Description:
ABSTRACT This report presents results of an underwater pile driving test conducted at South Marsh Island Block 130, offshore Louisiana.
A 24inch diameter tubular pile was driven to 310 feet penetration with a submerged hydraulic hammer.
The hammer drove the pile top from a position 33 feet above water to a point 175 feet below water.
The test was performed as a part of technology development for constructing an offshore drilling structure in 1,050 feet water depth.
PURPOSE AND SCOPE The pile foundation for platforms on the Louisiana Continental Shelf are currently installed with steam pile driving hammers, operated above the water.
The purpose of this test was to demonstrate the feasibility of pile driving with the hammer underwater.
Such a capability would make a significant impact on the cost of installing piling in very deep water because of the expense involved with extending the pile from the mud line to above water.
Thus, the test was performed as a part of the design effort for the 1,050-foot water depth Cognac platform, since its concept included features which would allow the piling for the platform to be installed with (1) an underwater pile driver or (2) drilling and grouting methods.
An early evaluation of these alternates indicated that the underwater pile driving would be several million dollars more attractive than cementing the piling in a drilled hole.
HAMMER SELECTION After reviewing the status of several hammers with the potential capability of underwater pile driving, a hydraulic pile driver was selected for the test.
It was the only hammer in field operational use which could be readily adapted for underwater use.
Other available hammer designs were either in the conceptual or development stage.
Also, the manufacturer had two similar but larger hammers (600,000 ft-lb energy rating) under construction at the time for use in the North Sea.
Such a large hammer was considered adequate to drive the Cognac platform piling.
Much development engineering work had been completed for adapting this hammer design for underwater use.
Thus, this hydraulic hammer was chosen for the test because it presented the best alternate to test the underwater pile driving concept and provide a sufficiently large underwater pile driver in time for the platform installation.
HAMMER MODIFICATIONS FOR THE UNDERWATER TEST Since the basic test objective was determining the ability of the hammer to drive at its rated energy while submerged in seawater, no attempt was made to solve the problems of positioning the hammer underwater.
The hammer would be placed on the pile above water and pile driving would proceed until the mud line or refusal is reached.
Divers would be used to reposition the hammer if it becomes necessary to remove it.
Thus, the hammer was only equipped with devices for:holding it on the pile top,offsetting submerged buoyancy, andmaintaining a gas environment inside the hammer casing and a gas cushion around the pile top.

Related Results

A New Mechanical Pile Connector Speeds Offshore Contruction Projects
A New Mechanical Pile Connector Speeds Offshore Contruction Projects
Abstract During the past year, a new mechanical pile connector has been introduced to the offshore construction industry. This connector has been the culmination ...
Analysis Of Three-Dimensional Pile Groups With Nonlinear Soil Response And Pile-Soil-Pile Interaction
Analysis Of Three-Dimensional Pile Groups With Nonlinear Soil Response And Pile-Soil-Pile Interaction
ABSTRACT Present methods of pile group analysis are either limited to special geometric cases or do not consider pile-soil-pile interaction. An analytical procedu...
Model Test of Jacked Pile Penetration Process Considering Influence of Pile Diameter
Model Test of Jacked Pile Penetration Process Considering Influence of Pile Diameter
In order to investigate the influence of different diameters on pile end resistance, pile side resistance, pile axial force and pile force transmission law of jacked pile penetrati...
Case Histories - Pile Driving In The Gulf Of Mexico
Case Histories - Pile Driving In The Gulf Of Mexico
ABSTRACT This paper presents a series of case histories on pile driving in the Gulf of Mexico, demonstrating the value of a pile drivability analysis to the engin...
Anchor-PiIe Design for Ocean-FIoor Environments Using Finite-Element Analysis
Anchor-PiIe Design for Ocean-FIoor Environments Using Finite-Element Analysis
ABSTRACT This paper analyzes some aspects of anchor-pile design for marine environments, using a finite-element mathematical model of the pile, soil, and the pile...
Pile Driving Measurements On The Heather Platform Installation
Pile Driving Measurements On The Heather Platform Installation
Abstract The first leg piles of the Heather Platform were instrumented using strain transducers and accelerometers that were attached to the pile just below its t...
Case Histories: Pile Driving Offshore India
Case Histories: Pile Driving Offshore India
ABSTRACT This paper presents a set of case histories on pile driving for a series of platforms set in the calcareous soils of the Arabian Sea, offshore India. In ...
Underwater Pile Driving Hammer At The "Maul Field"
Underwater Pile Driving Hammer At The "Maul Field"
ABSTRACT The RU-300 Underwater Hammer was designed to enable crews to continue pile driving operations on offshore structures during periods of bad weather and hi...

Back to Top