Javascript must be enabled to continue!
The Effect of Deepwater On The Performance Of Slender Underwater Hammers
View through CrossRef
ABSTRACT
Measurements of the impact energy of slender hydraulic underwater hammers show that the performance decreases as the hammer drives deeper under water. Energy is lost into the air circulating around the ram as it moves up and down, and probably also into the adhered water under the anvil. These energy losses should be taken into account in the design of piled foundations in deep water.
1. INTRODUCTION
Slender hydraulic underwater hammers were introduced in 1980. Their slim shape introduced substantial improvements over the first generation of large diameter underwater hammers. Slender hammers are much more versatile. When given an extension pipe (Figure 1a), they can follow a pile through the guides, replacing followers without requiring any structural modifications to the jacket. When equipped with a pile sleeve (Figure 1b), they can drive freely riding on free-standing piles, and when the pile diameter is wide enough, even on a shoulder inside the pile (Figure 1c).
The author's employer owns two types of slender hammer: the small MHU 195 with a specified net impact energy of 195 kNm, and the huge MHU 1700 with a specified net impact energy of 1700 kNm. Both hammers belong to the same series manufactured by Menck.
These hammers have been in use since 1980. On two piling jobs in 1981 the pile driving with the MHU 195 appeared unexpectedly difficult. Several piles could not achieve their target penetration. At that time, the hammers were not equipped with an adequate monitoring system, so the source of the problems remained unclear.
Since 1983, it has been possible to measure the impact energy of the MHU 1700s. The first time the measuring system was used in the field, during the pile installation of the Iwaki platform, offshore Japan, the hammer performed substantially less well than it had performed on test piles. Improvements to the hydraulic control of the hammer could not raise the energy to the target level. The cause could not be in the energy supply, as an underwater power pack with short hydraulic hoses was used, fed by an electric umbilical that had minimal energy losses. Suspicion was directed to the compressed air circulating around the ram. After the completion of the Iwaki installation, the vent ports in the inner wall of Heerema's MHU hammers (Figure 2) were enlarged.
Exxon later reported similar problems with their MHU 220s during the installation of the Lena Guyed Tower in 1983 (1). Extensive instrumentation of hammer and pile disclosed that the source was indeed the circulation of the compressed air around the ram. The air could not escape quickly enough, and caused cushioning of the ram just before the blow. External piping around the hammer eased the air flow and enhanced the efficiency from below 50% to between 60 and 80%.
Several instrumentations of the MHU 1700 were carried out in 1984 and 1985.
Title: The Effect of Deepwater On The Performance Of Slender Underwater Hammers
Description:
ABSTRACT
Measurements of the impact energy of slender hydraulic underwater hammers show that the performance decreases as the hammer drives deeper under water.
Energy is lost into the air circulating around the ram as it moves up and down, and probably also into the adhered water under the anvil.
These energy losses should be taken into account in the design of piled foundations in deep water.
1.
INTRODUCTION
Slender hydraulic underwater hammers were introduced in 1980.
Their slim shape introduced substantial improvements over the first generation of large diameter underwater hammers.
Slender hammers are much more versatile.
When given an extension pipe (Figure 1a), they can follow a pile through the guides, replacing followers without requiring any structural modifications to the jacket.
When equipped with a pile sleeve (Figure 1b), they can drive freely riding on free-standing piles, and when the pile diameter is wide enough, even on a shoulder inside the pile (Figure 1c).
The author's employer owns two types of slender hammer: the small MHU 195 with a specified net impact energy of 195 kNm, and the huge MHU 1700 with a specified net impact energy of 1700 kNm.
Both hammers belong to the same series manufactured by Menck.
These hammers have been in use since 1980.
On two piling jobs in 1981 the pile driving with the MHU 195 appeared unexpectedly difficult.
Several piles could not achieve their target penetration.
At that time, the hammers were not equipped with an adequate monitoring system, so the source of the problems remained unclear.
Since 1983, it has been possible to measure the impact energy of the MHU 1700s.
The first time the measuring system was used in the field, during the pile installation of the Iwaki platform, offshore Japan, the hammer performed substantially less well than it had performed on test piles.
Improvements to the hydraulic control of the hammer could not raise the energy to the target level.
The cause could not be in the energy supply, as an underwater power pack with short hydraulic hoses was used, fed by an electric umbilical that had minimal energy losses.
Suspicion was directed to the compressed air circulating around the ram.
After the completion of the Iwaki installation, the vent ports in the inner wall of Heerema's MHU hammers (Figure 2) were enlarged.
Exxon later reported similar problems with their MHU 220s during the installation of the Lena Guyed Tower in 1983 (1).
Extensive instrumentation of hammer and pile disclosed that the source was indeed the circulation of the compressed air around the ram.
The air could not escape quickly enough, and caused cushioning of the ram just before the blow.
External piping around the hammer eased the air flow and enhanced the efficiency from below 50% to between 60 and 80%.
Several instrumentations of the MHU 1700 were carried out in 1984 and 1985.
Related Results
An Evaluation Of Hydraulic Vs.Steam Pile Driving Hammers
An Evaluation Of Hydraulic Vs.Steam Pile Driving Hammers
Abstract
Hydraulic hammers have received much publicity in recent years, and much emphasis has been placed on their advantages. This paper makes a detailed evalua...
Subsea Installations Using Vibratory Piling Hammers
Subsea Installations Using Vibratory Piling Hammers
ABSTRACT
During the summer of 1987 ICE hydraulic vibratory hammers were used 3 times successfully for subsea installations of anchorpiles and template foundation ...
New Tendon and Riser Technologies Improve TLP Competitiveness in Ultra- Deepwater
New Tendon and Riser Technologies Improve TLP Competitiveness in Ultra- Deepwater
Abstract
The extensive industry experience with design, fabrication, installation, and operation of TLPs in water depths up to 4,000 ft has demonstrated the flexi...
The Future of Regulations for the Deepwater GOM
The Future of Regulations for the Deepwater GOM
Abstract
Deepwater oil and gas activities in the U.S. Gulf of Mexico Outer ContinentalShelf (OCS) are regulated by the Minerals Management Service (MMS). The leve...
Underwater Pile Driving Test Offshore Louisiana
Underwater Pile Driving Test Offshore Louisiana
ABSTRACT
This report presents results of an underwater pile driving test conducted at South Marsh Island Block 130, offshore Louisiana. A 24inch diameter tubular ...
The Synthesis of Unpaired Underwater Images for Monocular Underwater Depth Prediction
The Synthesis of Unpaired Underwater Images for Monocular Underwater Depth Prediction
Underwater depth prediction plays an important role in underwater vision research. Because of the complex underwater environment, it is extremely difficult and expensive to obtain ...
Emerging underwater survey technologies: A review and future outlook
Emerging underwater survey technologies: A review and future outlook
Emerging underwater survey technologies are revolutionizing the way we explore and understand the underwater world. This review examines the latest advancements in underwater surve...
A new conceptual design for subsea charging station
A new conceptual design for subsea charging station
With deepening ocean development , a larger scale Internet of Underwater Things (IoUT) is being realized[1].More and more underwater equipment is being deployed, various ocean moni...

