Identifying and prioritizing delay factors in Iran’s oil construction projects
View through CrossRef
Purpose
Successful implementation of construction projects is one of the crucial factors for the economic development of every country. The main part of the countries’ capital is allocated to civil and infrastructure projects annually, most of which are accomplished with delay. Construction projects are often criticized for overrunning time and budgets. Analyzing the factors causing delay is essential for omitting them and timely implementation of these projects. Due to the importance of oil projects, this study aims to investigate and analyze the factors causing a delay in Iran’s oil construction projects.
Design/methodology/approach
In this research, after a broad literature review, using the fuzzy Delphi method, a total of 75 delay factors were identified under 11 major categories of owner, contractor, consultant, equipment, labor, materials, design, contract and contractual relations, laws and regulations, environmental factors, and managerial factors. Then, by using the best-worst method, the factors were prioritized.
Findings
The results showed that sanction, governmental management systems, weak project management by the contractor, technical and managerial weaknesses of the consultant, financial problems and delay in payment by the owner, low efficiency of the equipment, low productivity of the workforce, changes in laws and regulations, inappropriate organizational structure linking to the project, changes in the design, and changes in the price of materials are the most crucial factors causing a delay in Iran’s oil construction projects.
Research limitations/implications
These findings are expected to have significant contributions to Iran’s oil construction industry in controlling the time overruns in construction contracts.
Originality/value
The main contribution of this study is to develop a comprehensive framework in which, causes of delay in Iran’s oil construction projects are addressed and prioritized.
Title: Identifying and prioritizing delay factors in Iran’s oil construction projects
Description:
Purpose
Successful implementation of construction projects is one of the crucial factors for the economic development of every country.
The main part of the countries’ capital is allocated to civil and infrastructure projects annually, most of which are accomplished with delay.
Construction projects are often criticized for overrunning time and budgets.
Analyzing the factors causing delay is essential for omitting them and timely implementation of these projects.
Due to the importance of oil projects, this study aims to investigate and analyze the factors causing a delay in Iran’s oil construction projects.
Design/methodology/approach
In this research, after a broad literature review, using the fuzzy Delphi method, a total of 75 delay factors were identified under 11 major categories of owner, contractor, consultant, equipment, labor, materials, design, contract and contractual relations, laws and regulations, environmental factors, and managerial factors.
Then, by using the best-worst method, the factors were prioritized.
Findings
The results showed that sanction, governmental management systems, weak project management by the contractor, technical and managerial weaknesses of the consultant, financial problems and delay in payment by the owner, low efficiency of the equipment, low productivity of the workforce, changes in laws and regulations, inappropriate organizational structure linking to the project, changes in the design, and changes in the price of materials are the most crucial factors causing a delay in Iran’s oil construction projects.
Research limitations/implications
These findings are expected to have significant contributions to Iran’s oil construction industry in controlling the time overruns in construction contracts.
Originality/value
The main contribution of this study is to develop a comprehensive framework in which, causes of delay in Iran’s oil construction projects are addressed and prioritized.
Related Results
Hydatid Disease of The Brain Parenchyma: A Systematic Review
Hydatid Disease of The Brain Parenchyma: A Systematic Review
Abstarct
Introduction
Isolated brain hydatid disease (BHD) is an extremely rare form of echinococcosis. A prompt and timely diagnosis is a crucial step in disease management. This ...
Causes of delay in construction projects: The case of oil and gas projects
Causes of delay in construction projects: The case of oil and gas projects
Successful implementation of construction projects is one of the key factors for economic development of every country. Every year, a major part of the countries’ capital is alloca...
Unveiling Construction Quality Factors: Insights from Asian Economy's Building Projects
Unveiling Construction Quality Factors: Insights from Asian Economy's Building Projects
Economic growth of any country depends on the construction projects and industry in the region. Therefore, the construction industry in Pakistan is directly related to quality and ...
A study of causes of delay and cost overrun in office construction projects in the eThekwini Municipal Area, South Africa
A study of causes of delay and cost overrun in office construction projects in the eThekwini Municipal Area, South Africa
On-time completion and conformity with assigned cost of every project are the most important factors in the success of project plans. Cost overruns and time overrun (delays) have b...
Application of Big Data in The Prevention of Work-Related Crimes in Early-Stage Construction Engineering
Application of Big Data in The Prevention of Work-Related Crimes in Early-Stage Construction Engineering
Preventing work-related crimes in the early stages of construction projects is a crucial way to ensure the safety, efficiency, and integrity of construction projects. Big data tech...
Understanding delays in housing construction: evidence from Northern Ireland
Understanding delays in housing construction: evidence from Northern Ireland
Purpose– The purpose of this paper is to investigate delay factors within private housing construction in Northern Ireland. Delays are inherent throughout the construction industry...
Budaya Struktur Pemerintahan Republik Islam Iran
Budaya Struktur Pemerintahan Republik Islam Iran
<p><em>Abstrak</em> - <strong>Kelahiran Republik Islam Iran tidak lepas dari peran Ayatollah Imam Khomeini, pemimpin spiritual ulama, sekaligus pemimpin pol...
The Methods Taken in SZ36-1 Oilfield in the Early Stage of Production
The Methods Taken in SZ36-1 Oilfield in the Early Stage of Production
Abstract
SZ 36-1 Oil Field is located in Liaodong Bay of Bohai Sea and is an unconsolidated sand and structure-lithology reservoir. The reservoir is distributed i...