Javascript must be enabled to continue!
Design and Analysis for the Lift Installation of the Veslefrikk Jacket
View through CrossRef
ABSTRACT
In order to provide a cost efficient development for the Veslefrikk field, a hybrid concept consisting of a floating production facility and a lift-installed wellhead jacket was chosen. This paper describes the design, analysis, and model testing work involved in the preparation for the lift installation of the jacket.
INTRODUCTION
Statoil's development concept for the Veslefrikk fleld 1n the northern North Sea, consists of a fixed wellhead platform adjacent to a floating production faci1ity in 174 m water. This innovative field development plan contributes to reduced investments making Veslefrikk economically viable in a low oil ' price scenario.
In compliance with the overall cost conscious development philosophy, a decision was made to lift-install the wellhead platform, which is among the tallest jacket structures in the North Sea. The Jacket has been designed to accommodate an offshore lift as well as an inshore lift followed by a wet tow.
Being 184 m long and with a lift weight of 9060 tonnes, the Veslefrikk jacket will be the largest Jacket to be 11ft-1nstalled and the heaviest marine lift in the world. This operation has only become Possible due to the emergence of larger capacity 11ft vessels, a light topside and an innovative jacket design.
The lift installation condition has had significant impact on the jacket design criteria. Accordingly, considerable time has been spent on analysing and designing the' jacket for this condition ensuring a light structure that can be lifted horizontally off the transport barge, lowered into the water and then upended.
A rigorous weight optimization program and an innovative design approach was implemented to satisfy the lift weight requirements. The overall design, including the use of a deck support frame, insert legs, antifouling coating, conductor shielding effects, X-braces, rotated topside and lightweight materials is presented in a separate 1989 OTC paper by Baerheim and Fossan (Ref. 1), and elsewhere by Lefranc et al. (Ref. 2 and 3). The purpose of this paper is to describe in more detail the aspects of the design and analysis particularly relating to the lift installation itself.
DESIGN BASIS
The jacket is to be lift installed using a large crane vessel. Two vessels are able to perform this lift: the DBI02 having two 6000 tonne cranes and the M7000 equipped with two 7000 tonne cranes. In addition, Balder and Hermod may lift up to 12000 tonnes in parallel. However, all these figures are maximum, unfactored loads, and so to maintain competition between the installation contractors, the maximum allowable weight of the jacket was somewhat less than 10000 tonnes.
The jacket weight for structural design purposes was taken as 9800 tonnes. The estimated lift weight at the time of writing is 9060 tonnes.
To be able to utilize the maximum capacity of the crane, the distance from the centre of gravity of the jacket to the crane vessel shall be a minimum.
Title: Design and Analysis for the Lift Installation of the Veslefrikk Jacket
Description:
ABSTRACT
In order to provide a cost efficient development for the Veslefrikk field, a hybrid concept consisting of a floating production facility and a lift-installed wellhead jacket was chosen.
This paper describes the design, analysis, and model testing work involved in the preparation for the lift installation of the jacket.
INTRODUCTION
Statoil's development concept for the Veslefrikk fleld 1n the northern North Sea, consists of a fixed wellhead platform adjacent to a floating production faci1ity in 174 m water.
This innovative field development plan contributes to reduced investments making Veslefrikk economically viable in a low oil ' price scenario.
In compliance with the overall cost conscious development philosophy, a decision was made to lift-install the wellhead platform, which is among the tallest jacket structures in the North Sea.
The Jacket has been designed to accommodate an offshore lift as well as an inshore lift followed by a wet tow.
Being 184 m long and with a lift weight of 9060 tonnes, the Veslefrikk jacket will be the largest Jacket to be 11ft-1nstalled and the heaviest marine lift in the world.
This operation has only become Possible due to the emergence of larger capacity 11ft vessels, a light topside and an innovative jacket design.
The lift installation condition has had significant impact on the jacket design criteria.
Accordingly, considerable time has been spent on analysing and designing the' jacket for this condition ensuring a light structure that can be lifted horizontally off the transport barge, lowered into the water and then upended.
A rigorous weight optimization program and an innovative design approach was implemented to satisfy the lift weight requirements.
The overall design, including the use of a deck support frame, insert legs, antifouling coating, conductor shielding effects, X-braces, rotated topside and lightweight materials is presented in a separate 1989 OTC paper by Baerheim and Fossan (Ref.
1), and elsewhere by Lefranc et al.
(Ref.
2 and 3).
The purpose of this paper is to describe in more detail the aspects of the design and analysis particularly relating to the lift installation itself.
DESIGN BASIS
The jacket is to be lift installed using a large crane vessel.
Two vessels are able to perform this lift: the DBI02 having two 6000 tonne cranes and the M7000 equipped with two 7000 tonne cranes.
In addition, Balder and Hermod may lift up to 12000 tonnes in parallel.
However, all these figures are maximum, unfactored loads, and so to maintain competition between the installation contractors, the maximum allowable weight of the jacket was somewhat less than 10000 tonnes.
The jacket weight for structural design purposes was taken as 9800 tonnes.
The estimated lift weight at the time of writing is 9060 tonnes.
To be able to utilize the maximum capacity of the crane, the distance from the centre of gravity of the jacket to the crane vessel shall be a minimum.
Related Results
Design and Installation of the Veslefrikk Jacket
Design and Installation of the Veslefrikk Jacket
ABSTRACT
The Veslefrikk A jacket, standing in 174 meter water depth in the North Sea, was lift installed in May 1989. The jacket is the heaviest lift installed of...
Fundamental study on rope vibration suppression by middle transfer floor using risk information
Fundamental study on rope vibration suppression by middle transfer floor using risk information
Lifts are essential for means of vertical transportation. Recently, the lifts installed in the high-rise buildings are long travel, thus the lift ropes are becoming longer. The nat...
Weight Optimization of the Veslefrikk Jacket
Weight Optimization of the Veslefrikk Jacket
Abstract
The Veslefrikk jacket will be installed in the North Sea in 174 meter waterdepth. It is the largest lifted offshore structure in the world.
...
Bullwinkle Loadout Analysis
Bullwinkle Loadout Analysis
ABSTRACT
The Bullwinkle jacket was loaded onto a launch barge using a conventional skidding operation. The size (over 1365 feet long), weight (approximately 50,00...
Delivering Best-In-Class Shallow Water Tender-Assisted Drilling Wellhead Platform, a New Chapter
Delivering Best-In-Class Shallow Water Tender-Assisted Drilling Wellhead Platform, a New Chapter
Abstract
This paper demonstrates another success story on delivering a new Best-In-Class Tendered Assisted Drilling (TAD) Wellhead Platform. A clear target/goal to a...
Gas Lift Journey to Maximize the Asset Value in Platong Field, Gulf of Thailand
Gas Lift Journey to Maximize the Asset Value in Platong Field, Gulf of Thailand
Abstract
Operating Platong field in the Gulf of Thailand (GoT) is challenging because of the small compartmentalized reservoirs in the fluvial deposition environm...
The Veslefrikk Jacket Concept
The Veslefrikk Jacket Concept
ABSTRACT
A new concept for developing oil fields has been prepared by Statoil for the Veslefrikk field in the North Sea.
For this deep- water location...
Monitoring Offshore Lift Dynamics
Monitoring Offshore Lift Dynamics
ABSTRACT
This paper illustrates the significance of lift dynamic aspects observed during two major offshore heavy lift operations performed in 1991. Extensive off...

