Abstract
A UK North Sea operator presented a challenging opportunity for the development of a contingency recovery system to be designed for deployment from an intervention vessel. The main requirement of the contingency tool was that it be capable of recovering coiled tubing that is subsequently left in a subsea well after previously operating an emergency shutdown (ESD) system and securing the well.
Typically, when an ESD operation must be performed, requirements demand that the vessel be unlatched from the subsea wellhead within 60 seconds. When the vessel returns, the operator has to recover the coiled tubing that was left in the well. Unlike conventional operations, for this vessel-deployed endeavor, the injector head is located over the moonpool, a large opening in the middle of the vessel that gives the operator subsea access. Unfortunately, the moonpool poses an inherent human risk; thus there exists the desire to limit human interaction in this type of operation.
To reduce the human risk involved, a spoolable spear system that eliminates the need to break out the lubricator/riser multiple times was engineered. The system was designed to enable retrieval of the sheared coiled tubing and recovery of the coiled tubing and connected tools to the work reel without breaking a lubricator/riser connection. Specifically, after a dressing run is completed, the spoolable coiled tubing spear is able to stab into the dressed open end of the coiled tubing and recover the coiled tubing string back through the injector head and back onto the work reel.
With an ever increasing focus on safety, particularly offshore safety, this spoolable spear system presents an opportunity to reduce human intervention in work locations and to significantly reduce the risk of injury. A reliability feature of the contingency system is that all components stressed during operation are to be replaced after each run, making it a one-run system. Multiple sizes of this coiled tubing recovery system have been developed for efficient and effective interventions while encouraging footprint minimization. Field-testing details will be reviewed and discussed during the associated presentation.
Title: Spoolable Coiled Tubing Spears: Recovering Subsea Wells After Emergency Shutdowns
Description:
Abstract
A UK North Sea operator presented a challenging opportunity for the development of a contingency recovery system to be designed for deployment from an intervention vessel.
The main requirement of the contingency tool was that it be capable of recovering coiled tubing that is subsequently left in a subsea well after previously operating an emergency shutdown (ESD) system and securing the well.
Typically, when an ESD operation must be performed, requirements demand that the vessel be unlatched from the subsea wellhead within 60 seconds.
When the vessel returns, the operator has to recover the coiled tubing that was left in the well.
Unlike conventional operations, for this vessel-deployed endeavor, the injector head is located over the moonpool, a large opening in the middle of the vessel that gives the operator subsea access.
Unfortunately, the moonpool poses an inherent human risk; thus there exists the desire to limit human interaction in this type of operation.
To reduce the human risk involved, a spoolable spear system that eliminates the need to break out the lubricator/riser multiple times was engineered.
The system was designed to enable retrieval of the sheared coiled tubing and recovery of the coiled tubing and connected tools to the work reel without breaking a lubricator/riser connection.
Specifically, after a dressing run is completed, the spoolable coiled tubing spear is able to stab into the dressed open end of the coiled tubing and recover the coiled tubing string back through the injector head and back onto the work reel.
With an ever increasing focus on safety, particularly offshore safety, this spoolable spear system presents an opportunity to reduce human intervention in work locations and to significantly reduce the risk of injury.
A reliability feature of the contingency system is that all components stressed during operation are to be replaced after each run, making it a one-run system.
Multiple sizes of this coiled tubing recovery system have been developed for efficient and effective interventions while encouraging footprint minimization.
Field-testing details will be reviewed and discussed during the associated presentation.
Related Results
Rigless Well Intervention Using Tubing Patch Technology Helps Restore Inactive Wells
Rigless Well Intervention Using Tubing Patch Technology Helps Restore Inactive Wells
Abstract
This paper provides in-depth analysis of a low-cost solution to economically sustain production and avoid high workover costs. This paper conducts the techn...
Prebending Coiled Tubing and Its Fatigue Life Prediction
Prebending Coiled Tubing and Its Fatigue Life Prediction
Coiled tubing is widely used in oil drilling and production operations. However, extreme high stress variation of coiled tubing during the processes of pulling out, rolling in the ...
Riserless Coiled-Tubing Well Intervention
Riserless Coiled-Tubing Well Intervention
Abstract
This paper describes a concept for subsea coiled tubing well intervention, without the use of a workover riser system. Coiled tubing analyses and design,...
Innovative Coiled Tubing Technology to Improve Performance in Horizontal Completions
Innovative Coiled Tubing Technology to Improve Performance in Horizontal Completions
Abstract
Recent technological innovations in seismic imaging, directional drilling and hydraulic fracturing and other completion techniques have made development of ...
Evolution Of Subsea Production Systems: A Worldwide Overview
Evolution Of Subsea Production Systems: A Worldwide Overview
ABSTRACT
The evolution in the use of subsea technology has seen advancement -from I well in the Gulf of Mexico in 1961 to over 750 wells in a tide variety of loca...
Jointed Tubing Injector Snubbing on Extended Reach Wells
Jointed Tubing Injector Snubbing on Extended Reach Wells
Abstract
OBJECTIVE / SCOPE
An injector has been developed that is able to continuously move conventional jointed tubing in and o...
Metal-Polymer Coiled Tubing
Metal-Polymer Coiled Tubing
Abstract
Metal-polymer coiled tubing (MCT) are flexible pipes based on a copolymer reinforced with steel tape, wires and ropes. During the research was proposed and ...
Design Principles For Multi-Well 'Subsea Production Equipment
Design Principles For Multi-Well 'Subsea Production Equipment
ABSTRACT
Use of multi-well subsea production systems has recently increased due to the early production this type of system offers for large oil fields and the ec...