Empirical Evaluation of Continuous Review Inventory Policies for Spare Parts in the Wire and Cable Manufacturing Industry: A Multi-Scenario Cost Analysis with Multi-Criteria Classification and Demand Behavior Integration
View through CrossRef
This study aims to enhance spare parts inventory management efficiency in the wire and cable manufacturing industry through a systematic analysis and data-driven approach. The analysis combines multi-criteria inventory classification methods: ABC analysis (based on annual consumption value), VED analysis (assessing vital, essential, and desirable criticality), and SDE analysis (evaluating scarce, difficult, and easy procurement levels) to efficiently group inventory based on annual consumption value, operational criticality, and procurement difficulty. Subsequently, demand pattern analysis is performed to evaluate each spare part’s demand characteristics. From an empirical dataset of 377 spare part items, fifteen items were selected from four high-priority classification groups ESA, VEA, VDA, and VSA for a detailed evaluation of suitable inventory control policies. Analysis of the selected items showed smooth demand behavior, whereas only two items in the ESA group exhibited intermittent demand. Two continuous review inventory control models, (s, S) and (s, Q), were assessed across four service levels 80, 90, 95, and 99 percent to evaluate their effectiveness in minimizing shortages and overall inventory costs. Accurately estimating shortage and opportunity-loss costs remains a significant challenge. To analyze the cost-performance trade-offs among ordering, holding, and shortage costs, three scenarios were considered: (1) total inventory cost (TIC) without shortage cost, (2) TIC including expedited shortage cost, and (3) TIC including opportunity-loss shortage. Results revealed that the (s, S) policy not only eliminated spare part shortages but also yielded significant reductions in total inventory costs by approximately 46 percent for TIC with expedited shortage costs and 97 percent for TIC with opportunity loss shortages relative to the manufacturer’s existing operational practices. Optimal service levels were determined by balancing TIC and shortage risk based on each item’s demand variability and criticality. The findings indicate that aligning inventory control policies with demand behavior and part criticality enhances cost efficiency, reliability, and production continuity.
Title: Empirical Evaluation of Continuous Review Inventory Policies for Spare Parts in the Wire and Cable Manufacturing Industry: A Multi-Scenario Cost Analysis with Multi-Criteria Classification and Demand Behavior Integration
Description:
This study aims to enhance spare parts inventory management efficiency in the wire and cable manufacturing industry through a systematic analysis and data-driven approach.
The analysis combines multi-criteria inventory classification methods: ABC analysis (based on annual consumption value), VED analysis (assessing vital, essential, and desirable criticality), and SDE analysis (evaluating scarce, difficult, and easy procurement levels) to efficiently group inventory based on annual consumption value, operational criticality, and procurement difficulty.
Subsequently, demand pattern analysis is performed to evaluate each spare part’s demand characteristics.
From an empirical dataset of 377 spare part items, fifteen items were selected from four high-priority classification groups ESA, VEA, VDA, and VSA for a detailed evaluation of suitable inventory control policies.
Analysis of the selected items showed smooth demand behavior, whereas only two items in the ESA group exhibited intermittent demand.
Two continuous review inventory control models, (s, S) and (s, Q), were assessed across four service levels 80, 90, 95, and 99 percent to evaluate their effectiveness in minimizing shortages and overall inventory costs.
Accurately estimating shortage and opportunity-loss costs remains a significant challenge.
To analyze the cost-performance trade-offs among ordering, holding, and shortage costs, three scenarios were considered: (1) total inventory cost (TIC) without shortage cost, (2) TIC including expedited shortage cost, and (3) TIC including opportunity-loss shortage.
Results revealed that the (s, S) policy not only eliminated spare part shortages but also yielded significant reductions in total inventory costs by approximately 46 percent for TIC with expedited shortage costs and 97 percent for TIC with opportunity loss shortages relative to the manufacturer’s existing operational practices.
Optimal service levels were determined by balancing TIC and shortage risk based on each item’s demand variability and criticality.
The findings indicate that aligning inventory control policies with demand behavior and part criticality enhances cost efficiency, reliability, and production continuity.
Related Results
Non-Recommended Publishing Lists: Strategies for Detecting Deceitful Journals
Non-Recommended Publishing Lists: Strategies for Detecting Deceitful Journals
Abstract
The rapid growth of open access publishing (OAP) has significantly improved the accessibility and dissemination of scientific knowledge. However, this expansion has also c...
Implementasi Metode Arima Data Warehouse Untuk Prediksi Permintaan Suku Cadang
Implementasi Metode Arima Data Warehouse Untuk Prediksi Permintaan Suku Cadang
Food production company is a company that focuses on the production of instant noodles, and machine reliability is crucial in the production process. To maintain machine reliabilit...
Background of the study
Background of the study
The automotive industry has indeed been making significant strides towards sustainability, with a focus on eco-friendly practices and the adoption of green technologies (Sun et al....
At Sea Test: Hawaii Deepwater Cable Program
At Sea Test: Hawaii Deepwater Cable Program
ABSTRACT
In order to investigate and demonstrate the technical feasibility of laying a Submarine power cable in the open ocean, in depths exceeding 6000 feet, ove...
Rearranging First-In First-Out (FIFO) Parts Layouts
Rearranging First-In First-Out (FIFO) Parts Layouts
Surabaya locomotive warehouse is one part of the company PT. Kereta Api Indonesia (Persero) as a place to store spare parts for repair and maintenance purposes, especially locomoti...
Prysverlagings op voorraad met ’n dalende vraag
Prysverlagings op voorraad met ’n dalende vraag
The problem faced in this paper is a periodic pricing of inventory with obsolescence and an unknown time horizon. Typical inventory items with these properties are music CDs. The p...
New Parallel Wire Cable Tether Study for Deepwater TLP
New Parallel Wire Cable Tether Study for Deepwater TLP
ABSTRACT
This paper describes New Prefabricated Parallel Wire Strand or shortly "New-PPWS", the result of joint industry research on the new concept of parallel w...
Critical Spare Parts Identification and Management of Mechanical Ventilation and Air-Conditioning (MVAC) System in University Campus
Critical Spare Parts Identification and Management of Mechanical Ventilation and Air-Conditioning (MVAC) System in University Campus
Spare parts are used to keep a system functioning, reducing downtime and the system’s life span. Recently, spare parts management has gained significant attention among maintenance...