Torpedo Base - A New Conductor Installation Process

View through CrossRef
Abstract In the last years Petrobras has optimized and reduced the cost of the mooring systems by the use of torpedo anchors. It consists of a tubular pile with heavy weight ballast, installed by a process that uses the energy generated by the free fall of the pile from a supply vessel. It's a low cost anchoring concept, with simple fabrication and installation. More than two hundred torpedo anchors were installed offshore Brazil in the last four years. Based on the success of the torpedo anchors for mooring purposes Petrobras Drilling and Exploration department decided to employ the same idea for installing the conductor casing. The benefit was that this installation could be accomplished from an anchor handling vessel saving important rig time. Another advantage from this installation method is the better foundation provided since no soil is removed during this process. The paper will give an overview of Petrobras Torpedo Base experience in the Albacora East field as well as a few other applications of this technology for the production side. Introduction In late 1984 Petrobras started its deepwater campaign in Campos Basin in the Marlim field using dynamic positioned (DP) drillships. Among the many problems related to deepwater drilling such as high wellhead stresses, wellhead equipment inadequacy, lack of experience with DP rigs, the loss of wells during the spud in caused considerable prejudice. Many actions were taken with the goal of reducing this problem. New dedicated equipment were designed, an extensive soil sampling campaign was carried out, adequate operational procedures were written, etc. After the implementation of those actions the number of well losses has dropped considerably but some wells were still lost per year. Thus a group of engineers aiming to improve the well performance decided to use Petrobras mooring torpedo experience to be fitted for well spud in. The idea is to install the 36" or 30" conductor casing previously to the DP arrival to the location. This would be carried out through the use of a DP tug with ROV support while delimity the well location with buoys. This would save significant money since the drillship daily rate cannot be compared to the tug's rate. Besides the well drilling time is reduced of about 1 to 1.5 days since the conductor casing is already installed. Conductor Casing Installation Procedures The standard deepwater casing well design at Campos Basin is 36"/30" × 13 3/8" × 9 5/8" × 7" (optional). Normally the 36" or 30" conductor casing with 36m long can be installed by drilling and cementing or by jetting depending on either soil conditions of the location. The jetting procedure in clay soils is reliable in most of the cases and adopted all over the world but from time to time a very poor spud in happens causing in some occasions the loss of the well. To understand this occurence it is important to know that the conductor casing is held in place by soil friction with the outside of the casing.
Title: Torpedo Base - A New Conductor Installation Process
Description:
Abstract In the last years Petrobras has optimized and reduced the cost of the mooring systems by the use of torpedo anchors.
It consists of a tubular pile with heavy weight ballast, installed by a process that uses the energy generated by the free fall of the pile from a supply vessel.
It's a low cost anchoring concept, with simple fabrication and installation.
More than two hundred torpedo anchors were installed offshore Brazil in the last four years.
Based on the success of the torpedo anchors for mooring purposes Petrobras Drilling and Exploration department decided to employ the same idea for installing the conductor casing.
The benefit was that this installation could be accomplished from an anchor handling vessel saving important rig time.
Another advantage from this installation method is the better foundation provided since no soil is removed during this process.
The paper will give an overview of Petrobras Torpedo Base experience in the Albacora East field as well as a few other applications of this technology for the production side.
Introduction In late 1984 Petrobras started its deepwater campaign in Campos Basin in the Marlim field using dynamic positioned (DP) drillships.
Among the many problems related to deepwater drilling such as high wellhead stresses, wellhead equipment inadequacy, lack of experience with DP rigs, the loss of wells during the spud in caused considerable prejudice.
Many actions were taken with the goal of reducing this problem.
New dedicated equipment were designed, an extensive soil sampling campaign was carried out, adequate operational procedures were written, etc.
After the implementation of those actions the number of well losses has dropped considerably but some wells were still lost per year.
Thus a group of engineers aiming to improve the well performance decided to use Petrobras mooring torpedo experience to be fitted for well spud in.
The idea is to install the 36" or 30" conductor casing previously to the DP arrival to the location.
This would be carried out through the use of a DP tug with ROV support while delimity the well location with buoys.
This would save significant money since the drillship daily rate cannot be compared to the tug's rate.
Besides the well drilling time is reduced of about 1 to 1.
5 days since the conductor casing is already installed.
Conductor Casing Installation Procedures The standard deepwater casing well design at Campos Basin is 36"/30" × 13 3/8" × 9 5/8" × 7" (optional).
Normally the 36" or 30" conductor casing with 36m long can be installed by drilling and cementing or by jetting depending on either soil conditions of the location.
The jetting procedure in clay soils is reliable in most of the cases and adopted all over the world but from time to time a very poor spud in happens causing in some occasions the loss of the well.
To understand this occurence it is important to know that the conductor casing is held in place by soil friction with the outside of the casing.

Related Results

Numerical modelling of a soil structure interaction for a torpedo base conductor in a petroleum well under an extreme lateral load
Numerical modelling of a soil structure interaction for a torpedo base conductor in a petroleum well under an extreme lateral load
This work aims to compare the performance, regarding the soil structure interaction, of a torpedo base conductor and a jetted conductor, considering a drilling rig drift-off scenar...
Inspection of Subsea Conductors Using an Innovative Drop-Down Camera
Inspection of Subsea Conductors Using an Innovative Drop-Down Camera
Abstract Subsea conductors are the foundational elements of offshore drilling operations, serving a dual purpose as both the structural framework and the main condui...
Aging Offshore well Conductors Structural Integrity Issues and Challenges in their Life Extension
Aging Offshore well Conductors Structural Integrity Issues and Challenges in their Life Extension
Abstract ADNOC Offshore operates more than 1300+ numbers of oil, gas and water offshore wells of age 59 years on wards, at 300+ well head platforms located in shallo...
Analyses and Measurements of Conductor Response for Jack-up Drilled Wells in 110 m Water Depth in Harsh Environments.
Analyses and Measurements of Conductor Response for Jack-up Drilled Wells in 110 m Water Depth in Harsh Environments.
Abstract The analysis of conductor systems for wells drilled by jack-ups is often limited to analysis of the conductor alone as a free standing unit. This paper d...
The Mathematical Models of the Operation Process for Critical Production Facilities Using Advanced Technologies
The Mathematical Models of the Operation Process for Critical Production Facilities Using Advanced Technologies
The paper presents data on the problems of monitoring and diagnosing the technical conditions of critical production facilities, such as torpedo ladle cars, steel ladles. The accid...
Successful and Efficient Drill & Drive Conductor Operation in Offshore East Java
Successful and Efficient Drill & Drive Conductor Operation in Offshore East Java
Abstracts Conductor setting depth is critical to provide structural support for next drilling sections. The shoe strength must suffice for drilling ahead and avoid a...
SS: Spar Technology- Developments in Deepwater spar installation
SS: Spar Technology- Developments in Deepwater spar installation
Abstract During the last seven years Heerema Marine Contractors (HMC) has installed more than half of all Spars in the deep waters of the Gulf of Mexico. The dual...

Back to Top