Search engine for discovering works of Art, research articles, and books related to Art and Culture
ShareThis
Javascript must be enabled to continue!

Offline Production Tree Installation: Key Decisions, Value Drivers and Lessons Learnt

View through CrossRef
Abstract After successfully drilling and completing 40 wells with 5000 psi rated production trees in the swamp operation within a 5-year campaign the diverter deck on the Swamp Rig barge never posed a challenge until 6650 psi production tree had to be installed on two non-associated gas wells. The Field Development Plan (FDP) was approved in 2013 and it contained a 2-well (NAG-1A and NAG-2A) development plan for the target reservoirs with estimated recovery of 213 BCF of rich gas and 4.6 MMSTB of pool condensate at initial production rates of 35 MMSCFD and 1,380 BCPD each for both wells. Gas production from these wells will bulk flow to the NAG separator located at the Production Flow Station where the pool condensate will be separated from it. The rich gas will subsequently be transported to the gas plant onshore bypass for supply to the domestic market through the ELPS. NAG-1A and NAG-2A wells are part of the Non-Associated Gas (NAG) development and were completed as single string deviated gas producers with HRWP completions to meet target production rates and reserve recovery. After successfully drilling and completing the NAG-1A well, it was later discovered that the diverter deck of the rig was going to impact the 6650 psi production tree while moving the rig onto the NAG-2A well slot on the same jacket. This paper sets out to give an overview of the planning, risks assessment and execution for using a crane barge to successfully install two 6650 psi production trees on two NAG wells incidents free, after the drilling rig departed location due to the diverter deck limitation. Lessons learned and best practices were captured as well as the resultant cost savings from using the crane barge instead of the rig to install the production trees on the two NAG wells. The total number of days to complete the offline XMT installation using a crane barge was 5 days for both wells while working daylight hours only. This resulted in a cost savings of 154,200 USD per well.
Title: Offline Production Tree Installation: Key Decisions, Value Drivers and Lessons Learnt
Description:
Abstract After successfully drilling and completing 40 wells with 5000 psi rated production trees in the swamp operation within a 5-year campaign the diverter deck on the Swamp Rig barge never posed a challenge until 6650 psi production tree had to be installed on two non-associated gas wells.
The Field Development Plan (FDP) was approved in 2013 and it contained a 2-well (NAG-1A and NAG-2A) development plan for the target reservoirs with estimated recovery of 213 BCF of rich gas and 4.
6 MMSTB of pool condensate at initial production rates of 35 MMSCFD and 1,380 BCPD each for both wells.
Gas production from these wells will bulk flow to the NAG separator located at the Production Flow Station where the pool condensate will be separated from it.
The rich gas will subsequently be transported to the gas plant onshore bypass for supply to the domestic market through the ELPS.
NAG-1A and NAG-2A wells are part of the Non-Associated Gas (NAG) development and were completed as single string deviated gas producers with HRWP completions to meet target production rates and reserve recovery.
After successfully drilling and completing the NAG-1A well, it was later discovered that the diverter deck of the rig was going to impact the 6650 psi production tree while moving the rig onto the NAG-2A well slot on the same jacket.
This paper sets out to give an overview of the planning, risks assessment and execution for using a crane barge to successfully install two 6650 psi production trees on two NAG wells incidents free, after the drilling rig departed location due to the diverter deck limitation.
Lessons learned and best practices were captured as well as the resultant cost savings from using the crane barge instead of the rig to install the production trees on the two NAG wells.
The total number of days to complete the offline XMT installation using a crane barge was 5 days for both wells while working daylight hours only.
This resulted in a cost savings of 154,200 USD per well.

Related Results

SS: Spar Technology- Developments in Deepwater spar installation
SS: Spar Technology- Developments in Deepwater spar installation
Abstract During the last seven years Heerema Marine Contractors (HMC) has installed more than half of all Spars in the deep waters of the Gulf of Mexico. The dual...
Mensa Project: Subsea Tree System
Mensa Project: Subsea Tree System
Abstract This paper describes the design, product development and offshore installation of the subsea trees for the Shell Offshore Inc. (SOI) Mensa Project. The M...
Trained-feature specific offline learning in an orientation detection task
Trained-feature specific offline learning in an orientation detection task
AbstractIt has been suggested that sleep provides additional enhancement of visual perceptual learning (VPL) acquired before sleep, termed offline performance gains. A majority of ...
Full Offline Well Cementing Implementation Resulting in Significant Time Savings and Improvement in Operational Efficiency
Full Offline Well Cementing Implementation Resulting in Significant Time Savings and Improvement in Operational Efficiency
Abstract The current global low oil price environment has driven many operators to consider having a quicker and more efficient operations and reduction of the well ...
Independence Installation
Independence Installation
Abstract This Session paper will review the planning, preparation, and execution of the installation of the Independence Hub facility in Mississippi Canyon Block ...
SS: MODU Anchor: Improved Predictions of MODU Fluke Anchors Increases the Confidence in Mooring System Design
SS: MODU Anchor: Improved Predictions of MODU Fluke Anchors Increases the Confidence in Mooring System Design
Abstract An overview of the current Norwegian and international requirements for design and installation of fluke anchors is given. Important design and installat...
Offline Pre-trained Multi-agent Decision Transformer
Offline Pre-trained Multi-agent Decision Transformer
AbstractOffline reinforcement learning leverages previously collected offline datasets to learn optimal policies with no necessity to access the real environment. Such a paradigm i...
Inter-specific variations in tree stem methane and nitrous oxide exchanges in a tropical rainforest
Inter-specific variations in tree stem methane and nitrous oxide exchanges in a tropical rainforest
<p>Tropical forests are the most productive terrestrial ecosystems, global centres of biodiversity and important participants in the global carbon and water cycles. T...

Back to Top