Javascript must be enabled to continue!
Mensa Project: Subsea Tree System
View through CrossRef
Abstract
This paper describes the design, product development and offshore installation of the subsea trees for the Shell Offshore Inc. (SOI) Mensa Project. The Mensa Project represents the world's deepest subsea tree at the time of installation and the longest offset from the host platform. The extreme water depth, high flow rate and erosion resistance requirements resulted in a number of significant technical advancements in the subsea tree design, installation equipment and installation techniques.
Introduction
The Mensa development plan utilizes three satellite wells in 5,300 ft water depth, completed with 10,000 psi working pressure, guidelineless, diverless subsea trees producing to a subsea manifold located five miles from the trees. A single main flowline carries the commingled produced fluids from the manifold to a shallow water platform located 63 miles from the manifold. The subsea tree design applied existing guidelineless technology extended to deeper water. A split tree was designed to resist wear and enable retrieval of components subject to erosion wear while leaving the master valves in place. In the first quarter of 1997, the first tree was subjected to the factory acceptance and system integration testing program, which simulated the offshore installation. The first tree installation was completed in July 1997 and the second in September 1997. The third tree is scheduled for installation in May 1998.
Subsea Equipment Overview
The Mensa wells are located in Mississippi Canyon Block687, approximately 140 miles southeast of New Orleans, in 5,300 ft of water. The total offset distance from the subsea trees to the host platform is 68 miles. Three wells were completed using guidelineless diverless subsea trees. Each tree is connected to a subsea manifold via a 6" flowline and a steel tube hydraulic umbilical. The hydraulic umbilical incorporates 7 lines for control of the tree functions and chemical injection. The 6" flowline and hydraulic umbilical were installed using a first end stab & hinge over connection at the manifold and the second end laid down near the tree using terminationsleds with vertical hubs. The distance between the trees and the manifold is approximately 5 miles. The flowline and umbilical connections between the tree and the termination sleds were accomplished using inverted U shaped jumpers, approximately 60 ft long. All stab & hinge over and inverted "U" jumper connections feature ROV operated hydraulic connectors. The subsea manifold accommodates the tie-ins for the three 6" production flowlines and hydraulic umbilical to the subsea trees. The manifold production header connects to the 12" gas export line. The hydraulic umbilical and glycol supply lines also connect to the manifold. A sensor module is installed and there are provisions for connection of a hydrate remediation umbilical. The production control system for the subsea trees is electro-hydraulic. A common electrical umbilical connects the Master Control Station (MCS) on the production platform to the Electrical Distribution Structure (EDS) near the manifold. Separate electrical umbilical link the EDS to each tree control pod and to the manifold. The distance between the manifold and the production platform is approximately 63 miles. A schematic of the subsea production system arrangement is shown in Figure 1.
Title: Mensa Project: Subsea Tree System
Description:
Abstract
This paper describes the design, product development and offshore installation of the subsea trees for the Shell Offshore Inc.
(SOI) Mensa Project.
The Mensa Project represents the world's deepest subsea tree at the time of installation and the longest offset from the host platform.
The extreme water depth, high flow rate and erosion resistance requirements resulted in a number of significant technical advancements in the subsea tree design, installation equipment and installation techniques.
Introduction
The Mensa development plan utilizes three satellite wells in 5,300 ft water depth, completed with 10,000 psi working pressure, guidelineless, diverless subsea trees producing to a subsea manifold located five miles from the trees.
A single main flowline carries the commingled produced fluids from the manifold to a shallow water platform located 63 miles from the manifold.
The subsea tree design applied existing guidelineless technology extended to deeper water.
A split tree was designed to resist wear and enable retrieval of components subject to erosion wear while leaving the master valves in place.
In the first quarter of 1997, the first tree was subjected to the factory acceptance and system integration testing program, which simulated the offshore installation.
The first tree installation was completed in July 1997 and the second in September 1997.
The third tree is scheduled for installation in May 1998.
Subsea Equipment Overview
The Mensa wells are located in Mississippi Canyon Block687, approximately 140 miles southeast of New Orleans, in 5,300 ft of water.
The total offset distance from the subsea trees to the host platform is 68 miles.
Three wells were completed using guidelineless diverless subsea trees.
Each tree is connected to a subsea manifold via a 6" flowline and a steel tube hydraulic umbilical.
The hydraulic umbilical incorporates 7 lines for control of the tree functions and chemical injection.
The 6" flowline and hydraulic umbilical were installed using a first end stab & hinge over connection at the manifold and the second end laid down near the tree using terminationsleds with vertical hubs.
The distance between the trees and the manifold is approximately 5 miles.
The flowline and umbilical connections between the tree and the termination sleds were accomplished using inverted U shaped jumpers, approximately 60 ft long.
All stab & hinge over and inverted "U" jumper connections feature ROV operated hydraulic connectors.
The subsea manifold accommodates the tie-ins for the three 6" production flowlines and hydraulic umbilical to the subsea trees.
The manifold production header connects to the 12" gas export line.
The hydraulic umbilical and glycol supply lines also connect to the manifold.
A sensor module is installed and there are provisions for connection of a hydrate remediation umbilical.
The production control system for the subsea trees is electro-hydraulic.
A common electrical umbilical connects the Master Control Station (MCS) on the production platform to the Electrical Distribution Structure (EDS) near the manifold.
Separate electrical umbilical link the EDS to each tree control pod and to the manifold.
The distance between the manifold and the production platform is approximately 63 miles.
A schematic of the subsea production system arrangement is shown in Figure 1.
Related Results
Mensa Project: An Overview
Mensa Project: An Overview
ABSTRACT
This paper presents an overview of the Shell Offshore Inc. (SOI) Mensa Project, a very remote subsea gas development in 5300 feet of water in the Gulf of...
Mensa Project: Subsea Control System
Mensa Project: Subsea Control System
Abstract
This paper reflects on the development of a subsea production control system for the Mensa Project. It will present the technical challenges encountered ...
Simple Subsea Trees for Shallow Water: An Economical Alternative
Simple Subsea Trees for Shallow Water: An Economical Alternative
Abstract
Simple, diver assisted subsea completions have been installed and operated successfully in many shallow water oil fields around the world. Although these...
Subsea Factory–Standardization of the Brownfield Factory
Subsea Factory–Standardization of the Brownfield Factory
Abstract
As part of the corporate technology strategy Statoil has launched a technology plan for the Subsea Factory concept. The plan describes how to combine subsea...
Ormen Lange Subsea Production System
Ormen Lange Subsea Production System
Abstract
This paper presents the concept and the technical solutions developed and applied to the Ormen Lange subsea production system. First, the key technical c...
Inspection of Subsea Conductors Using an Innovative Drop-Down Camera
Inspection of Subsea Conductors Using an Innovative Drop-Down Camera
Abstract
Subsea conductors are the foundational elements of offshore drilling operations, serving a dual purpose as both the structural framework and the main condui...
Technology Focus: Subsea Systems (August 2025)
Technology Focus: Subsea Systems (August 2025)
_
From a broader and high-level perspective—considering importance, impact, significance, and criticality—subsea systems and advanced offshore engineering play an...
Evolution Of Subsea Production Systems: A Worldwide Overview
Evolution Of Subsea Production Systems: A Worldwide Overview
ABSTRACT
The evolution in the use of subsea technology has seen advancement -from I well in the Gulf of Mexico in 1961 to over 750 wells in a tide variety of loca...

