Benguela-Belize Compliant Piled Tower: Tower Fabrication

View through CrossRef
Abstract Kiewit Offshore Services, Ltd. (KOS) was subcontracted by DSME to fabricate two of the major components of the Benguela-Belize Compliant Piled Tower (CPT). KOS' work scope included the fabrication and loadout of the Tower Base Template (TBT) weighing 3,200 tons and the Tower Base Section (TBS) weighing 28,000 tons. Materials used in the fabrication of the TBT and TBS included high-end API grade plates and tubulars. KOS used German, Japanese, and domestic steel mills to supply the tower material. The TBS and TBT were divided into several major subassemblies weighing from 100 to 2,000 tons. Subassembly components such as tower legs and flex legs were fabricated by domestic subcontractors and required intense subcontract coordination efforts. Due to the offshore installation window, the fabrication schedule was critical from beginning of the project and had to be accelerated to meet the delivery date. Dimensional control was a major fabrication effort and required extensive involvement and coordination between all parties involved to achieve acceptable tolerances. Given the aggressive fabrication schedule, all the riser joints and field splice coatings were applied in the air, resulting in a critical path activity which had its own unique set of challenges. KOS loaded out the TBT using self-propelled modular transporters. Due to the heavy weight of the TBS, KOS utilized strand jacks in a skidding operation to loadout thestructure onto Heerema's H-851 launch barge. Production KOS was responsible for the procurement, fabrication, loadout and sefastening of the Tower Base Section (TBS) and Tower Base Template (TBT) structures of the CPT. KOS' traditional safety program combined with Chevron's Incident and Injury Free (IIF) program resulted in a strong safety performance on an extremely fast track project. Committed to constructing a quality product, the KOS project team implemented these new programs:ekly client quality meetingsaft Quality Tool Box meetingslity stand-downs The TBS structure was 110' × 110' square, 830' long and weighed 28,000 tons. The structure consisted primarily of tubular members ranging in size from 16' to 144' in diameter, with wall thicknesses up to 4'. In addition to four main legs, the TBS had twelve pre-installed flex legs starting from Elev. (-) 485' and extending down to Elev. (-) 1,216'. These flex legs were attached to the tower main legs at the top via shear and yoke plate assemblies. Additionally, each flex leg was freely supported by a series of eight flex leg guides, which were evenly spaced along the main legs. The TBS structure is illustrated in Figure 1. The TBT structure was 110' × 110' square, 46' tall and weighed 3,200 tons. This structure had four main and four dummy legs, which were 72' in diameter with wall thicknesses up to 3.5'. Additionally, there were twelve pile sleeves (119' in diameter with wall thicknesses up to 3.5') which were connected to the main legs via short horizontal and diagonal braces. This structure was constructed and loaded out in an upright position.
Title: Benguela-Belize Compliant Piled Tower: Tower Fabrication
Description:
Abstract Kiewit Offshore Services, Ltd.
(KOS) was subcontracted by DSME to fabricate two of the major components of the Benguela-Belize Compliant Piled Tower (CPT).
KOS' work scope included the fabrication and loadout of the Tower Base Template (TBT) weighing 3,200 tons and the Tower Base Section (TBS) weighing 28,000 tons.
Materials used in the fabrication of the TBT and TBS included high-end API grade plates and tubulars.
KOS used German, Japanese, and domestic steel mills to supply the tower material.
The TBS and TBT were divided into several major subassemblies weighing from 100 to 2,000 tons.
Subassembly components such as tower legs and flex legs were fabricated by domestic subcontractors and required intense subcontract coordination efforts.
Due to the offshore installation window, the fabrication schedule was critical from beginning of the project and had to be accelerated to meet the delivery date.
Dimensional control was a major fabrication effort and required extensive involvement and coordination between all parties involved to achieve acceptable tolerances.
Given the aggressive fabrication schedule, all the riser joints and field splice coatings were applied in the air, resulting in a critical path activity which had its own unique set of challenges.
KOS loaded out the TBT using self-propelled modular transporters.
Due to the heavy weight of the TBS, KOS utilized strand jacks in a skidding operation to loadout thestructure onto Heerema's H-851 launch barge.
Production KOS was responsible for the procurement, fabrication, loadout and sefastening of the Tower Base Section (TBS) and Tower Base Template (TBT) structures of the CPT.
KOS' traditional safety program combined with Chevron's Incident and Injury Free (IIF) program resulted in a strong safety performance on an extremely fast track project.
Committed to constructing a quality product, the KOS project team implemented these new programs:ekly client quality meetingsaft Quality Tool Box meetingslity stand-downs The TBS structure was 110' × 110' square, 830' long and weighed 28,000 tons.
The structure consisted primarily of tubular members ranging in size from 16' to 144' in diameter, with wall thicknesses up to 4'.
In addition to four main legs, the TBS had twelve pre-installed flex legs starting from Elev.
(-) 485' and extending down to Elev.
(-) 1,216'.
These flex legs were attached to the tower main legs at the top via shear and yoke plate assemblies.
Additionally, each flex leg was freely supported by a series of eight flex leg guides, which were evenly spaced along the main legs.
The TBS structure is illustrated in Figure 1.
The TBT structure was 110' × 110' square, 46' tall and weighed 3,200 tons.
This structure had four main and four dummy legs, which were 72' in diameter with wall thicknesses up to 3.
5'.
Additionally, there were twelve pile sleeves (119' in diameter with wall thicknesses up to 3.
5') which were connected to the main legs via short horizontal and diagonal braces.
This structure was constructed and loaded out in an upright position.

Related Results

Benguela-Belize Compliant Piled Tower: Tower Design
Benguela-Belize Compliant Piled Tower: Tower Design
Abstract The compliant tower is a proven bottom-founded platform which has been used successfully for three developments in the Gulf of Mexico. The compliant towe...
Project-Focused Approach Facilitates Benguela-Belize Success
Project-Focused Approach Facilitates Benguela-Belize Success
Abstract From the outset of the Benguela-Belize Compliant Piled Tower project, the Gulf Marine Fabricators (GMF) management team established a target of finding a...
Benguela-Belize Project Overview
Benguela-Belize Project Overview
Abstract The Benguela-Belize Project, an oil and gas production development located in the northern part of Block 14, offshore Angola, West Africa, is the first a...
Effect of ground subsidence on piled raft foundation
Effect of ground subsidence on piled raft foundation
Extensive researches for piled rafts have been performed but the evaluation of their behavior in ground subsidence condition is still a challenge. In this study, centrifugal tests ...
Constraint-Force-Based (CFB) Modeling of Compliant Mechanisms
Constraint-Force-Based (CFB) Modeling of Compliant Mechanisms
Numerous works have been done on modeling compliant modules or joints, and the closed-form models of many widely-used compliant modules have been developed. However, the modeling o...
The Delta Tower: A Light, Compliant Tower for the Gulf of Mexico
The Delta Tower: A Light, Compliant Tower for the Gulf of Mexico
ABSTRACT The concept which is described in the paper is applicable to fields located in the Gulf of Mexico in water depths ranging from 1 000 to 1 750 feet. The c...
Geochemical sourcing of granite ground stone tools from Belize
Geochemical sourcing of granite ground stone tools from Belize
<p>Portable X-ray fluorescence (pXRF) provides a new alternative to destructive methods of raw material characterization, such as X-ray fluorescence (XRF), neutron activation...
Lena Guyed Tower Project Overview
Lena Guyed Tower Project Overview
ABSTRACT The installation of the Lena guyed tower was one of the industry's most significant accomplishments of 1983. This paper serves as an introduction to a se...

Back to Top