Javascript must be enabled to continue!
EkofisK Oil and Gas Pipeline Construction
View through CrossRef
American Institute of Mining, Metallurgical, and Petroleum Engineers, Inc.
Abstract
Phillips Petroleum Co. Norway is constructing a 220-mile, 1-million BOPD pipeline from Ekofisk to Teesside, England, pipeline from Ekofisk to Teesside, England, and a 274.5-mile, 2.3-Bcf/D gas pipeline from Ekofisk to Emden, Germany. Peach pipeline will have two intermediate booster pipeline will have two intermediate booster platforms. Both lines are laid and only platforms. Both lines are laid and only tie-in work, testing and booster platforms erection remain to be completed.
Introduction
Phillips Petroleum Co. Norway, operators of the Phillips Norway Group, acting on behalf of Norpipe A/S, is entering the final stages of completion for their oil and gas pipelines in the North Sea. Four hundred ninety-four and a half miles of large-diameter pipe was laid during the 1973 and 1974 lay season. Of this amount, 466 miles was marine pipeline. The 34-in. OD, 220-mile oil pipeline from Ekofisk to Teesside, England, has a capacity of 1 million BOPD and the 36-in., 274.5-mile gas pipeline from Ekofisk to Emden, Germany, has a capacity of 2.28 Bcf/D. Both the oil and gas pipelines are owned by Norpipe A/S, a 50–50 joint venture of the Phillips Group and Statoil, the Norwegian Phillips Group and Statoil, the Norwegian national oil company. The Phillips Group consists of Phillips Petroleum Co. Norway, 36.960 percent, American Petrofina Exploration Co. Norway, 30-000 percent, Norsk Agip A/S, 13.040 percent, Norsk Hydro A/S, 6.700 percent, Elf Norge A/S, 5.396 percent, Total Marine Norsk A/S, 4.047 percent, Aquitaine Norge A/S, 2.698 percent, Eurafrep Norge A/S, 0.456 percent, percent, Eurafrep Norge A/S, 0.456 percent, Coparex Norge, 0.399 percent, and Cofranord A/S, 0.304 percent.
The Phillips Norway Group's Ekofisk field, discovered in 1969, was the first of the giant North Sea discoveries. Later discoveries of six adjoining fields by the group confirmed the fact that the huge reserves of oil and gas could only be transported by pipeline. Late in 1970, three possible routes were surveyed, to Norway, Germany and England. The deep trench offshore Norway shown in the survey complicated transporting the oil to Norway as called for in the license agreement. The trench was 1,100 ft deep and the state of the art for marine pipe lay barges had not progressed to the point where it was feasible to lay and trench large-diameter pipelines in this depth. pipelines in this depth. The Ekofisk to Teesside crude oil pipeline consists of approximately 216 miles of 34-in. OD by 0.719-in. wall thickness API 5LX Grade X-60 pipe in the marine portion of the line, and approximately 4 miles of 34-in. OD by 0.812-in. wall thickness API 5LX Grade X-60 pipe from the land point to the Teesside processing plant. Initial pumping equipment consists of three General Electric Frame 3 gas-fired combustion turbines driving Bingham centrifugal pumps installed on "P" platform at Ekofisk that will deliver a maximum of 542,400 BOPD to Teesside. Two intermediate booster platforms (37/4A and 36/22A) will be installed. In the first phase of operation these platforms will have shutoff valves, scraper launching and receiving
Title: EkofisK Oil and Gas Pipeline Construction
Description:
American Institute of Mining, Metallurgical, and Petroleum Engineers, Inc.
Abstract
Phillips Petroleum Co.
Norway is constructing a 220-mile, 1-million BOPD pipeline from Ekofisk to Teesside, England, pipeline from Ekofisk to Teesside, England, and a 274.
5-mile, 2.
3-Bcf/D gas pipeline from Ekofisk to Emden, Germany.
Peach pipeline will have two intermediate booster pipeline will have two intermediate booster platforms.
Both lines are laid and only platforms.
Both lines are laid and only tie-in work, testing and booster platforms erection remain to be completed.
Introduction
Phillips Petroleum Co.
Norway, operators of the Phillips Norway Group, acting on behalf of Norpipe A/S, is entering the final stages of completion for their oil and gas pipelines in the North Sea.
Four hundred ninety-four and a half miles of large-diameter pipe was laid during the 1973 and 1974 lay season.
Of this amount, 466 miles was marine pipeline.
The 34-in.
OD, 220-mile oil pipeline from Ekofisk to Teesside, England, has a capacity of 1 million BOPD and the 36-in.
, 274.
5-mile gas pipeline from Ekofisk to Emden, Germany, has a capacity of 2.
28 Bcf/D.
Both the oil and gas pipelines are owned by Norpipe A/S, a 50–50 joint venture of the Phillips Group and Statoil, the Norwegian Phillips Group and Statoil, the Norwegian national oil company.
The Phillips Group consists of Phillips Petroleum Co.
Norway, 36.
960 percent, American Petrofina Exploration Co.
Norway, 30-000 percent, Norsk Agip A/S, 13.
040 percent, Norsk Hydro A/S, 6.
700 percent, Elf Norge A/S, 5.
396 percent, Total Marine Norsk A/S, 4.
047 percent, Aquitaine Norge A/S, 2.
698 percent, Eurafrep Norge A/S, 0.
456 percent, percent, Eurafrep Norge A/S, 0.
456 percent, Coparex Norge, 0.
399 percent, and Cofranord A/S, 0.
304 percent.
The Phillips Norway Group's Ekofisk field, discovered in 1969, was the first of the giant North Sea discoveries.
Later discoveries of six adjoining fields by the group confirmed the fact that the huge reserves of oil and gas could only be transported by pipeline.
Late in 1970, three possible routes were surveyed, to Norway, Germany and England.
The deep trench offshore Norway shown in the survey complicated transporting the oil to Norway as called for in the license agreement.
The trench was 1,100 ft deep and the state of the art for marine pipe lay barges had not progressed to the point where it was feasible to lay and trench large-diameter pipelines in this depth.
pipelines in this depth.
The Ekofisk to Teesside crude oil pipeline consists of approximately 216 miles of 34-in.
OD by 0.
719-in.
wall thickness API 5LX Grade X-60 pipe in the marine portion of the line, and approximately 4 miles of 34-in.
OD by 0.
812-in.
wall thickness API 5LX Grade X-60 pipe from the land point to the Teesside processing plant.
Initial pumping equipment consists of three General Electric Frame 3 gas-fired combustion turbines driving Bingham centrifugal pumps installed on "P" platform at Ekofisk that will deliver a maximum of 542,400 BOPD to Teesside.
Two intermediate booster platforms (37/4A and 36/22A) will be installed.
In the first phase of operation these platforms will have shutoff valves, scraper launching and receiving.
Related Results
Reservoir Aspects Of Ekofisk Subsidence
Reservoir Aspects Of Ekofisk Subsidence
ABSTRACT
In November 1984 Phillips Petroleum Company discovered subsidence of the seabed overlying the Ekofisk oil reservoirs offshore Norway. This phenomenon is ...
Ekofisk II - Planning for Low Operating Costs Through Lifetime
Ekofisk II - Planning for Low Operating Costs Through Lifetime
Abstract
The age of the existing Ekofisk platforms, together with the fact that they are sinking due to subsidence caused by compaction of the reservoir formation...
Structural Reliability Assessment of Ekofisk Jackets Under Extreme Loading
Structural Reliability Assessment of Ekofisk Jackets Under Extreme Loading
Abstract
Seabed subsidence increases the probability that the crests of extreme waves will impact platform deck structures. In the years since significant subside...
Development Program for Ekofisk Field - Offshore Norway
Development Program for Ekofisk Field - Offshore Norway
Abstract
The Phillips Group discovered the Ekofisk field on the Norwegian Continental Shelf of the North Sea with the drilling of the Ekofisk IAX late 1969. Three...
Installation Analysis of Matterhorn Pipeline Replacement
Installation Analysis of Matterhorn Pipeline Replacement
Abstract
The paper describes the installation analysis for the Matterhorn field pipeline replacement, located in water depths between 800-ft to 1200-ft in the Gul...
Remotely Controlled Pipeline Isolation Plugs
Remotely Controlled Pipeline Isolation Plugs
Abstract
Often subsea pipelines require planned shutdown/intervention due to repair, rerouting, addition of valves, etc. The negative economic impact can be drama...
Potentials of GIS-based analyses of Ajaokuta -Kaduna-Kano gas pipeline in Nigeria
Potentials of GIS-based analyses of Ajaokuta -Kaduna-Kano gas pipeline in Nigeria
Abstract. Geographic and Information System (GIS) Potentials and emerging technologies in overcoming topographic challenges during construction of Ajaokuta-Kaduna-Kano (AKK) gas pi...
The Development History Of Greater Ekofisk
The Development History Of Greater Ekofisk
Abstract
The Ekofisk Field, discovered in 1969, at a time when exploratory interest in the hostile North Sea was beginning to wane, marked the beginning of a new ...

