Computational Study of N-Job M-Machine Flow Shop Scheduling Problems: SPT, EDD, NEH, NEH-EDD, and Modified-NEH Algorithms

View through CrossRef
This paper discusses about the flow shop scheduling problems using shortest processing time, earliest due date (EDD), Nawaz, Enscore, and Ham (NEH), NEH-EDD, and modified-NEH methods. The objective of this research is to determine the performance of these methods in minimizing makespan and total tardiness. Processing times and due dates were randomly generated, and computational studies were performed in Microsoft Visual Basic 6.0. The experiments are performed for small and medium data sets. Efficiency index, relative error, and run time measure the performance of each method. Experimental results showed that NEH has the best performance in minimizing the makespan in both data sets; these are 53.35 time unit for small data sets and 83.803 time unit for medium data sets. NEH-EDD has the best performance in minimizing total tardiness with 9.37 time unit for small data sets and 231.02 time unit for medium data sets. Modified-NEH, as the proposed method for minimizing makespan and total tardiness at the same time, has good enough result. For minimizing the makespan, modified-NEH results in 57.15 time unit for small data sets and 88.107 time unit for medium data sets. For minimizing total tardiness, the modified-NEH results in 14.21 time unit for small data sets and 246.57 time unit for medium sets.
Title: Computational Study of N-Job M-Machine Flow Shop Scheduling Problems: SPT, EDD, NEH, NEH-EDD, and Modified-NEH Algorithms
Description:
This paper discusses about the flow shop scheduling problems using shortest processing time, earliest due date (EDD), Nawaz, Enscore, and Ham (NEH), NEH-EDD, and modified-NEH methods.
The objective of this research is to determine the performance of these methods in minimizing makespan and total tardiness.
Processing times and due dates were randomly generated, and computational studies were performed in Microsoft Visual Basic 6.
The experiments are performed for small and medium data sets.
Efficiency index, relative error, and run time measure the performance of each method.
Experimental results showed that NEH has the best performance in minimizing the makespan in both data sets; these are 53.
35 time unit for small data sets and 83.
803 time unit for medium data sets.
NEH-EDD has the best performance in minimizing total tardiness with 9.
37 time unit for small data sets and 231.
02 time unit for medium data sets.
Modified-NEH, as the proposed method for minimizing makespan and total tardiness at the same time, has good enough result.
For minimizing the makespan, modified-NEH results in 57.
15 time unit for small data sets and 88.
107 time unit for medium data sets.
For minimizing total tardiness, the modified-NEH results in 14.
21 time unit for small data sets and 246.
57 time unit for medium sets.

Related Results

Work Values
Work Values
Research has identified TV series and, also more recently social media, as different actors in vocational socialization, providing individuals with career-related information (Levi...
FLOW SHOP SCHEDULING BASED ON PALMER-NEH, GUPTA-NEH AND DANNENBRING-NEH ALGORITHMS TO MINIMIZE THE ENERGY COST
FLOW SHOP SCHEDULING BASED ON PALMER-NEH, GUPTA-NEH AND DANNENBRING-NEH ALGORITHMS TO MINIMIZE THE ENERGY COST
In the manufacturing industry, the most widely used equipment is equipment that uses electricity. Electricity cost is one of the highest operational production costs after labor co...
Standard Penetration Test in Malaysia: Safety Issues and Improvement Opportunities
Standard Penetration Test in Malaysia: Safety Issues and Improvement Opportunities
Standard Penetration Test (SPT) is the most frequently used field test for site investigation where drilling work is performed in-situ to determine properties of geomaterials for a...
ANALISIS PELAPORAN SPT TAHUNAN BADAN PADA CV JS MELALUI E-FORM 1771
ANALISIS PELAPORAN SPT TAHUNAN BADAN PADA CV JS MELALUI E-FORM 1771
In an effort to enhance taxpayer compliance, the Directorate General of Taxes (DJP) has implemented a new innovation in the tax administration system, namely e-form. This study aim...
Real time scheduling system (RTSS)
Real time scheduling system (RTSS)
Traditional research in Job Shop Scheduling (JSS) is largely based on combinatorial analysis. Unfortunately, the NP-complete nature of the problem forces many assumptions into exis...
JOB DEMANDS DAN JOB RESOURCES (JD-R) PENGARUHNYA TERHADAP PRODUKTIVITAS KARYAWAN
JOB DEMANDS DAN JOB RESOURCES (JD-R) PENGARUHNYA TERHADAP PRODUKTIVITAS KARYAWAN
            Produktivitas karyawan yang stabil dan sesuai target adalah merupakan faktor yang sangat penting untuk menjaga  kelangsungan hidup perusahaan tetapi  untuk menciptakan ...

Back to Top