Search engine for discovering works of Art, research articles, and books related to Art and Culture
ShareThis
Javascript must be enabled to continue!

Optimisation of tower crane rotation mechanism force acceleration mode at steady payload hoisting

View through CrossRef
The process of optimisation of the force acceleration mode of the rotation mechanism of the tower crane with the beam jib at steady payload hoisting was examined in the presented paper. The crane rotation mechanism was presented as a dynamic model with 4DOF in which the main motion of the rotation and payload hoisting mechanisms is considered as well as oscillations of the rotation part of the crane and the payload in the plane of slew. For such a dynamic model, a mathematical model which is a system of ordinary second order differential equations was formulated. The system of equations was reduced to the angular coordinate of the payload slew and was represented by the sixth order equation. The optimisation of the rotation mechanism’s acceleration mode at steady payload hoisting was carried out based on the RMS of the drive torque criterion considering constraints on the drive torque and drive power. The optimisation criterion as well as the constraints were reduced to the generalised criterion. When optimising , the movements and velocities of the generalised rotation mechanism coordinates in the beginning and in the end of the acceleration process were chosen as motion boundary conditions. The acceleration mode of the crane rotation mechanism at steady payload hoisting was obtained as the result of optimisation. The obtained mode minimised the action of the dynamic payloads and decreases the maximum values of the crane’s mast deformation, drive power, and deviation of the payload cable from the vertical. At that, the crane’s elements’ and payload’s oscillations upon reaching the steady motion mode were eliminated. The results of the study may be used in automation systems for controlling the rotation mechanisms of tower cranes, which ensures improved efficiency and stability of work during payloads hoisting
Title: Optimisation of tower crane rotation mechanism force acceleration mode at steady payload hoisting
Description:
The process of optimisation of the force acceleration mode of the rotation mechanism of the tower crane with the beam jib at steady payload hoisting was examined in the presented paper.
The crane rotation mechanism was presented as a dynamic model with 4DOF in which the main motion of the rotation and payload hoisting mechanisms is considered as well as oscillations of the rotation part of the crane and the payload in the plane of slew.
For such a dynamic model, a mathematical model which is a system of ordinary second order differential equations was formulated.
The system of equations was reduced to the angular coordinate of the payload slew and was represented by the sixth order equation.
The optimisation of the rotation mechanism’s acceleration mode at steady payload hoisting was carried out based on the RMS of the drive torque criterion considering constraints on the drive torque and drive power.
The optimisation criterion as well as the constraints were reduced to the generalised criterion.
When optimising , the movements and velocities of the generalised rotation mechanism coordinates in the beginning and in the end of the acceleration process were chosen as motion boundary conditions.
The acceleration mode of the crane rotation mechanism at steady payload hoisting was obtained as the result of optimisation.
The obtained mode minimised the action of the dynamic payloads and decreases the maximum values of the crane’s mast deformation, drive power, and deviation of the payload cable from the vertical.
At that, the crane’s elements’ and payload’s oscillations upon reaching the steady motion mode were eliminated.
The results of the study may be used in automation systems for controlling the rotation mechanisms of tower cranes, which ensures improved efficiency and stability of work during payloads hoisting.

Related Results

Optimization of the joint startup of the boom and load hoisting mechanisms of a jib crane
Optimization of the joint startup of the boom and load hoisting mechanisms of a jib crane
During the joint motion of the boom and load hoisting mechanisms, dynamic loads increase, leading to additional energy consumption, which subsequently contributes to the deteriorat...
OPTIMALISASI LETAK TOWER CRANE TERHADAP WAKTU SIKLUS PADA PROYEK Y
OPTIMALISASI LETAK TOWER CRANE TERHADAP WAKTU SIKLUS PADA PROYEK Y
In a construction project, there are various kinds of very complex activities. Therefore, heavy equipment, especially Tower Cranes is used to assist the work on the construction pr...
Operational Dynamics Of An Offshore Crane
Operational Dynamics Of An Offshore Crane
Abstract A computational method is described for calculating the detailed dynamics of fixed offshore platform cranes based on finite element techniques. The metho...
Optimasi Penempatan Tower Crane terhadap Waktu Siklus pada Proyek X
Optimasi Penempatan Tower Crane terhadap Waktu Siklus pada Proyek X
ABSTRAKKegiatan konstruksi adalah suatu rangkaian kegiatan yang saling berkaitan dan mempunyai tujuan tertentu. Tujuan dari proyek konstruksi adalah mampu merealisasikan kegiatan p...
Control of a Multimode Double-Pendulum Overhead Crane System Using Input Shaping Controllers
Control of a Multimode Double-Pendulum Overhead Crane System Using Input Shaping Controllers
This paper investigates the impact of higher derivative input shaping for minimizing both oscillations, namely hook and payload of a multimode double-pendulum overhead crane (MDPOC...
Crane Load Moment System For Offshore Crane Operations
Crane Load Moment System For Offshore Crane Operations
Abstract History has shown that dependency upon the crane operator to monitor loads and boom angle or load radius do not allow the margin necessary to perform the...
GNSS-Based High-Precision Fixed-Point and Lofting of Hoisting Operation for Construction Tower Crane
GNSS-Based High-Precision Fixed-Point and Lofting of Hoisting Operation for Construction Tower Crane
GNSS receiver is one of novel sensors applied to accurate management and control technology for the construction tower crane. Since the low-precision of m-level navigation applicat...
PENENTUAN LOKASI TOWER CRANE PADA PROYEK KONSTRUKSI BERBASIS SIMULASI
PENENTUAN LOKASI TOWER CRANE PADA PROYEK KONSTRUKSI BERBASIS SIMULASI
Development of high-level building construction projects that require complex equipment that can be used in high-level construction, equipment used to help complete construction pr...

Back to Top