Search engine for discovering works of Art, research articles, and books related to Art and Culture
ShareThis
Javascript must be enabled to continue!

Snorre Subsea Production System

View through CrossRef
ABSTRACT Saga Petroleum will make extensive use of subsea systems to develop the Snorre Field. Of the planned 46 wells needed for the field's first phase development, 10 will be subsea wells. Another 47 subsea wells may be added during the second phase development, bringing the total to possibly 57 subsea wells. The Snorre Subsea Production System was previously described in OTC paper 62021. This follow-up paper expands the discussion of the system with emphasis on some of the more innovative aspects of the design. Specific issues addressed are: guideline-less drilling and completion system, the manifold system, control system, TFL well-servicing, and the remotely operated maintenance vehicle which will be used to maintain the manifold and control system components. DESCRIPTION The Snorre Subsea template system is shown in Fig. 1, which identifies the various sub-systems that comprise the template system. The 10 + 10 template will develop 20 wells, but only 10 at a given time. As a well is depleted it can be abandoned and replaced with another drilled through the same template. The template system is 48 metres long, 32 metres wide, and (including the 3 metre skirts) 19 metres tall. As installed, with the manifold sub-system (but not the well bay equipment, which will be installed as the wells are drilled) it weighs approximately 2500 tonnes in air. It will be installed by a heavy lift crane vessel in 335 metres water depth, 6 kilometres NE of the Snorre TLP. The template structure is a truss structure made primarily of large diameter tubulars. It features upright sections that provide separating walls between the well slots. These walls, which give the template the appearance of an English "toast rack," serve to protect the adjacent equipment during drilling and installation operations in the adjoining well slot and also are used for guidance of equipment into the well slot. DRILLING AND COMPLETION Immediately after the template is installed it will be leveled by pressuring or applying suction to the skirted mud-mat compartments. Thirty-inch conductions will then be installed in the four corner well slots to stabilize the template. The remaining 6 conductors will then be drilled, cemented, and locked to the template wellguides to complete the foundation. Conventional drilling and completion equipment and casing programs will be used for the Snorre subsea wells, with the exception that guideline-less techniques will be used to install equipment. As previously mentioned, the "toast-racks" play an important role in the guideline-less system. Figure 2 shows a cut-away view of a well slot. One of the two "toast-rack" members is illustrated with its "bumper," the "well guards," and the two drilling guides, that are in each well slot. The bumper, including the corresponding one on the other "toast rack" that has been cut away, interact with bumper plates mounted on the BOP's alignment structure and the tree's alignment structure to position the equipment for installation on the wellhead.
Title: Snorre Subsea Production System
Description:
ABSTRACT Saga Petroleum will make extensive use of subsea systems to develop the Snorre Field.
Of the planned 46 wells needed for the field's first phase development, 10 will be subsea wells.
Another 47 subsea wells may be added during the second phase development, bringing the total to possibly 57 subsea wells.
The Snorre Subsea Production System was previously described in OTC paper 62021.
This follow-up paper expands the discussion of the system with emphasis on some of the more innovative aspects of the design.
Specific issues addressed are: guideline-less drilling and completion system, the manifold system, control system, TFL well-servicing, and the remotely operated maintenance vehicle which will be used to maintain the manifold and control system components.
DESCRIPTION The Snorre Subsea template system is shown in Fig.
1, which identifies the various sub-systems that comprise the template system.
The 10 + 10 template will develop 20 wells, but only 10 at a given time.
As a well is depleted it can be abandoned and replaced with another drilled through the same template.
The template system is 48 metres long, 32 metres wide, and (including the 3 metre skirts) 19 metres tall.
As installed, with the manifold sub-system (but not the well bay equipment, which will be installed as the wells are drilled) it weighs approximately 2500 tonnes in air.
It will be installed by a heavy lift crane vessel in 335 metres water depth, 6 kilometres NE of the Snorre TLP.
The template structure is a truss structure made primarily of large diameter tubulars.
It features upright sections that provide separating walls between the well slots.
These walls, which give the template the appearance of an English "toast rack," serve to protect the adjacent equipment during drilling and installation operations in the adjoining well slot and also are used for guidance of equipment into the well slot.
DRILLING AND COMPLETION Immediately after the template is installed it will be leveled by pressuring or applying suction to the skirted mud-mat compartments.
Thirty-inch conductions will then be installed in the four corner well slots to stabilize the template.
The remaining 6 conductors will then be drilled, cemented, and locked to the template wellguides to complete the foundation.
Conventional drilling and completion equipment and casing programs will be used for the Snorre subsea wells, with the exception that guideline-less techniques will be used to install equipment.
As previously mentioned, the "toast-racks" play an important role in the guideline-less system.
Figure 2 shows a cut-away view of a well slot.
One of the two "toast-rack" members is illustrated with its "bumper," the "well guards," and the two drilling guides, that are in each well slot.
The bumper, including the corresponding one on the other "toast rack" that has been cut away, interact with bumper plates mounted on the BOP's alignment structure and the tree's alignment structure to position the equipment for installation on the wellhead.

Related Results

Ormen Lange Subsea Production System
Ormen Lange Subsea Production System
Abstract This paper presents the concept and the technical solutions developed and applied to the Ormen Lange subsea production system. First, the key technical c...
Subsea Factory–Standardization of the Brownfield Factory
Subsea Factory–Standardization of the Brownfield Factory
Abstract As part of the corporate technology strategy Statoil has launched a technology plan for the Subsea Factory concept. The plan describes how to combine subsea...
Subsea Facilities
Subsea Facilities
Abstract This paper presents the system design and concept solutions selected for the Ormen Lange subsea facilities. The field is located in a r...
Snorre Subsea Tree and Completion Equipment
Snorre Subsea Tree and Completion Equipment
ABSTRACT The Snorre Subsea Production System (SPS) is an innovative 10 + 10 well facility which will be tied back to the Snorre tension leg platform (Figure 1). The ...
Snorre Project Strategies and Status
Snorre Project Strategies and Status
ABSTRACT The Snorre development is one of the most challenging projects carried out in the Norwegian North Sea since the pioneering days of the early and mid 1970...
Implementing Deepwater Subsea Reliability Strategy
Implementing Deepwater Subsea Reliability Strategy
Abstract For more than a decade, subsea technology has been perceived as delivering innovative, reliable and cost effective solutions to oil & gas exploitatio...
Design, Installation, And Connection Of Subsea Lines On East Frigg Field
Design, Installation, And Connection Of Subsea Lines On East Frigg Field
ABSTRACT This paper describes the subsea network which interconnects the three subsea templates at EAST FRIGG field, and connects this field to the FRIGG field, 1...
Subsea Production Controls-The Trend Toward Simplification
Subsea Production Controls-The Trend Toward Simplification
Abstract Control of subsea wellheads has evolved from the earliest diver operated wellheads to systems involving sophisticated electro-hydraulic techniques. With ...

Back to Top