Search engine for discovering works of Art, research articles, and books related to Art and Culture
ShareThis
Javascript must be enabled to continue!

Snorre Subsea Tree and Completion Equipment

View through CrossRef
ABSTRACT The Snorre Subsea Production System (SPS) is an innovative 10 + 10 well facility which will be tied back to the Snorre tension leg platform (Figure 1). The Snorre SPS (Figure 2) will be installed in 1100 ft (335 m) of water, 93 miles (150 km) off the west coast of Norway in the northern sector of the North Sea2. The SPS installation is scheduled for the spring of 1992, with drilling and completion of the first subsea well slated for the fall of 1992. In general, field-proven components have been used wherever possible, with new technology being extensively verified and tested prior to installation. To the extent practical, the drilling and completion equipment designs also use field-proven components. These components have been combined in a unique manner to produce a safe and reliable system which: (1) employs guidelineless, remotely-operated techniques for deployment, installation, and retrieval of the various subsea modules, (2) provides through flow line (TFL) maintenance capability, (3) uses metal seals and welded constructions for connections on permanently-installed equipment, (4) minimizes the number of hydraulic functions on the subsea tree, and (5) has been specifically designed to enhance the safety of simultaneous drilling and production operations. This paper explains the basic design features of the Snorre subsea tree and completion equipment. In addition, a brief description of the equipment is provided.
Title: Snorre Subsea Tree and Completion Equipment
Description:
ABSTRACT The Snorre Subsea Production System (SPS) is an innovative 10 + 10 well facility which will be tied back to the Snorre tension leg platform (Figure 1).
The Snorre SPS (Figure 2) will be installed in 1100 ft (335 m) of water, 93 miles (150 km) off the west coast of Norway in the northern sector of the North Sea2.
The SPS installation is scheduled for the spring of 1992, with drilling and completion of the first subsea well slated for the fall of 1992.
In general, field-proven components have been used wherever possible, with new technology being extensively verified and tested prior to installation.
To the extent practical, the drilling and completion equipment designs also use field-proven components.
These components have been combined in a unique manner to produce a safe and reliable system which: (1) employs guidelineless, remotely-operated techniques for deployment, installation, and retrieval of the various subsea modules, (2) provides through flow line (TFL) maintenance capability, (3) uses metal seals and welded constructions for connections on permanently-installed equipment, (4) minimizes the number of hydraulic functions on the subsea tree, and (5) has been specifically designed to enhance the safety of simultaneous drilling and production operations.
This paper explains the basic design features of the Snorre subsea tree and completion equipment.
In addition, a brief description of the equipment is provided.

Related Results

Snorre Subsea Production System
Snorre Subsea Production System
ABSTRACT Saga Petroleum will make extensive use of subsea systems to develop the Snorre Field. Of the planned 46 wells needed for the field's first phase developm...
Mensa Project: Subsea Tree System
Mensa Project: Subsea Tree System
Abstract This paper describes the design, product development and offshore installation of the subsea trees for the Shell Offshore Inc. (SOI) Mensa Project. The M...
Subsea Factory–Standardization of the Brownfield Factory
Subsea Factory–Standardization of the Brownfield Factory
Abstract As part of the corporate technology strategy Statoil has launched a technology plan for the Subsea Factory concept. The plan describes how to combine subsea...
A New Approach to Completing a Previously Drilled Subsea Well
A New Approach to Completing a Previously Drilled Subsea Well
ABSTRACT Offshore operators tie successful subsea exploratory wells into field plans when possible and have used a variety of adaptation bases to complete the wel...
Ormen Lange Subsea Production System
Ormen Lange Subsea Production System
Abstract This paper presents the concept and the technical solutions developed and applied to the Ormen Lange subsea production system. First, the key technical c...
High Voltage Subsea Pump – A Low Cost Subsea Boosting Enabler
High Voltage Subsea Pump – A Low Cost Subsea Boosting Enabler
In a cost constrained scenario, technology driven solutions aiming at CAPEX reductions are crucial to make Subsea Processing (SSP) projects economically attractive. Subsea Processi...
Deep Water X-mas Tree Standardization -- Interchangeability Approach
Deep Water X-mas Tree Standardization -- Interchangeability Approach
ABSTRACT Aiming the rationalization of subsea operations to turn the production of oil and gas more economical and reliable, standardization of subsea equipment i...
Technology Focus: Subsea Systems (August 2025)
Technology Focus: Subsea Systems (August 2025)
_ From a broader and high-level perspective—considering importance, impact, significance, and criticality—subsea systems and advanced offshore engineering play an...

Back to Top