THE NEW GREENLINK 500 MW INTERCONNECTOR
View through CrossRef
European countries are committed to decarbonising power generation with clear goals over the coming decades. As a consequence, an energy transition from fossil fuel generation to renewable energy sources is required. This will influence electrical transmission systems which will need to develop and adapt to changes that new renewable energy sources bring. Electricity grids can accommodate these changes more easily if they are connected to other grids, thus allowing for power exchange and stability support during operation. The Great Britain and Ireland electricity grids are classed as islanded power systems with few interconnections.
Interconnectors are high-voltage cables or transmission lines used to connect the electricity grids of different regions or countries. They are an asset for increasing energy security and reliability, stabilizing the price of electricity and supporting integration of renewable energy sources. Interconnectors are used to balance supply and demand by transferring excess renewable energy from one country to another. Ireland had only two interconnectors in operations until beginning of 2025:
Moyle Interconnector, between Scotland and Northern Ireland,
East-West Interconnector, between England and Republic of Ireland.
An additional two interconnectors are being established. The Celtic Interconnector, between the southern coast of Republic of Ireland and the north-west coast of France, is expected to begin operation in 2026 and the Greenlink Interconnector, between the eastern coast of Republic of Ireland and south-west Wales, which went into operation in 2025.
The Greenlink Interconnector is a subsea and underground electricity interconnector cable with a nominal capacity of 500 MW that connects the electricity grids of Ireland and Great Britain. It consists of two converter stations – one located near Great Island substation in County Wexford and the other near Pembroke substation in Pembrokeshire – connected by the High Voltage Direct Current (HVDC) cables under the Irish Sea. The total length of the cable is 200 km, with 160 km being installed under the sea. The HVDC link is configured as a symmetrical monopole operating at a voltage of ±320 kV d.c. The Greenlink Interconnector will provide a bi-directional power supply, depending on the supply and demand in each country and will double the interconnection capacity between Ireland and Great Britain and increase the security of supply for consumers, as well as further the integration of low-carbon energy sources. Greenlink Interconnector will contribute to the economic and environmental development of both Ireland and Great Britain. This paper outlines the methodology and technologies used for project design, as well as the significance of the project.
Srpski nacionalni komitet Međunarodnog saveta za velike električne mreže
Title: THE NEW GREENLINK 500 MW INTERCONNECTOR
Description:
European countries are committed to decarbonising power generation with clear goals over the coming decades.
As a consequence, an energy transition from fossil fuel generation to renewable energy sources is required.
This will influence electrical transmission systems which will need to develop and adapt to changes that new renewable energy sources bring.
Electricity grids can accommodate these changes more easily if they are connected to other grids, thus allowing for power exchange and stability support during operation.
The Great Britain and Ireland electricity grids are classed as islanded power systems with few interconnections.
Interconnectors are high-voltage cables or transmission lines used to connect the electricity grids of different regions or countries.
They are an asset for increasing energy security and reliability, stabilizing the price of electricity and supporting integration of renewable energy sources.
Interconnectors are used to balance supply and demand by transferring excess renewable energy from one country to another.
Ireland had only two interconnectors in operations until beginning of 2025:
Moyle Interconnector, between Scotland and Northern Ireland,
East-West Interconnector, between England and Republic of Ireland.
An additional two interconnectors are being established.
The Celtic Interconnector, between the southern coast of Republic of Ireland and the north-west coast of France, is expected to begin operation in 2026 and the Greenlink Interconnector, between the eastern coast of Republic of Ireland and south-west Wales, which went into operation in 2025.
The Greenlink Interconnector is a subsea and underground electricity interconnector cable with a nominal capacity of 500 MW that connects the electricity grids of Ireland and Great Britain.
It consists of two converter stations – one located near Great Island substation in County Wexford and the other near Pembroke substation in Pembrokeshire – connected by the High Voltage Direct Current (HVDC) cables under the Irish Sea.
The total length of the cable is 200 km, with 160 km being installed under the sea.
The HVDC link is configured as a symmetrical monopole operating at a voltage of ±320 kV d.
c.
The Greenlink Interconnector will provide a bi-directional power supply, depending on the supply and demand in each country and will double the interconnection capacity between Ireland and Great Britain and increase the security of supply for consumers, as well as further the integration of low-carbon energy sources.
Greenlink Interconnector will contribute to the economic and environmental development of both Ireland and Great Britain.
This paper outlines the methodology and technologies used for project design, as well as the significance of the project.
Related Results
Blunt Chest Trauma and Chylothorax: A Systematic Review
Blunt Chest Trauma and Chylothorax: A Systematic Review
Abstract
Introduction: Although traumatic chylothorax is predominantly associated with penetrating injuries, instances following blunt trauma, as a rare and challenging condition, ...
Nigerian Gas Transmission Tariff Framework Study
Nigerian Gas Transmission Tariff Framework Study
Abstract
The Federal Government of Nigeria intends to develop the domestic gas market by opening investment opportunity for infrastructural development, and by inclu...
Kaji eksperimen pengaruh hardening dan tempering terhadap kekuatan tarik dan kekerasan pada baja karbon sedang
Kaji eksperimen pengaruh hardening dan tempering terhadap kekuatan tarik dan kekerasan pada baja karbon sedang
This study aims to determine the effect of hardening and tempering on tensile strength (ASTM E 8) and hardness (Rockwell) applied to medium carbon steel. The heat treatment process...
Abstract P5-14-01: A meta-analysis of clinical benefit rates for fulvestrant 500 mg versus alternative therapies for treatment of postmenopausal, estrogen receptor-positive advanced breast cancer
Abstract P5-14-01: A meta-analysis of clinical benefit rates for fulvestrant 500 mg versus alternative therapies for treatment of postmenopausal, estrogen receptor-positive advanced breast cancer
Abstract
Background
Fulvestrant 500 mg has demonstrated improved efficacy vs fulvestrant 250 mg (time to progression [TTP]/progression free survival [...
Pendapatan Masyarakat pada Komponen Silvopasture dan Agrisilvikultur Kecamatan Parangloe Kabupaten gowa
Pendapatan Masyarakat pada Komponen Silvopasture dan Agrisilvikultur Kecamatan Parangloe Kabupaten gowa
Pendapatan Masyarakat pada Komponen Silvopasture dan Agrisilvikultur Kecamatan Parangloe Kabupaten gowaThe Community Revenue In Silvopasture Components and Agrisilvikulture Parangl...
Scoliosis among children in Qinghai-Tibetan Plateau of China: A cross-sectional epidemiological study
Scoliosis among children in Qinghai-Tibetan Plateau of China: A cross-sectional epidemiological study
BackgroundThe average altitude of Qinghai-Tibetan Plateau is 4,500 m and most of the residents are Tibetan ethnicity. The purpose of this study was to investigate the prevalence of...
Analisis Partial Discharge Pada Saluran Kabel Tegangan Menengah 20 kV (Studi Assesmen SKTM di PT. PLN (Persero) UP3 Menteng)
Analisis Partial Discharge Pada Saluran Kabel Tegangan Menengah 20 kV (Studi Assesmen SKTM di PT. PLN (Persero) UP3 Menteng)
This study aims to determine the status of the cable condition to the emergence voltage of Partial Discharge, as well as the status of the cable to discharge the Partial Discharge....
Insecticides for control of light brown apple moth and codling moth in Australia
Insecticides for control of light brown apple moth and codling moth in Australia
Spray treatments of chlorpyrifos, chlorpyrifos-methyl, leptophos, mexacarbate, Bacillus thuringiensis and standard recommendations for control of Epiphyas postvittana Walk. and Cyd...