Javascript must be enabled to continue!
360 Tie-Ins In The Gulf: A Breaking Success
View through CrossRef
ABSTRACT
The development of a new field production system in the Arabian Gulf required the installation and connection of a very large number of pipelines.
The magnitude of the project called for a non conventional answer and North Sea techniques were used extensively to tackle what has been the largest ever pipeline tie-in contract. The latest DP DSV ORELIA mobilised especially from the UK for this project provided a most valuable contribution.
This paper describes in detail the engineering concepts as well as the problems ans solutions developed during the 6 month project.
INTRODUCTION
Within the objective of upgrading production capacity, an important Middle East Company had a construction project launched in order to totally reorganise the production system. The basic concept was to have the wellheads grouped around and linked to a series of gas/oil separation platforms (further referred as GOSPS).
In practice, this resulted in an array of pipelines departing from the GOSP and connected by pair to different wellheads. The GOSP design was based on a corridor concept where provision for future lines was made (having in mind long term field development). Typically, each main side of the rectangular GOSP was carrying between 8 and 12 risers ranging from 10 inches to 24 inches nominal pipe dimensions. From these risers, a straight "lead spool" of the order of 73 m long was to be connected (corridor spool). Then, a "fan spool" carrying various elbows was to be installed and intended to enable pipe laying within reasonable distance to take place (near platforms). Similarly, careful attention was paid to the restriction of access to GOSP for any type of working units (jack-up rigs, anchor barges) owing to the number of lines on the seabed. Concentration of all incoming and departing flowlines was achieved on two sides only leaving the two other sides fully clear. For short term production facilities (mainly linked to the wellheads under installation) the pipelines were under installation and connection and testing was required. Such "closing spools" ranging from 10 to' 50 meters flange to flange were usually of Z or L shape to allow for compensation of thermal stresses within the pipeline.
Typical sketches of a GOSP are shown below (Figure 1 and 2).
The corresponding approach of a wellhead sattelite was much simpler as it required only two product lines (oil/gas and water). Consequently, the scope of work was 1imited to one "lead spool" and one "closing spool".
The water depth for the subsea work was between 30 and 60 meters and most of the work was scheduled to take place during the winter season.
PERFORMANCE OF THE WORK
PROBLEMS AND SOLUTIONS
Construction work in the Arabian Gulf is based on the utilization of Anchor Barges as surface support vessels owing to the generally shallow water depths encountered in this area of the world. In addition, shallow water and limited fetch are resulting in short period waves of high frequency but limited amplitude which has not so far called for surface vessel requirements comparable to the North Sea present standards.
Title: 360 Tie-Ins In The Gulf: A Breaking Success
Description:
ABSTRACT
The development of a new field production system in the Arabian Gulf required the installation and connection of a very large number of pipelines.
The magnitude of the project called for a non conventional answer and North Sea techniques were used extensively to tackle what has been the largest ever pipeline tie-in contract.
The latest DP DSV ORELIA mobilised especially from the UK for this project provided a most valuable contribution.
This paper describes in detail the engineering concepts as well as the problems ans solutions developed during the 6 month project.
INTRODUCTION
Within the objective of upgrading production capacity, an important Middle East Company had a construction project launched in order to totally reorganise the production system.
The basic concept was to have the wellheads grouped around and linked to a series of gas/oil separation platforms (further referred as GOSPS).
In practice, this resulted in an array of pipelines departing from the GOSP and connected by pair to different wellheads.
The GOSP design was based on a corridor concept where provision for future lines was made (having in mind long term field development).
Typically, each main side of the rectangular GOSP was carrying between 8 and 12 risers ranging from 10 inches to 24 inches nominal pipe dimensions.
From these risers, a straight "lead spool" of the order of 73 m long was to be connected (corridor spool).
Then, a "fan spool" carrying various elbows was to be installed and intended to enable pipe laying within reasonable distance to take place (near platforms).
Similarly, careful attention was paid to the restriction of access to GOSP for any type of working units (jack-up rigs, anchor barges) owing to the number of lines on the seabed.
Concentration of all incoming and departing flowlines was achieved on two sides only leaving the two other sides fully clear.
For short term production facilities (mainly linked to the wellheads under installation) the pipelines were under installation and connection and testing was required.
Such "closing spools" ranging from 10 to' 50 meters flange to flange were usually of Z or L shape to allow for compensation of thermal stresses within the pipeline.
Typical sketches of a GOSP are shown below (Figure 1 and 2).
The corresponding approach of a wellhead sattelite was much simpler as it required only two product lines (oil/gas and water).
Consequently, the scope of work was 1imited to one "lead spool" and one "closing spool".
The water depth for the subsea work was between 30 and 60 meters and most of the work was scheduled to take place during the winter season.
PERFORMANCE OF THE WORK
PROBLEMS AND SOLUTIONS
Construction work in the Arabian Gulf is based on the utilization of Anchor Barges as surface support vessels owing to the generally shallow water depths encountered in this area of the world.
In addition, shallow water and limited fetch are resulting in short period waves of high frequency but limited amplitude which has not so far called for surface vessel requirements comparable to the North Sea present standards.
Related Results
Estimating Deterioration in the Concrete Tie-Ballast Interface Based on Vertical Tie Deflection Profile: A Numerical Study
Estimating Deterioration in the Concrete Tie-Ballast Interface Based on Vertical Tie Deflection Profile: A Numerical Study
In ballasted concrete tie track, the tie-ballast interface can deteriorate resulting in concrete tie bottom abrasion, ballast pulverization and/or voids in tie-ballast interfaces. ...
A functional study of all 40
C. elegans
insulin-like peptides
A functional study of all 40
C. elegans
insulin-like peptides
Abstract
The human genome encodes ten insulin-like genes, whereas the
C. elegans
genome remarkably encodes fo...
Challenges in Execution of Brownfield Projects Without Production Shutdown – Case Study
Challenges in Execution of Brownfield Projects Without Production Shutdown – Case Study
Abstract
Oil producing companies are targeting minimal modifications to existing facilities in an attempt to increase oil production with minimal capital investment ...
Product-precursor relationships amongst inositol polyphosphates. Incorporation of [32P]Pi into myo-inositol 1,3,4,6-tetrakisphosphate, myo-inositol 1,3,4,5-tetrakisphosphate, myo-inositol 3,4,5,6-tetrakisphosphate and myo-inositol 1,3,4,5,6-pentakisphosph
Product-precursor relationships amongst inositol polyphosphates. Incorporation of [32P]Pi into myo-inositol 1,3,4,6-tetrakisphosphate, myo-inositol 1,3,4,5-tetrakisphosphate, myo-inositol 3,4,5,6-tetrakisphosphate and myo-inositol 1,3,4,5,6-pentakisphosph
Avian erythrocytes were incubated with myo-[3H]inositol for 6-7 h and with [32P]Pi for the final 50-90 min of this period. An acid extract was prepared from the prelabelled erythro...
Gulf of Mexico Environmental Program
Gulf of Mexico Environmental Program
ABSTRACT
The Gulf Universities Research Corporation, representing approximately 1400 academic scientists with some involvement in marine and coastal affairs, has ...
Velocity Modelling and Depth Conversion Uncertainty Mitigation in GS327 Oil Field, in Gulf of Suez Basin
Velocity Modelling and Depth Conversion Uncertainty Mitigation in GS327 Oil Field, in Gulf of Suez Basin
Abstract
The Gulf of Suez rift initiated in the Late Oligocene, probably propagating northwards, and intersecting a major east-west structural boundary of Late Eocen...
Understanding tie strength in social networks using a local “bow tie” framework
Understanding tie strength in social networks using a local “bow tie” framework
AbstractUnderstanding factors associated with tie strength in social networks is essential in a wide variety of settings. With the internet and cellular phones providing additional...
Emergence of Bow-tie Architecture in Evolving Feedforward Networks
Emergence of Bow-tie Architecture in Evolving Feedforward Networks
Abstract
Bow-tie architecture is a layered network structure that has a narrow middle layer with multiple inputs and outputs. Such structures are widely seen in the...

