Studi Sistem Drainase Air Tambang Batubara di Sump Pit Bara4 PT Berkat Anugerah Sejahtera
View through CrossRef
Open-pit mining system mining is greatly influenced by surface runoff, rainwater and groundwater. This surface water runoff is highly dependent on rainfall catchment areas, climate, and land use. Handling surface water runoff entering the mining area by creating water channels in the form of open channels and closed channels. One of the mining methods that is generally carried out in Indonesia is the open-pit mining method, which is widely found in East Kalimantan. Large basins will be created as a result of this mining technique, which could eventually serve as a reservoir for water from both surface runoff and groundwater. Therefore, an analysis of the runoff water output in the sump is required, sump capacity and appropriate pumping ratio so that mining activities can continue. The results of the study obtained the runoff discharge value in the sump was 4,071.37 m3/day, the sump capacity was 207,474.07 m3, the water balance in the sump with a total runoff discharge of 5,871.37 m3/day, and the existing volume of water in the sump was 24,771 m3. evaporation of 4.36 m3/day, infiltration of 91.36 m3/day, and pump discharge of 8,229.27 m3/day. A pumping ratio of 0.71 was obtained.
Asosiasi Riset Ilmu Manajemen dan Bisnis Indonesia
Title: Studi Sistem Drainase Air Tambang Batubara di Sump Pit Bara4 PT Berkat Anugerah Sejahtera
Description:
Open-pit mining system mining is greatly influenced by surface runoff, rainwater and groundwater.
This surface water runoff is highly dependent on rainfall catchment areas, climate, and land use.
Handling surface water runoff entering the mining area by creating water channels in the form of open channels and closed channels.
One of the mining methods that is generally carried out in Indonesia is the open-pit mining method, which is widely found in East Kalimantan.
Large basins will be created as a result of this mining technique, which could eventually serve as a reservoir for water from both surface runoff and groundwater.
Therefore, an analysis of the runoff water output in the sump is required, sump capacity and appropriate pumping ratio so that mining activities can continue.
The results of the study obtained the runoff discharge value in the sump was 4,071.
37 m3/day, the sump capacity was 207,474.
07 m3, the water balance in the sump with a total runoff discharge of 5,871.
37 m3/day, and the existing volume of water in the sump was 24,771 m3.
evaporation of 4.
36 m3/day, infiltration of 91.
36 m3/day, and pump discharge of 8,229.
27 m3/day.
A pumping ratio of 0.
71 was obtained.
Related Results
DESAIN JARINGAN DRAINASE DESA GANDANG BARAT KECAMATAN MALIKU KABUPATEN PULANG PISAU
DESAIN JARINGAN DRAINASE DESA GANDANG BARAT KECAMATAN MALIKU KABUPATEN PULANG PISAU
Daerah rawa di Indonesia mempunyai lahan seluas 39.424.500 hektar.Jumlah rawa Pasang surut di Kabupaten Pulang Pisau 9.063.000 hektar, di Kecamatan...
Evaluasi Kinerja Pompa Dalam Sistem Penirisan Tambang Pit 4 PT Bara Energi Lestari, Kabupaten Nagan Raya, Provinsi Aceh
Evaluasi Kinerja Pompa Dalam Sistem Penirisan Tambang Pit 4 PT Bara Energi Lestari, Kabupaten Nagan Raya, Provinsi Aceh
PT. Bara Energi Lestari merupakan perusahaan yang bergerak di bidang kegiatan pertambangan batubara dengan menerapkan sistem penambangan terbuka (open pit). Tingginya curah hujan m...
Morphometry of an hexagonal pit crater in Pavonis Mons, Mars
Morphometry of an hexagonal pit crater in Pavonis Mons, Mars
<p><strong>Introduction:</strong></p>
<p>Pit craters are peculiar depressions found in almost every terrestria...
ANALISA KAPASITAS DIMENSI SALURAN DRAINASE DI JALAN KEBUN AGUNG SAMARINDA
ANALISA KAPASITAS DIMENSI SALURAN DRAINASE DI JALAN KEBUN AGUNG SAMARINDA
Saluran drainase merupakan saluran air atau jalur pembuangan air untuk mengurangi kelebihan air. Saluran drainase direncanakan untuk menampung debit rencana dengan aman berd...
EVALUASI DAN PERENCANAAN SALURAN DRAINASE PROYEK SPBU JALAN SILIWANGI RANGKASBITUNG – BANTEN
EVALUASI DAN PERENCANAAN SALURAN DRAINASE PROYEK SPBU JALAN SILIWANGI RANGKASBITUNG – BANTEN
Pembangunan suatu SPBU memerlukan perencanaan saluran drainase baik bagi keperluan
drainase dalam SPBU maupun untuk keperluan drainase lingkungan. Drainase lingkungan
d...
EVALUASI SISTEM DRAINASE DI KELURAHAN PAMINGGIR GARUT
EVALUASI SISTEM DRAINASE DI KELURAHAN PAMINGGIR GARUT
Perencanaan dan pelaksanaan pembuatan jalan telah lama menyadari bahwa kehadiran air di dalam dan sekitar badan perkerasan jalan akan mempercepat teurunnya kekuatan/kehancuan jalan...
PENGARUH NILAI KARAKTERISTIK BATUBARA TERHADAP GROSS CALORIFIC VALUE BATUBARA PT BUKIT ASAM
PENGARUH NILAI KARAKTERISTIK BATUBARA TERHADAP GROSS CALORIFIC VALUE BATUBARA PT BUKIT ASAM
PT Bukit Asam Tbk adalah perusahaan bisnis batubara yang cukup besar di Indonesia. Batubara tergolong sumber energi karena memiliki nilai kalor untuk terjadinya pembakaran. Oleh ka...
Gasifikasi Batubara Bawah Tanah: Teknologi Pemanfaatan Batubara Ramah Lingkungan
Gasifikasi Batubara Bawah Tanah: Teknologi Pemanfaatan Batubara Ramah Lingkungan
Di Indonesia, kebutuhan dan distribusi pemanfaatan batubara sangat bervariasi. Hal ini disebabkan oleh tersebarnya industri pengguna batubara, pengangkutan dan penyimpanannya.Kadar...