Search engine for discovering works of Art, research articles, and books related to Art and Culture
ShareThis
Javascript must be enabled to continue!

Roncador Field: Transport of P-36 and Installation of the Mooring System

View through CrossRef
Abstract This paper describes the transport and installation phases of the semi-submersible PETROBRAS 36, since the unit's depart from Davie shipyard in Canada, where the conversion had been undertaken, up to the hook-up of the mooring system in Roncador Field. The selection of dry transportation of P-36 from Canada to Brazil, using the heavy lift carrier Mighty Servant 1 from Dockwise, was driven by a combination of technical and strategic issues. A set of technical studies was performed to make this 32,700-ton heavy transport feasible, taking into account the risk factors involved in the operation. P-36 mooring system comprises 16 lines in taut leg configuration, using polyester ropes and Vertically Loaded Anchors (VLAs). The water depth at the anchor locations ranges from 1200 to 1520m. The installation of a mooring system of this size in such depths represented an enormous challenge. The irregular soil characteristics in Roncador where two subsea canyons converge near to the platform location presented an additional complication factor. Background Petrobras-36 Production Unit. The Spirit of Columbus semisubmersible platform was originally built as a drilling and production unit, able to process up to 100,000 bpd. Twelve mooring legs composed its original mooring system that was designed for a maximum water depth of 500m. The construction of the unit was concluded in 1994 but, up to 1996, when it was contracted by Petrobras and renamed to Petrobras-36, it had never operated. In order to operate in Roncador Field, located in Campos Basin, the Spirit of Columbus undertook an extensive upgrade, performed at Davie shipyard in Canada. The upgrade included the installation of new process facilities for 180,000 bpd of oil and 7,200,000 m3/d of gas and 24,000 m3/d water injection capacity and facilities for risers' support. Structural modifications to support new equipment and to comply with stability and buoyancy requirements were also executed. Paper OTC 12136 (Ref.3) gives an overview of Roncador development program and a detailed description of the platform upgrade is given in paper OTC 12140 (Ref. 4). Mooring System Upgrade. The water depth increase (from 500 to 1360m), the huge number of flexible risers supported by the Unit and the strong currents in Roncador resulted in the need to upgrade the Unit's mooring system to 16 legs. Following Petrobras specifications, the system was designed in a taut leg configuration, using polyester ropes 1800m long with a Minimum Break Load (MBL) of 1,000 tons. Project Design Mooring Ropes. The 1,800m polyester legs were divided in 3 segments in order to turn easier the operations with the ropes inside the Anchor Handling Vessels. The segments were supplied in different lengths, to enable the abandonment of the lines in buoys, after the pre-setting (see below). The ropes were designed including a surplus of 25% on top of the necessary Safety Factors to comply with eventual resistance losses during the Unit's lifetime. The amount of polyester to be purchased was enormous. So, Petrobras decided to split the purchase among three different suppliers.
Title: Roncador Field: Transport of P-36 and Installation of the Mooring System
Description:
Abstract This paper describes the transport and installation phases of the semi-submersible PETROBRAS 36, since the unit's depart from Davie shipyard in Canada, where the conversion had been undertaken, up to the hook-up of the mooring system in Roncador Field.
The selection of dry transportation of P-36 from Canada to Brazil, using the heavy lift carrier Mighty Servant 1 from Dockwise, was driven by a combination of technical and strategic issues.
A set of technical studies was performed to make this 32,700-ton heavy transport feasible, taking into account the risk factors involved in the operation.
P-36 mooring system comprises 16 lines in taut leg configuration, using polyester ropes and Vertically Loaded Anchors (VLAs).
The water depth at the anchor locations ranges from 1200 to 1520m.
The installation of a mooring system of this size in such depths represented an enormous challenge.
The irregular soil characteristics in Roncador where two subsea canyons converge near to the platform location presented an additional complication factor.
Background Petrobras-36 Production Unit.
The Spirit of Columbus semisubmersible platform was originally built as a drilling and production unit, able to process up to 100,000 bpd.
Twelve mooring legs composed its original mooring system that was designed for a maximum water depth of 500m.
The construction of the unit was concluded in 1994 but, up to 1996, when it was contracted by Petrobras and renamed to Petrobras-36, it had never operated.
In order to operate in Roncador Field, located in Campos Basin, the Spirit of Columbus undertook an extensive upgrade, performed at Davie shipyard in Canada.
The upgrade included the installation of new process facilities for 180,000 bpd of oil and 7,200,000 m3/d of gas and 24,000 m3/d water injection capacity and facilities for risers' support.
Structural modifications to support new equipment and to comply with stability and buoyancy requirements were also executed.
Paper OTC 12136 (Ref.
3) gives an overview of Roncador development program and a detailed description of the platform upgrade is given in paper OTC 12140 (Ref.
4).
Mooring System Upgrade.
The water depth increase (from 500 to 1360m), the huge number of flexible risers supported by the Unit and the strong currents in Roncador resulted in the need to upgrade the Unit's mooring system to 16 legs.
Following Petrobras specifications, the system was designed in a taut leg configuration, using polyester ropes 1800m long with a Minimum Break Load (MBL) of 1,000 tons.
Project Design Mooring Ropes.
The 1,800m polyester legs were divided in 3 segments in order to turn easier the operations with the ropes inside the Anchor Handling Vessels.
The segments were supplied in different lengths, to enable the abandonment of the lines in buoys, after the pre-setting (see below).
The ropes were designed including a surplus of 25% on top of the necessary Safety Factors to comply with eventual resistance losses during the Unit's lifetime.
The amount of polyester to be purchased was enormous.
So, Petrobras decided to split the purchase among three different suppliers.

Related Results

SS: Spar Technology- Developments in Deepwater spar installation
SS: Spar Technology- Developments in Deepwater spar installation
Abstract During the last seven years Heerema Marine Contractors (HMC) has installed more than half of all Spars in the deep waters of the Gulf of Mexico. The dual...
North Sea Mooring Systems: How Reliable Are They?
North Sea Mooring Systems: How Reliable Are They?
In recent years a number of high profile mooring failures have emphasised the high risk nature of this element of a floating structure. Semi-submersible Mobile Offshore Drilling Un...
Integrity Management of Mooring Systems
Integrity Management of Mooring Systems
Abstract Mooring systems remain an important component of an overall field development. There are numerous sources in literature describing challenges with mooring s...
Mooring System Integrity Challenges and Repair Experience of South China Sea Floating Production Units
Mooring System Integrity Challenges and Repair Experience of South China Sea Floating Production Units
Abstract This paper is written to provide working experience for mooring integrity works done in South China Sea. The relevant statistical data and repair methods of...
Sensitivity Analysis of Different Parameters of Taut Mooring System of a Truss Spar
Sensitivity Analysis of Different Parameters of Taut Mooring System of a Truss Spar
Abstract The taut mooring system is widely used for some advantages, such as smaller mooring radius, lighter total weight and better anti-corrosion performance. In t...
A Fixed Single-Point Mooring Innovation Solution for Offshore LNG-FSRU Import Terminal
A Fixed Single-Point Mooring Innovation Solution for Offshore LNG-FSRU Import Terminal
Abstract Natural gas plays a critical role in sustainable development and energy transition because it's safe, high-heat and clean energy. LNG-FSRU is an offshore fl...
Gryphon Alpha FPSO - Experience Gained During Moorings Replacement and Hook-Up
Gryphon Alpha FPSO - Experience Gained During Moorings Replacement and Hook-Up
Abstract In a North Sea storm during February 2011 the Gryphon Alpha FPSO broke four of her 10 mooring lines and moved partially off station, causing damage to su...
Zigzag Mooring Line Design for Shallow Water Semi-Submersible FOWT
Zigzag Mooring Line Design for Shallow Water Semi-Submersible FOWT
Abstract A novel mooring design with zigzag-shaped mooring line profile (patent pending) is proposed as a small footprint soft mooring system for floating offshore w...

Back to Top