Search engine for discovering works of Art, research articles, and books related to Art and Culture
ShareThis
Javascript must be enabled to continue!

Platform Emmy Strengthening And Requalification

View through CrossRef
ABSTRACT Older platforms that may require assessment and/or strengthening to continue operation are of primary interest and concern to operators, designers and regulators. Experience with damage assessment and abatement, evaluation of the strength of damaged members and the evaluation of the capacity of strengthened members are subjects of equal interest. The experience with platform Emmy adds to this emerging pool of knowledge. Platform Emmy was installed offshore Southern California in 1961, using design guidelines and practice current at the time, both of which have undergone drastic changes. The platform suffered both cracks and member indentations, due predominantly to accidental impact by equipment and a supply boat. The present operator used various methods to reduce the operational and environmental loads on the one hand, and to increase the resistance of the platform structure on the other. These were performed in order to continue platform operation and to obtain requalification permits, The operator used novel techniques based on recent tests to evaluate the strength of damaged members, and also used unique approaches to damage control, containment and monitoring. The criteria used for reanalysis are presented. The need for appropriate criteria is discussed. The involvement of the regulator and third party reviewer is also presented. HISTORICAL BACKGROUND In 1961, Platform Emmy was installed in 45.5 feet of water on California State Lease PRC 425.1, Huntington Beach Offshore Field, approximately one mile offshore Huntington Beach, California (Figure 1). The original owners operated the platform as a drilling and production platform. A satellite platform was added in 1980, south of Emmy, connected by two personnel bridges. The satellite housed equipment and supplies on a single deck for a steam-water flooding program (Figure 2). Shell purchased both platforms in 1986 from Phillips Petroleum, the owner at the time. They are operated by Shell Western Exploration and Production, Inc. (SWEPI). An initial survey was conducted which revealed damage at the -3 bracing level; subsequently, both platforms were included in a comprehensive survey and upgrade. Since no significant damage was observed on the Satellite Platform, only Emmy is reviewed in this paper. An original set of structural drawings was available, indicating the structural framing, sizing and detailing, as well as the pile foundations [1]. A typical broadside (east) elevation, as originally designed, is shown in Figure 3. Similarly, a narrowside (north) elevation is shown in Figure 4. The original soil investigation report was also available [2]. The platform was designed to Uniform Building Code (UBC) criteria, current at the time. These criteria were later incorporated into the First Edition of API RP2A in 1969, but were replaced by modern seismic guidelines in the 7th Edition, 1976. PLATFORM DESCRIPTION Emmy is comprised of a three-level deck, a jacket and a pile foundation. The deck is an open frame with X bracing along both main axes to accommodate lateral loads. It consists of two girders running north-south and seven trussed girders running east-west. The Drilling Deck supports the workover rig, a mezzanine is located above the Production Deck and the Lower Deck houses utility equipment
Title: Platform Emmy Strengthening And Requalification
Description:
ABSTRACT Older platforms that may require assessment and/or strengthening to continue operation are of primary interest and concern to operators, designers and regulators.
Experience with damage assessment and abatement, evaluation of the strength of damaged members and the evaluation of the capacity of strengthened members are subjects of equal interest.
The experience with platform Emmy adds to this emerging pool of knowledge.
Platform Emmy was installed offshore Southern California in 1961, using design guidelines and practice current at the time, both of which have undergone drastic changes.
The platform suffered both cracks and member indentations, due predominantly to accidental impact by equipment and a supply boat.
The present operator used various methods to reduce the operational and environmental loads on the one hand, and to increase the resistance of the platform structure on the other.
These were performed in order to continue platform operation and to obtain requalification permits, The operator used novel techniques based on recent tests to evaluate the strength of damaged members, and also used unique approaches to damage control, containment and monitoring.
The criteria used for reanalysis are presented.
The need for appropriate criteria is discussed.
The involvement of the regulator and third party reviewer is also presented.
HISTORICAL BACKGROUND In 1961, Platform Emmy was installed in 45.
5 feet of water on California State Lease PRC 425.
1, Huntington Beach Offshore Field, approximately one mile offshore Huntington Beach, California (Figure 1).
The original owners operated the platform as a drilling and production platform.
A satellite platform was added in 1980, south of Emmy, connected by two personnel bridges.
The satellite housed equipment and supplies on a single deck for a steam-water flooding program (Figure 2).
Shell purchased both platforms in 1986 from Phillips Petroleum, the owner at the time.
They are operated by Shell Western Exploration and Production, Inc.
(SWEPI).
An initial survey was conducted which revealed damage at the -3 bracing level; subsequently, both platforms were included in a comprehensive survey and upgrade.
Since no significant damage was observed on the Satellite Platform, only Emmy is reviewed in this paper.
An original set of structural drawings was available, indicating the structural framing, sizing and detailing, as well as the pile foundations [1].
A typical broadside (east) elevation, as originally designed, is shown in Figure 3.
Similarly, a narrowside (north) elevation is shown in Figure 4.
The original soil investigation report was also available [2].
The platform was designed to Uniform Building Code (UBC) criteria, current at the time.
These criteria were later incorporated into the First Edition of API RP2A in 1969, but were replaced by modern seismic guidelines in the 7th Edition, 1976.
PLATFORM DESCRIPTION Emmy is comprised of a three-level deck, a jacket and a pile foundation.
The deck is an open frame with X bracing along both main axes to accommodate lateral loads.
It consists of two girders running north-south and seven trussed girders running east-west.
The Drilling Deck supports the workover rig, a mezzanine is located above the Production Deck and the Lower Deck houses utility equipment.

Related Results

EMMY/360
EMMY/360
The Stanford EMMY is a vertically organized, dynamically microprogrammed flexible host machine configured as part of the Stanford Emulation Laboratory. EMMY/360 is an emulation of ...
Dylemat tożsamości w artystycznej koncepcji Emmy Andijewskiej
Dylemat tożsamości w artystycznej koncepcji Emmy Andijewskiej
Artykuł poświęcony jest zagadnieniu tożsamości w artystycznej koncepcji ukraińskiej pisarki Emmy Andijewskiej. Kreowanie tożsamości kulturowej stało się szczególnie istotną kwestią...
Le sol : enquête sur les mécanismes de (non) émergence d’un problème public environnemental
Le sol : enquête sur les mécanismes de (non) émergence d’un problème public environnemental
Si les sols sont indispensables à l’activité humaine et au bon fonctionnement des écosystèmes, ils ne font pourtant l’objet d’aucune mesure de conservation contraignante qui leur s...
Wellbore Strengthening Uncertainties and Workflow Optimizations
Wellbore Strengthening Uncertainties and Workflow Optimizations
Abstract Drilling depleted reservoirs is a challenging operation due to significant mud losses and potential risk of wellbore collapse against shale or high-pressure...
Deepwater Platform Design
Deepwater Platform Design
ABSTRACT Results of preliminary platform design studies enable engineers"to identify and appraise major variables affecting deepwater platform capabilities. Trans...
The Removal of the Maureen Steel Gravity Platform
The Removal of the Maureen Steel Gravity Platform
Abstract The Maureen drilling, production and oil storage platform is located in 95.6m of water in block 16/29 of the U.K. Continental Shelf, and consists of a la...
Evaluating the performance of skewed prestressed concrete bridge after strengthening
Evaluating the performance of skewed prestressed concrete bridge after strengthening
Abstract The objectives of this paper are to explain the application of repairing and strengthening methods on the damaged members of the bridge structure, to analyz...

Back to Top