Javascript must be enabled to continue!
The Skirt Piled Gullfaks C Platform Installation
View through CrossRef
ABSTRACT
The Gullfaks C concrete platform was successfully installed on a soft soil site in 1989. This was the first time the new foundation concept of skirt piling i.e. very deep concrete skirts acting as piles, was implemented for a gravity base structure.
The platform foundation consists of 16 large diameter skirt piles penetrating 22 meters into the seabed. Installation of these "piles" was achieved by platform weight and underbase suction.
The platform weight was initially carried as base contact pressures. A soil strengthening scheme enabled full weight of the platform to be carried by the skirtpiles within 3 months.
Through this first skirtpiled platform installation, the concept of skirt piling should be recognized as a proven design.
INTRODUCTION
The Gullfaks C platform installed in May 1989 is the largest and heaviest offshore concrete structure ever built. Designed for 220 m water depth it has a displacement of more than 1.4 million tonnes and represents a total investment of $ 2 billions.
Contrary to previous gravity base structures, the Gullfaks C platform was offered one of the most complex seabed conditions in the North Sea to date.
The upper 45 meters of soils consist predominantly of normally consolidated soft clay and loose clayey and silty sands with interbedded dense sand layers, see Fig. 2.
The combination of a heavy gravity structure and soft soils called for a new foundation solution:–skirt piles through soft soil layers, and.–strength improvement of soils below the depth that could be reached by skirt piles.
The strength improvement was achieved through an acccelerated soil consolidation by means of a large soil drain system comprizing more than 800 single filters and a total filter area of 1600 m2 The system was operated with suction through the first summer season. In this period 8000 m3 of ground water was extracted from the foundation soils.
The platform foundation base area amounts to 16000 m2 The foundation is made up of 1400 running metres of concrete skirts penetrated 22 m into the seabed. The skirt piles consist of 16 circular concrete cells of diameter 28 m and wall thickness 0.4 m, see Fig. 1.
After soil strengthening by artificial drainage, the operational platform submerged weight of 500.000 tonnes is mainly transferred to the soil as skirt tip resistance and skirt wall friction. This will reduce the future platform settlements significantly.
The skirt penetration driving force was provided by platform water ballasting and underbase suction.
FOUNDATION DESIGN ASPECTS AND INSTALLATION PRINCIPLES
Foundation design aspects
There are four major foundation aspects of the GBS foundation. These are:–Skirt penetration resistance–Foundation stability–Foundation load distribution–Platform settlement
Foundation stability of Gullfaks C could theoretically be obtained in several ways, e.g. by large base area, very deep skirts or"stronger" soil. The relationship between these parameters are shown in Fig. 3. At the design stage, it was apparent that any realistic solution would have to be based on much deeper skirts than for any platform before.
Title: The Skirt Piled Gullfaks C Platform Installation
Description:
ABSTRACT
The Gullfaks C concrete platform was successfully installed on a soft soil site in 1989.
This was the first time the new foundation concept of skirt piling i.
e.
very deep concrete skirts acting as piles, was implemented for a gravity base structure.
The platform foundation consists of 16 large diameter skirt piles penetrating 22 meters into the seabed.
Installation of these "piles" was achieved by platform weight and underbase suction.
The platform weight was initially carried as base contact pressures.
A soil strengthening scheme enabled full weight of the platform to be carried by the skirtpiles within 3 months.
Through this first skirtpiled platform installation, the concept of skirt piling should be recognized as a proven design.
INTRODUCTION
The Gullfaks C platform installed in May 1989 is the largest and heaviest offshore concrete structure ever built.
Designed for 220 m water depth it has a displacement of more than 1.
4 million tonnes and represents a total investment of $ 2 billions.
Contrary to previous gravity base structures, the Gullfaks C platform was offered one of the most complex seabed conditions in the North Sea to date.
The upper 45 meters of soils consist predominantly of normally consolidated soft clay and loose clayey and silty sands with interbedded dense sand layers, see Fig.
2.
The combination of a heavy gravity structure and soft soils called for a new foundation solution:–skirt piles through soft soil layers, and.
–strength improvement of soils below the depth that could be reached by skirt piles.
The strength improvement was achieved through an acccelerated soil consolidation by means of a large soil drain system comprizing more than 800 single filters and a total filter area of 1600 m2 The system was operated with suction through the first summer season.
In this period 8000 m3 of ground water was extracted from the foundation soils.
The platform foundation base area amounts to 16000 m2 The foundation is made up of 1400 running metres of concrete skirts penetrated 22 m into the seabed.
The skirt piles consist of 16 circular concrete cells of diameter 28 m and wall thickness 0.
4 m, see Fig.
1.
After soil strengthening by artificial drainage, the operational platform submerged weight of 500.
000 tonnes is mainly transferred to the soil as skirt tip resistance and skirt wall friction.
This will reduce the future platform settlements significantly.
The skirt penetration driving force was provided by platform water ballasting and underbase suction.
FOUNDATION DESIGN ASPECTS AND INSTALLATION PRINCIPLES
Foundation design aspects
There are four major foundation aspects of the GBS foundation.
These are:–Skirt penetration resistance–Foundation stability–Foundation load distribution–Platform settlement
Foundation stability of Gullfaks C could theoretically be obtained in several ways, e.
g.
by large base area, very deep skirts or"stronger" soil.
The relationship between these parameters are shown in Fig.
3.
At the design stage, it was apparent that any realistic solution would have to be based on much deeper skirts than for any platform before.
Related Results
Effect of ground subsidence on piled raft foundation
Effect of ground subsidence on piled raft foundation
Extensive researches for piled rafts have been performed but the evaluation of their behavior in ground subsidence condition is still a challenge. In this study, centrifugal tests ...
Large-Scale Penetration Test At A Deepwater Site
Large-Scale Penetration Test At A Deepwater Site
ABSTRACT
The largest offshore soil penetration test ever undertaken was planned and carried out in 1985 in the Gullfaks Field, North Sea. In more than 200 m water...
Load sharing behaviour in piled-raft foundations over sand and clay: An experimental investigation
Load sharing behaviour in piled-raft foundations over sand and clay: An experimental investigation
Piled-raft foundations have gained increasing popularity in the past few decades, providing a viable alternative to traditional raft and pile foundations. Despite this, designers a...
Study on Offshore Skirt Penetration Using the Geocentrifuge
Study on Offshore Skirt Penetration Using the Geocentrifuge
Abstract
The behaviour of deep skirts in clay has been stud, ied by performing centrifuge tests. A circular skirt pile with length 36 m, inside diameter 10.5 m an...
Modelling of Piled Raft Foundation on Soft Clay
Modelling of Piled Raft Foundation on Soft Clay
This study relates to the analysis of un – piled and piled raft foundations with soft clay soil conditions.The subsoil model was assumed uniform underneath the foundation with soil...
SS: Spar Technology- Developments in Deepwater spar installation
SS: Spar Technology- Developments in Deepwater spar installation
Abstract
During the last seven years Heerema Marine Contractors (HMC) has installed more than half of all Spars in the deep waters of the Gulf of Mexico. The dual...
Flow Induced Inline Separation (FIIS) De-watering Tests at the Gullfaks Field
Flow Induced Inline Separation (FIIS) De-watering Tests at the Gullfaks Field
Abstract
Several fields on the Norwegian Continental Shelf have reached the decline phase with an increasing production of water and gas, often in combination with r...
T&I Engineering of Monopiles: Key Considerations – Bid to Execution
T&I Engineering of Monopiles: Key Considerations – Bid to Execution
Abstract
Monopiles remain the simplest and most widely adopted foundation solution for offshore wind farms. However, unlike onshore developments, offshore monopil...

