Construction Regulatory Compliance and Public Building Project Delivery in Akure Metropolis, Nigeria

View through CrossRef
The research paper examines the correlation between the Construction Regulatory Compliance it terms of Environmental Standards Compliance, Project Timeliness and Project Cost performance on the construction of public buildings in Akure Metropolis. The analysis has shown that compliance with the environmental regulations is positively related to timely project completion and cost control. In particular, the Environmental Standards Compliance is moderately correlated with Project Timeliness (r = 0.454, p < 0.001, N = 104) stating that projects that are stronger in compliance are completed more-timely. On the same note, compliance correlates with Project Cost performance (r = 0.317, p = 0.001, N = 103) but in a positive direction, indicating that projects that comply with environmental standards have a higher chance of meeting or going below the budget. Also, there is a positive relationship between Project Timeliness and Project Cost (r = 0.324, p = 0.001, N = 103), which means that timely projects are more efficient in cost control, whereas delays lead to increased costs. Regression analysis also supports these results as Environmental Standards Compliance predicts 22.2 percent of the variance in overall Project Delivery performance (R 2 = 0.222, p < 0.001). The model indicates that as Environmental Standards Compliance increases by one unit, Project Delivery is expected to improve by 0.451 units (B = 0.451, p < 0.001). The ANOVA output (F = 29.142, p < 0.001) indicates that the model is statistically significant, and that environmental compliance has a non-trivial effect on the delivery of the project. These results indicate that the enhancement of environmental compliance can serve as a strategic tool to enhance the outcome of the project in the construction in public buildings in Akure Metropolis, and it can bring both environmental and economic values.
Title: Construction Regulatory Compliance and Public Building Project Delivery in Akure Metropolis, Nigeria
Description:
The research paper examines the correlation between the Construction Regulatory Compliance it terms of Environmental Standards Compliance, Project Timeliness and Project Cost performance on the construction of public buildings in Akure Metropolis.
The analysis has shown that compliance with the environmental regulations is positively related to timely project completion and cost control.
In particular, the Environmental Standards Compliance is moderately correlated with Project Timeliness (r = 0.
454, p < 0.
001, N = 104) stating that projects that are stronger in compliance are completed more-timely.
On the same note, compliance correlates with Project Cost performance (r = 0.
317, p = 0.
001, N = 103) but in a positive direction, indicating that projects that comply with environmental standards have a higher chance of meeting or going below the budget.
Also, there is a positive relationship between Project Timeliness and Project Cost (r = 0.
324, p = 0.
001, N = 103), which means that timely projects are more efficient in cost control, whereas delays lead to increased costs.
Regression analysis also supports these results as Environmental Standards Compliance predicts 22.
2 percent of the variance in overall Project Delivery performance (R 2 = 0.
222, p < 0.
001).
The model indicates that as Environmental Standards Compliance increases by one unit, Project Delivery is expected to improve by 0.
451 units (B = 0.
451, p < 0.
001).
The ANOVA output (F = 29.
142, p < 0.
001) indicates that the model is statistically significant, and that environmental compliance has a non-trivial effect on the delivery of the project.
These results indicate that the enhancement of environmental compliance can serve as a strategic tool to enhance the outcome of the project in the construction in public buildings in Akure Metropolis, and it can bring both environmental and economic values.

Related Results

EFFECTS OF TIME MANAGEMENT PRACTICES ON THE PERFORMANCE OF BUILDING PROJECT DELIVERY IN AKURE, ONDO STATE, NIGERIA
EFFECTS OF TIME MANAGEMENT PRACTICES ON THE PERFORMANCE OF BUILDING PROJECT DELIVERY IN AKURE, ONDO STATE, NIGERIA
Effective management of time in construction project accounts for increased project delivery performance in terms of cost, time, and quality. This study aims to assess the effect o...
De gevel – een intermediair element tussen buiten en binnen
De gevel – een intermediair element tussen buiten en binnen
This study is based on the fact that all people have a basic need for protection from other people (and animals) as well as from the elements (the exterior climate). People need a ...
Architecture between heteronomy and self-generation
Architecture between heteronomy and self-generation
Introduction «I have never worked in the technocratic exaltation, solving a constructive problem and that’s it. I’ve always tried to interpret the space of human life» (Vitto...
Sources of Legal Regulation of Compliance in Ukrainian Banks
Sources of Legal Regulation of Compliance in Ukrainian Banks
Problem setting. The banking sector plays a crucial role in the economy and therefore needs to function in a comprehensive and effective legal environment. In order to monitor comp...
THE IMPACT OF CLOUD COMPUTING ON CONSTRUCTION PROJECT DELIVERY ABUJA NIGERIA
THE IMPACT OF CLOUD COMPUTING ON CONSTRUCTION PROJECT DELIVERY ABUJA NIGERIA
Cloud computing is the delivery of computing services, such as storage, processing power, and software applications, via the internet. Cloud computing offers various advantages and...
Factors Influencing Solar Photovoltaic Utilization for Energy Services among Residentials in Akure, Nigeria
Factors Influencing Solar Photovoltaic Utilization for Energy Services among Residentials in Akure, Nigeria
Aims: Residential sector is the largest electricity consumer in Nigeria. But they also contribute heavily to the climate change through their choice of energy. Mostly prefer source...
Analysis of project delivery systems in Chinese construction industry with data envelopment analysis (DEA)
Analysis of project delivery systems in Chinese construction industry with data envelopment analysis (DEA)
PurposeSelecting a proper project delivery system is one of the critical issues for the success of a project. This paper discusses the application of project delivery systems in Ch...
IMPACT OF CREDIT RISK MANAGEMENT ON PERFORMANCE OF MICROFINANCE BANKS IN AKURE, ONDO STATE
IMPACT OF CREDIT RISK MANAGEMENT ON PERFORMANCE OF MICROFINANCE BANKS IN AKURE, ONDO STATE
The study examined the impact of credit risk management on performance of microfinance banks in Akure, Ondo State. The research design used in the study was survey research design ...

Back to Top