Multilateral History - Deepest Level 4 Cemented Junction Installation
View through CrossRef
Abstract
An operator was challenged with increasing production efficiencies from new single wellbores in the deep Tarim basin reservoirs of China. To increase and optimize single well production performance, multilateral drilling and completion technology were implemented on this initial pilot test well.
The remote location of the multilateral well in the Tarim Desert of the Xinjiang Province in northwestern China proved to be an operational and logistical challenge in terms of time (4 to 5 days travel by vehicle) and distance (3600 kilometers) to the nearest repair and maintenance facilities in Tanggu, Tianjin Province in eastern China. Critical planning, aggressive project management oversight, and strong collaboration between the operator and service supplier resulted in the world’s deepest TAML Level 4 cemented multilateral installation at 5082 m TVD junction depth and 5889 m MD at the lateral toe.
The well design was based on a vertical pilot well, or motherbore, drilled and cased into the reservoir. The multilateral system was then installed to add an additional wellbore, thereby increasing reservoir exposure. The goals of this system were to accelerate production, increase ultimate recovery and, for this particular operator, to qualify multilateral technology for this particular field application. Because of the unprecedented depth of the proposed junction, thorough project management and planning were required throughout, from the feasibility phase through the execution phase, to amplify risk mitigation and to effect a successful project installation.
This project is the first multilateral installation for this client; it was the first cemented Level 4 multilateral in China, and is the deepest Level 4 multilateral installed worldwide. This paper describes the objectives, challenges, best practices, contingencies, logistics issues, results, and lessons learned from the implementation of this deep-set multilateral technology.
Title: Multilateral History - Deepest Level 4 Cemented Junction Installation
Description:
Abstract
An operator was challenged with increasing production efficiencies from new single wellbores in the deep Tarim basin reservoirs of China.
To increase and optimize single well production performance, multilateral drilling and completion technology were implemented on this initial pilot test well.
The remote location of the multilateral well in the Tarim Desert of the Xinjiang Province in northwestern China proved to be an operational and logistical challenge in terms of time (4 to 5 days travel by vehicle) and distance (3600 kilometers) to the nearest repair and maintenance facilities in Tanggu, Tianjin Province in eastern China.
Critical planning, aggressive project management oversight, and strong collaboration between the operator and service supplier resulted in the world’s deepest TAML Level 4 cemented multilateral installation at 5082 m TVD junction depth and 5889 m MD at the lateral toe.
The well design was based on a vertical pilot well, or motherbore, drilled and cased into the reservoir.
The multilateral system was then installed to add an additional wellbore, thereby increasing reservoir exposure.
The goals of this system were to accelerate production, increase ultimate recovery and, for this particular operator, to qualify multilateral technology for this particular field application.
Because of the unprecedented depth of the proposed junction, thorough project management and planning were required throughout, from the feasibility phase through the execution phase, to amplify risk mitigation and to effect a successful project installation.
This project is the first multilateral installation for this client; it was the first cemented Level 4 multilateral in China, and is the deepest Level 4 multilateral installed worldwide.
This paper describes the objectives, challenges, best practices, contingencies, logistics issues, results, and lessons learned from the implementation of this deep-set multilateral technology.
Related Results
Economical Multilateral Well Technology for Canadian Heavy Oil
Economical Multilateral Well Technology for Canadian Heavy Oil
Abstract
In the last two years there has been a dramatic increase in the pace of the evolution of multilateral systems. Many systems with new features and improve...
Economical Multilateral Well Technology For Canadian Heavy Oil
Economical Multilateral Well Technology For Canadian Heavy Oil
Abstract
In the last several years there has been a dramatic increase in the pace of the evolution of multilateral systems. Many systems with new features and imp...
Multilateral Technology Innovations Ready to Maximize Field Development
Multilateral Technology Innovations Ready to Maximize Field Development
Abstract
For a quarter of a century sustained technological advances in multilateral technology have enhanced economics and extended the production life of fields in...
Development, Testing, and Field Case Histories of Multilateral Well Completion Systems
Development, Testing, and Field Case Histories of Multilateral Well Completion Systems
Abstract
Many enhancements have recently been made to multilateral completion systems, not only as a result of advances in technology but also because of changes ...
Horizontal Gravel Packs Successfully Deployed in Trinidad's First Multilateral Well — Planning, Implementation, and Remedial Strategies
Horizontal Gravel Packs Successfully Deployed in Trinidad's First Multilateral Well — Planning, Implementation, and Remedial Strategies
AbstractThis paper discusses the first multilateral well drilled in Trinidad and the unique integration of techniques that allowed sand control procedures to be implemented as well...
Uncemented and cemented primary total hip arthroplasty in the Swedish Hip Arthroplasty Register Evaluation of 170,413 operations
Uncemented and cemented primary total hip arthroplasty in the Swedish Hip Arthroplasty Register Evaluation of 170,413 operations
BACKGROUND AND PURPOSE: Since the introduction of total hip arthroplasty (THA) in Sweden, both components have most commonly been cemented. A decade ago the frequency of uncemented...
Statoil North Sea – Successful World Record MLT Installation
Statoil North Sea – Successful World Record MLT Installation
Abstract
In October 2010 the deepest set sealed multilateral junction in the industry was installed at 6900 m MD in Oseberg South well 30/9-F-9 AY1/Y2.
...
Screening Variables for Multilateral Technology
Screening Variables for Multilateral Technology
Abstract
The multilateral well was one of the leading technologies of 1999, and it will continue to be one of the leading technologies for the next 5-10 years. It...