The Jackup Monopile: A Production Drilling Platform
View through CrossRef
ABSTRACT
The paper describes the main conceptual and design aspects of a Jack-Up Monopile Platform concept intended for drilling and production in North Sea and which combines technology from Gravity Base Platforms and Jack-Up Rigs.
The platformcomprises3 main elements:An integrated deck, completely equipped and tested on shore prior to installationA single supporting leg with its associated jacking systemA gravity base that ensures the stability on site and during towing and can provide for extra storage The derrick and drill floor operate over the centre of the leg structure, and risers are installed through its centre, thus providing protection against damage from supply boats.
The Jack-Up Monopile Platform has been designed for 150 meters water depth in North Sea environment. It provides for a total deck payload of 10 600 tonnes which includes:Accommodation facilities for 160 personsDrilling equipments for 24 wells at 7 000 metres depthProduction equipments including injection equipment for processing 120 000 barrels oil per dayPower and utilities necessary to maintain the efficient platform operation The design allows complete fabrication and hook up of all the platform facilities to take place at an offshore construction yard prior to installation at a field location, without the need of deep water mating sites nor the use of heavy lift vessels.
The key advantage is its ability to be decommissioned easily and relocated after any eventual upgrading of its facilities. This improves the cost effective aspect of such a design and makes it specially fitted to marginal field development.
The Jack-Up Monopile Platform has been Specifically developed to meet North Sea environmental conditions and regulations and is self erected, self installed, with risers efficiently protected and can be easily decommissioned for use on other fields, thus providing operators with a cost effective development solution.
INTRODUCTION
For big oil fields, a conventional development scheme consists in installing a jacket or a concrete platform with several separate modules (drilling, production, injection, accommodation, etc...) to be towed out and installed on the site, thus requiring heavy lift vessels and high hook up costs. Such a development can take several years before first oil and so corresponds to a very high investment cost before production.
For satellite or marginal fields, some other possibilities exist such as subsea developments or use of floating production facilities. They imply subsea wellheads and completions for which technology is sophisticated. For many years now, designers have proposed mobile concepts that combine both drilling and production options.
One of this transposition concerns the jack-up concept which technology is cost-effective and well-proven now. With regards to semis which motions can be important and which are weight sensitive, jack-ups allow for early production using conventional wellheads at the platform level.
Unfortunately, conventional jack-ups cannot operate in water depth greater than 100/110 metres in North Sea.
Title: The Jackup Monopile: A Production Drilling Platform
Description:
ABSTRACT
The paper describes the main conceptual and design aspects of a Jack-Up Monopile Platform concept intended for drilling and production in North Sea and which combines technology from Gravity Base Platforms and Jack-Up Rigs.
The platformcomprises3 main elements:An integrated deck, completely equipped and tested on shore prior to installationA single supporting leg with its associated jacking systemA gravity base that ensures the stability on site and during towing and can provide for extra storage The derrick and drill floor operate over the centre of the leg structure, and risers are installed through its centre, thus providing protection against damage from supply boats.
The Jack-Up Monopile Platform has been designed for 150 meters water depth in North Sea environment.
It provides for a total deck payload of 10 600 tonnes which includes:Accommodation facilities for 160 personsDrilling equipments for 24 wells at 7 000 metres depthProduction equipments including injection equipment for processing 120 000 barrels oil per dayPower and utilities necessary to maintain the efficient platform operation The design allows complete fabrication and hook up of all the platform facilities to take place at an offshore construction yard prior to installation at a field location, without the need of deep water mating sites nor the use of heavy lift vessels.
The key advantage is its ability to be decommissioned easily and relocated after any eventual upgrading of its facilities.
This improves the cost effective aspect of such a design and makes it specially fitted to marginal field development.
The Jack-Up Monopile Platform has been Specifically developed to meet North Sea environmental conditions and regulations and is self erected, self installed, with risers efficiently protected and can be easily decommissioned for use on other fields, thus providing operators with a cost effective development solution.
INTRODUCTION
For big oil fields, a conventional development scheme consists in installing a jacket or a concrete platform with several separate modules (drilling, production, injection, accommodation, etc.
) to be towed out and installed on the site, thus requiring heavy lift vessels and high hook up costs.
Such a development can take several years before first oil and so corresponds to a very high investment cost before production.
For satellite or marginal fields, some other possibilities exist such as subsea developments or use of floating production facilities.
They imply subsea wellheads and completions for which technology is sophisticated.
For many years now, designers have proposed mobile concepts that combine both drilling and production options.
One of this transposition concerns the jack-up concept which technology is cost-effective and well-proven now.
With regards to semis which motions can be important and which are weight sensitive, jack-ups allow for early production using conventional wellheads at the platform level.
Unfortunately, conventional jack-ups cannot operate in water depth greater than 100/110 metres in North Sea.
Related Results
Jackup Designed for Optimum Operational Time in Ice Conditions
Jackup Designed for Optimum Operational Time in Ice Conditions
There is at present a large interest in exploration for hydrocarbons in the Arctic. In shallow waters, up to, say, 70m, jackups are utilized outside the ice season, while there is ...
On the Jackup Platform In the North Sea
On the Jackup Platform In the North Sea
Abstract
The adaptability of the jackup drilling platform to the severe environment of the North Sea requires knowledge of its capabilities both Afloat and while ...
Jackup Operations: New Operational Recommended Practices
Jackup Operations: New Operational Recommended Practices
Abstract
The 2005 U.S. Gulf of Mexico hurricane season validated the industry's practice of "shut-in and evacuate". Successful application of this practice result...
Effect of Installation Platform on Bearing Capacity of an Offshore Monopile Foundation
Effect of Installation Platform on Bearing Capacity of an Offshore Monopile Foundation
An installation platform will disturb the natural seabed adjacent to a monopile and, consequently, affects the bearing capacity of the monopile foundation. Thus, consideration of t...
Installing Jackups in Punch-Through-Sensitive Clays
Installing Jackups in Punch-Through-Sensitive Clays
ABSTRACT
The paper describes some of the problems of installing a jackup adjacent to a fixed platform in an area with difficult geotechnical conditions. An accoun...
Experimental Investigation of Permeability and Fluid Loss Properties of Water Based Mud Under High Pressure-High Temperature Conditions
Experimental Investigation of Permeability and Fluid Loss Properties of Water Based Mud Under High Pressure-High Temperature Conditions
Drilling in deeper formations and in high pressure and high temperature (HPHT) environments is a new frontier for the oil industry. Fifty years ago, no one would have imagined dril...
Drilling Variables At Technical Limit Of Drilling Rate
Drilling Variables At Technical Limit Of Drilling Rate
Abstract
Recorded drilling times may show significant variations from well to well even for the same total depth in the same field. Apart from the formation chara...
Inspection of Subsea Conductors Using an Innovative Drop-Down Camera
Inspection of Subsea Conductors Using an Innovative Drop-Down Camera
Abstract
Subsea conductors are the foundational elements of offshore drilling operations, serving a dual purpose as both the structural framework and the main condui...