Samarang Pipeline-Replacement Project: Application of an Innovative Approach for Shallow-Water Pipeline Installation

View through CrossRef
Abstract This paper presents the approach adopted in the replacement of ageing pipelines at offshore Sabah, Malaysia by PETRONAS Carigali Sdn. Bhd. (PCSB), the E&P arm of PETRONAS. Several options were explored to best deliver the project considering the installation difficulties were exacerbated by the congested field, ageing offshore structures, spaghetti pipeline networks, monsoon wind and presence of corals on the seabed. On top of these, the field's shallow water provides further complexity to the construction and installation works. The paper also shares the means engaged to mitigate the challenges and lessons learnt during the project's planning and executing stages. Subsequent to the preventive inspection findings, a project was initiated in 2006 – as part of PCSB's commitment to rejuvenate ageing offshore facilities, sustaining the field's integrity and assuring reliability of supply. The Samarang pipeline replacement project was initiated to address these issues and espouse the integrated field development within its block. As a fast track project, the construction method engaged has to be sound and capable for expeditious work completion to avoid jeopardizing production. Through a thorough evaluation process, an innovative pipeline installation approach utilizing a shallow draft work barge was chosen for the project. The project was completed with the successful installation of all four pipelines in December 2007. Despite many challenges, the project progressed smoothly without major setbacks. It was successfully completed ahead of schedule, within budget and recorded zero LTI and zero TRCF. The new construction method which requires assimilation of both the conventional and new approaches for offshore installation, has demonstrated its effectiveness hence proving the plausibility of the method for other projects with similar circumstances. In the pursuit of sustaining and revitalizing old offshore facilities, pipeline replacements are inevitable to prolong intra and interfield operation flow of hydrocarbon. The unique and uncertain offshore environment, particularly at the shallow water areas introduces many installation challenges. Although proven methods are available, exploring a new approach to pipeline installation is essential to safely and effectively deliver projects with minimum costs. By selecting a suitable approach for pipeline installation, new networks of hydrocarbon flow facilities can be developed, thus allowing continuous production for decades to come.
Title: Samarang Pipeline-Replacement Project: Application of an Innovative Approach for Shallow-Water Pipeline Installation
Description:
Abstract This paper presents the approach adopted in the replacement of ageing pipelines at offshore Sabah, Malaysia by PETRONAS Carigali Sdn.
Bhd.
(PCSB), the E&P arm of PETRONAS.
Several options were explored to best deliver the project considering the installation difficulties were exacerbated by the congested field, ageing offshore structures, spaghetti pipeline networks, monsoon wind and presence of corals on the seabed.
On top of these, the field's shallow water provides further complexity to the construction and installation works.
The paper also shares the means engaged to mitigate the challenges and lessons learnt during the project's planning and executing stages.
Subsequent to the preventive inspection findings, a project was initiated in 2006 – as part of PCSB's commitment to rejuvenate ageing offshore facilities, sustaining the field's integrity and assuring reliability of supply.
The Samarang pipeline replacement project was initiated to address these issues and espouse the integrated field development within its block.
As a fast track project, the construction method engaged has to be sound and capable for expeditious work completion to avoid jeopardizing production.
Through a thorough evaluation process, an innovative pipeline installation approach utilizing a shallow draft work barge was chosen for the project.
The project was completed with the successful installation of all four pipelines in December 2007.
Despite many challenges, the project progressed smoothly without major setbacks.
It was successfully completed ahead of schedule, within budget and recorded zero LTI and zero TRCF.
The new construction method which requires assimilation of both the conventional and new approaches for offshore installation, has demonstrated its effectiveness hence proving the plausibility of the method for other projects with similar circumstances.
In the pursuit of sustaining and revitalizing old offshore facilities, pipeline replacements are inevitable to prolong intra and interfield operation flow of hydrocarbon.
The unique and uncertain offshore environment, particularly at the shallow water areas introduces many installation challenges.
Although proven methods are available, exploring a new approach to pipeline installation is essential to safely and effectively deliver projects with minimum costs.
By selecting a suitable approach for pipeline installation, new networks of hydrocarbon flow facilities can be developed, thus allowing continuous production for decades to come.

Related Results

Installation Analysis of Matterhorn Pipeline Replacement
Installation Analysis of Matterhorn Pipeline Replacement
Abstract The paper describes the installation analysis for the Matterhorn field pipeline replacement, located in water depths between 800-ft to 1200-ft in the Gul...
Water Trash Collector
Water Trash Collector
In today day to day life, approximately 71% of the Earth's surface is covered by Without affecting significant role that technology plays in our modern world, environmental and wat...
Integrated Operations (IO) Model for Samarang Field Conceptual Study
Integrated Operations (IO) Model for Samarang Field Conceptual Study
Abstract Integrated Operations (IO) was indentified as part of the redevelopment program in Samarang field. The IO framework defined was focusing on Asset Management...
First Arctic Subsea Pipelines Moving to Reality
First Arctic Subsea Pipelines Moving to Reality
Abstract Two offshore development projects which involve subsea arctic pipelines are being proposed by British Petroleum Exploration (BP). Both projects are locat...
SS: Spar Technology- Developments in Deepwater spar installation
SS: Spar Technology- Developments in Deepwater spar installation
Abstract During the last seven years Heerema Marine Contractors (HMC) has installed more than half of all Spars in the deep waters of the Gulf of Mexico. The dual...
Beachpull Installation of Long Pipelines and Cables
Beachpull Installation of Long Pipelines and Cables
Conventional pipelay (i.e. S-lay) is not feasible in shallow water locations owing to the draft of pipelay barges. Pipelay using beachpull method provides an alternative to such re...
The Kapitean Stage (Upper Miocene) of New Zealand
The Kapitean Stage (Upper Miocene) of New Zealand
<p>The ten chapters in this thesis are presented in the form of nine independent papers and a note. A separate abstract is given below for each chapter. I. The type section o...

Back to Top