Study of The Application of Bunker Checklist on The MT. Fatmawati Ship to Improve and Prevent Pollution During Bunker Filling

View through CrossRef
Bunkering on ships is a very important job with a high risk of danger. Bunkering is moving liquid fuel oil from a bunker barge or bunker terminal. The process of transferring oil has the potential to cause pollution. Pollution can occur if an operational error occurs, such as an overflow, pipe, or bunker hose breaking. Overflow is one factor that most contribute to oil spills during the bunkering process. Oil overflow incidents by ships can result in expensive claims, with cleanup costs, penalties, and environmental damage running into millions of dollars. Studies to reduce the risk of oil pollution from bunkering operations need to continue. This study was carried out to know the implementation of the bunker safety checklist. The study was conducted using a case study method strengthened by a literature study. The study was conducted on board MT. Fatmawati with Dead Weight Tonnase (DWT) 7762 metric tons. The ship is driven by a diesel engine with a power of 2721 kW at 195 RPM. The 100% HFO capacity stored on board is 531.44 m3. The ship can also carry an HSD of 119.77 m3 at 100% capacity—security and safety considerations. The maximum fuel capacity that can be loaded is in the range of 80 - 90%. The study results obtained by implementing the bunker safety checklist in bunkering activities are highly recommended. Bunkering will be well planned, from planning, estimating the fuel loaded, and executing to reporting. Safety requirements and pollution prevention due to oil spills can be avoided with work planned and recorded in a checklist.
Title: Study of The Application of Bunker Checklist on The MT. Fatmawati Ship to Improve and Prevent Pollution During Bunker Filling
Description:
Bunkering on ships is a very important job with a high risk of danger.
Bunkering is moving liquid fuel oil from a bunker barge or bunker terminal.
The process of transferring oil has the potential to cause pollution.
Pollution can occur if an operational error occurs, such as an overflow, pipe, or bunker hose breaking.
Overflow is one factor that most contribute to oil spills during the bunkering process.
Oil overflow incidents by ships can result in expensive claims, with cleanup costs, penalties, and environmental damage running into millions of dollars.
Studies to reduce the risk of oil pollution from bunkering operations need to continue.
This study was carried out to know the implementation of the bunker safety checklist.
The study was conducted using a case study method strengthened by a literature study.
The study was conducted on board MT.
Fatmawati with Dead Weight Tonnase (DWT) 7762 metric tons.
The ship is driven by a diesel engine with a power of 2721 kW at 195 RPM.
The 100% HFO capacity stored on board is 531.
44 m3.
The ship can also carry an HSD of 119.
77 m3 at 100% capacity—security and safety considerations.
The maximum fuel capacity that can be loaded is in the range of 80 - 90%.
The study results obtained by implementing the bunker safety checklist in bunkering activities are highly recommended.
Bunkering will be well planned, from planning, estimating the fuel loaded, and executing to reporting.
Safety requirements and pollution prevention due to oil spills can be avoided with work planned and recorded in a checklist.

Related Results

Design and Optimization for Ship Structure Based on Knowledge-Based Engineering
Design and Optimization for Ship Structure Based on Knowledge-Based Engineering
It is always pursued that the excellent ship structure is rapidly designed and modified on the premise of ensuring security in ship engineering. In this paper, design and optimizat...
Urban Vitality Open Science Checklist
Urban Vitality Open Science Checklist
The Urban Vitality Open Science Checklist (UV-OSCL) is a list of 14 items that helps researchers work according to open science principles in all phases of their research Those op...
Connecting Ship Operation and Architecture in Ship Design Processes
Connecting Ship Operation and Architecture in Ship Design Processes
It is challenging to deal with the operation of ships by crew members in ship design processes. This is important because the efficiency and safety of ship operations ultimately de...
Different methods of longwall full mining partial filling and optimal design of filling process
Different methods of longwall full mining partial filling and optimal design of filling process
Abstract Different methods of longwall full mining partial filling have been extensively studied to meet the special mining requirements of pressure coal resources ...
Soviet Shipbuilding: Productivity improvement Efforts
Soviet Shipbuilding: Productivity improvement Efforts
Constant demand for new naval and commercial vessels has created special conditions for the Government-owned Soviet shipbuilding industry, which practically has not been affected b...
Research progress of solid waste resource utilization backfill mining for Jinchuan Nickel Mine, China
Research progress of solid waste resource utilization backfill mining for Jinchuan Nickel Mine, China
The Jinchuan Nickel Mine is the largest large-scale copper–nickel sulfide deposit in China and the third largest in the world. Due to the deep burial of the ore body, high geostres...
Advancing Automation in Early-Stage Navy Ship System Design
Advancing Automation in Early-Stage Navy Ship System Design
Ship systems, such as the electrical distribution and thermal management systems, are larger, more complex, and more integrated than ever before due to the radical increase in elec...

Back to Top