Communication performance challenges in PPP projects: cases of Ghana and South Africa
View through CrossRef
Purpose
The need to gain theoretical and practical understanding into the communication performance challenges in public private partnership (PPP) projects is considered as a precursor to effective communication strategies, management, planning and improvement in PPP models in both developed and developing countries. Hence, the purpose of this paper is to investigate the nature of communication performance challenges in PPP projects.
Design/methodology/approach
By adopting a deductive research design, a questionnaire survey of participants in the communication network of PPP projects in two countries (Ghana and South Africa) was conducted. The responses were analyzed using mean scores, Kendall’s concordance and Mann–Whitney U test.
Findings
The results revealed communication performance challenges that are unique to PPP project environment. Additionally, there were other typologies of communication challenges such as untimeliness, distortions and protocols that were frequently experienced in Ghana and not in South Africa. Also the emergence of misunderstanding affirmed that indeed this is a communication problem that is common and not peculiar to any project context or country.
Practical implications
With communication challenges and information asymmetries as notable challenges in PPP coupled with suggestions that effective communication is central to success of PPP projects and management, the insight into the communication performance challenges given by this study could be very useful to effective planning and strategies towards communication in construction project delivery in PPP and thus underline the importance of deriving mechanisms and protocols that suit PPP project environments.
Originality/value
These findings can be a precursor for developing bespoke communication systems, tools, protocols and communication behaviours to facilitate information flow aimed at overcoming information asymmetries and ultimately improving the quality of communication actions, tasks and outcomes in PPP project delivery.
Title: Communication performance challenges in PPP projects: cases of Ghana and South Africa
Description:
Purpose
The need to gain theoretical and practical understanding into the communication performance challenges in public private partnership (PPP) projects is considered as a precursor to effective communication strategies, management, planning and improvement in PPP models in both developed and developing countries.
Hence, the purpose of this paper is to investigate the nature of communication performance challenges in PPP projects.
Design/methodology/approach
By adopting a deductive research design, a questionnaire survey of participants in the communication network of PPP projects in two countries (Ghana and South Africa) was conducted.
The responses were analyzed using mean scores, Kendall’s concordance and Mann–Whitney U test.
Findings
The results revealed communication performance challenges that are unique to PPP project environment.
Additionally, there were other typologies of communication challenges such as untimeliness, distortions and protocols that were frequently experienced in Ghana and not in South Africa.
Also the emergence of misunderstanding affirmed that indeed this is a communication problem that is common and not peculiar to any project context or country.
Practical implications
With communication challenges and information asymmetries as notable challenges in PPP coupled with suggestions that effective communication is central to success of PPP projects and management, the insight into the communication performance challenges given by this study could be very useful to effective planning and strategies towards communication in construction project delivery in PPP and thus underline the importance of deriving mechanisms and protocols that suit PPP project environments.
Originality/value
These findings can be a precursor for developing bespoke communication systems, tools, protocols and communication behaviours to facilitate information flow aimed at overcoming information asymmetries and ultimately improving the quality of communication actions, tasks and outcomes in PPP project delivery.
Related Results
Deconstructing the Barriers to ASRH in Contemporary Ghana
Deconstructing the Barriers to ASRH in Contemporary Ghana
Adolescent Sexual Reproductive Health (ASRH) is crucial for the physical, emotional, and social well-being of adolescents. The paper aims to identify the barriers to ASRH in Ghana ...
Performance Evaluation of Triple-Frequency GPS/Galileo Techniques for Precise Static and Kinematic Applications
Performance Evaluation of Triple-Frequency GPS/Galileo Techniques for Precise Static and Kinematic Applications
The objective of this research was to develop new precise point positioning (PPP) processing models using triple-frequency GPS/Galileo observations. Different triple-frequency PPP ...
Assessment of the PPP-AR Strategy for ZTD and IWV in Africa: A One-Year GNSS Study
Assessment of the PPP-AR Strategy for ZTD and IWV in Africa: A One-Year GNSS Study
With the increasing demand for near real-time atmospheric water vapor monitoring, this study evaluates the performance of the open-source PRIDE PPP-AR software (version 3.0.5) for ...
Public-Private Partnerships in Republic of Korea: Experience and Results
Public-Private Partnerships in Republic of Korea: Experience and Results
The Republic of Korea came to realize the acute necessity of launching the public-private partnership (PPP) at the turn of the 90s, the country happened to fall short of such infra...
Assessment of Multi-GNSS RT-PPP Services for the Antarctic Region
Assessment of Multi-GNSS RT-PPP Services for the Antarctic Region
The international service that ensures access to data and products of global navigation satellite systems (GNSSs), known as the IGS, runs a real-time service (RTS) project to suppo...
Afrikanske smede
Afrikanske smede
African Smiths Cultural-historical and sociological problems illuminated by studies among the Tuareg and by comparative analysisIn KUML 1957 in connection with a description of sla...
Critical success factors in public‐private partnership (PPP) on infrastructure delivery in Nigeria
Critical success factors in public‐private partnership (PPP) on infrastructure delivery in Nigeria
PurposeFederal and State Governments began to explore more subtle alternatives for accessing private sector resources in the delivery and operation of public facilities. The purpos...
Exploration of building adaptations and retrofitting challenges in Ghana
Exploration of building adaptations and retrofitting challenges in Ghana
Purpose– The Ghanaian banking industry has over the last 20 years witnessed tremendous growth to the extent that rural banks are now expanding their activities into urban centres. ...