PRODUKTIVITAS ALAT EXCAVATOR VIBRO HAMMER UNTUK PEMANCANGAN SSP REUSE PADA PROYEK RENTANG IRRIGATION MODERNIZATION PROJECT DI KABUPATEN MAJALENGKA

View through CrossRef
Rentang Dam is currently implementing a project, namely the Rentang Irrigation ModernizationProject (RIMP), which aims to restore irrigation functions, stabilize soil conditions, and alsooptimize water distribution. One of the projects that is being implemented as an effort to stabilize thecondition of the land is the installation of SSP Reuse piling. In the erection of SSP Reuse, the heavyequipment used was a vibro hammer excavator. From the erection of the SSP Reuse erection usinga vibro hammer excavator, its productivity can be seen. In this study, we review the productivity ofa vibro hammer excavator tool for erecting SSP Reuse on the right side of the CP. 168 – CP. 170110 meters long. The erection of the SSP Reuse is a follow-up effort to ensure that landslides do notoccur and access to residents' houses is wide. The productivity of the vibro hammer excavator forerecting SSP Reuse with a working day of 30 days per 8 hours, the average point obtained per dayis 9.17 sticks. Meanwhile, for the cycle time on day 1 at 13 SSP Reuse points with dimensions of 8 x0.4 m with vibration via a vibro hammer, the total cycle time was 200.71 minutes and the averagecycle was 15.44 minutes. Finally, the average cycle time of the vibro hammer piling tool taken during30 days of work had a cycle time of 11.33 minutes per rod.
Title: PRODUKTIVITAS ALAT EXCAVATOR VIBRO HAMMER UNTUK PEMANCANGAN SSP REUSE PADA PROYEK RENTANG IRRIGATION MODERNIZATION PROJECT DI KABUPATEN MAJALENGKA
Description:
Rentang Dam is currently implementing a project, namely the Rentang Irrigation ModernizationProject (RIMP), which aims to restore irrigation functions, stabilize soil conditions, and alsooptimize water distribution.
One of the projects that is being implemented as an effort to stabilize thecondition of the land is the installation of SSP Reuse piling.
In the erection of SSP Reuse, the heavyequipment used was a vibro hammer excavator.
From the erection of the SSP Reuse erection usinga vibro hammer excavator, its productivity can be seen.
In this study, we review the productivity ofa vibro hammer excavator tool for erecting SSP Reuse on the right side of the CP.
168 – CP.
170110 meters long.
The erection of the SSP Reuse is a follow-up effort to ensure that landslides do notoccur and access to residents' houses is wide.
The productivity of the vibro hammer excavator forerecting SSP Reuse with a working day of 30 days per 8 hours, the average point obtained per dayis 9.
17 sticks.
Meanwhile, for the cycle time on day 1 at 13 SSP Reuse points with dimensions of 8 x0.
4 m with vibration via a vibro hammer, the total cycle time was 200.
71 minutes and the averagecycle was 15.
44 minutes.
Finally, the average cycle time of the vibro hammer piling tool taken during30 days of work had a cycle time of 11.
33 minutes per rod.

Related Results

DAMPAK TEKNOLOGI TERHADAP PROSES BELAJAR MENGAJAR
DAMPAK TEKNOLOGI TERHADAP PROSES BELAJAR MENGAJAR
DAFTAR PUSTAKAAditama, M. H. R., & Selfiardy, S. (2022). Kehidupan Mahasiswa Kuliah Sambil Bekerja di Masa Pandemi Covid-19. Kidspedia: Jurnal Pendidikan Anak Usia Dini, 3(...
Pengaruh Kondisi Alat Berat Terhadap Kelancaran Pekerjaan Pada Proyek Pembangunan Kolam Regulasi Nipa – Nipa
Pengaruh Kondisi Alat Berat Terhadap Kelancaran Pekerjaan Pada Proyek Pembangunan Kolam Regulasi Nipa – Nipa
Meneliti pengaruh kondisi alat berat terhadap kelancaran pekerjaan sangat penting untuk mengidentifikasi faktor-faktor yang mempengaruhi kinerja alat berat dan bagaimana hal terseb...
OPTIMALISASI PRODUKSI ALAT BERAT DALAM PEKERJAAN GALIAN DAN TANAMAN DI PROYEK JALAN RAYA (STUDI KASUS: JALUR LINTAS SELATAN LOT 2 BLITAR)
OPTIMALISASI PRODUKSI ALAT BERAT DALAM PEKERJAAN GALIAN DAN TANAMAN DI PROYEK JALAN RAYA (STUDI KASUS: JALUR LINTAS SELATAN LOT 2 BLITAR)
Abstrak             The effectiveness and success of construction projects is greatly influenced by the productivity of heavy equipment, especially in terms of excavation work an...
Produktivitas Excavator Class PC-2500 dan PC-2000 pada Pembuatan Temporary Sump Paris Barat
Produktivitas Excavator Class PC-2500 dan PC-2000 pada Pembuatan Temporary Sump Paris Barat
Abstract. PT Adaro Indonesia will be in the area of Overburden Loading and Temporary Sump Manufacturing West Paris Bottom Pit South Tutupan. West Paris Sump will be excavated with ...
Analisis Estimasi Penyelesaian Proyek Konstruksi terhadap Waktu dan Biaya
Analisis Estimasi Penyelesaian Proyek Konstruksi terhadap Waktu dan Biaya
Proyek konstruksi merupakan kegiatan yang memiliki tingkat kompleksitas tinggi, sehingga sering terjadi keterlambatan penyelesaian proyek maupun pembengkakan biaya akibat sistem ma...
Analisa Produktivitas Mesin Kerupuk Kentang Dengan Menggunakan Metode Objective Matrix (OMAX)
Analisa Produktivitas Mesin Kerupuk Kentang Dengan Menggunakan Metode Objective Matrix (OMAX)
Pengukuran produktivitas memegang peranan yang sangat penting dalam mengevaluasi dan menentukan strategi lebih lanjut untuk meningkatkan tingkat produktivitas. Penelitian ini bertu...
Aplikasi Metode Earned Value Management Proyek Warehouse
Aplikasi Metode Earned Value Management Proyek Warehouse
Earned Value Management (EVM) adalah suatu pendekatan yang digunakan untuk mengukur dan mengelola kinerja proyek dengan membandingkan nilai sebenarnya yang telah dikerjakan dengan ...
FAKTOR-FAKTOR YANG MEMPENGARUHI MORTALITAS PADA PASIEN DENGAN FRAKTUR COSTA: Literature Review
FAKTOR-FAKTOR YANG MEMPENGARUHI MORTALITAS PADA PASIEN DENGAN FRAKTUR COSTA: Literature Review
FAKTOR-FAKTOR YANG MEMPENGARUHI MORTALITAS PADA PASIEN DENGAN FRAKTUR COSTA: Literature  Review Anna Tri Wahyuni1), Masfuri2),  Liya Arista3)1,2,3 Fakultas Ilmu Keperawatan Univers...

Back to Top