PERBANDINGAN METODE MEKANIS DENGAN METODE BLASTING PADA PEMBANGUNAN TEROWONGAN BENDUNGAN RUKOH

View through CrossRef
The construction of tunnels is a vital component of dam infrastructure projects, including the Rukoh Dam located in Pidie Regency, Nangroe Aceh Darussalam. This research seeks to compare two excavation methods, specifically the mechanical method (breaker) and the blasting method, analyzed concerning time, cost, labor efficiency, and the environmental effects produced. This study employed a mixed method research approach, integrating qualitative and quantitative methods using techniques such as field observation, interviews, documentation, and literature reviews. The analysis results indicate that the blasting method needs just 129 days (33.33%) of the overall work, while the mechanical method takes 194 days (50.12%). This implies that the work process is quicker and more efficient regarding time. The overall expense of labor utilizing the blasting method is Rp. 10,947,465,448 (62%), more efficient than the mechanical method of Rp. 14,585,533,097 (82.6%). Regarding labor, the blasting method needs 56 employees, particularly certified professionals, while the mechanical method requires 50 employees. The environmental effects of the blasting method produce considerable vibrations and require strict supervision to avoid affecting nearby structures and increasing air pollution, while the mechanical method produces low and local vibrations, making it safer for the environment and comparatively more environmentally friendly with controllable pollution. Abstrak Pembangunan terowongan merupakan bagian vital dalam proyek infrastruktur bendungan, salah satunya pada Bendungan Rukoh di Kabupaten Pidie, Nangroe Aceh Darusalam. Penelitian ini bertujuan untuk membandingkan dua metode penggalian yaitu metode mekanis (breaker) dan metode peledakan (blasting) dinilai dari segi efisiensi waktu, biaya dan tenaga kerja, serta dampak lingkungan yang ditimbulkan. Metode penelitian mix method digunakan dalam penelitian ini dengan menggabungkan metode kualitatif dan kuantitatif melalui teknik observasi lapangan, wawancara, dokumentasi, dan studi pustaka. Hasil analisis menunjukkan bahwa metode blasting hanya membutuhkan waktu 129 hari (33,33%) dari total seluruh pekerjaan dibandingkan metode mekanis 194 hari (50,12%). Hal ini berarti pengerjaan kegiatan lebih cepat dan efektif secara waktu. Biaya total pekerjaan dengan menggunakan metode blasting sebesar Rp.10.947.465.448 (62%) lebih efisien dibanding metode mekanis sebesar Rp.14.585.533.097 (82,6%). Dalam hal tenaga kerja, metode blasting membutuhkan 56 pekerja terutama tenaga ahli yang bersertifikasi, sementara metode mekanis membutuhkan 50 pekerja. Dampak lingkungan yang ditimbukan dari metode blasting menghasilkan getaran yang signifikan dan memerlukan pengawasan ketat agar tidak berdampak pada struktur di sekitar lokasi serta menghasilkan polusi udara yang lebih tinggi, sementara metode mekanis menghasilkan getaran rendah dan bersifat lokal, sehingga lebih aman untuk lingkungan sekitar serta relatif lebih ramah lingkungan dengan polusi yang dapat dikendalikan.
Title: PERBANDINGAN METODE MEKANIS DENGAN METODE BLASTING PADA PEMBANGUNAN TEROWONGAN BENDUNGAN RUKOH
Description:
The construction of tunnels is a vital component of dam infrastructure projects, including the Rukoh Dam located in Pidie Regency, Nangroe Aceh Darussalam.
This research seeks to compare two excavation methods, specifically the mechanical method (breaker) and the blasting method, analyzed concerning time, cost, labor efficiency, and the environmental effects produced.
This study employed a mixed method research approach, integrating qualitative and quantitative methods using techniques such as field observation, interviews, documentation, and literature reviews.
The analysis results indicate that the blasting method needs just 129 days (33.
33%) of the overall work, while the mechanical method takes 194 days (50.
12%).
This implies that the work process is quicker and more efficient regarding time.
The overall expense of labor utilizing the blasting method is Rp.
10,947,465,448 (62%), more efficient than the mechanical method of Rp.
14,585,533,097 (82.
6%).
Regarding labor, the blasting method needs 56 employees, particularly certified professionals, while the mechanical method requires 50 employees.
The environmental effects of the blasting method produce considerable vibrations and require strict supervision to avoid affecting nearby structures and increasing air pollution, while the mechanical method produces low and local vibrations, making it safer for the environment and comparatively more environmentally friendly with controllable pollution.
Abstrak Pembangunan terowongan merupakan bagian vital dalam proyek infrastruktur bendungan, salah satunya pada Bendungan Rukoh di Kabupaten Pidie, Nangroe Aceh Darusalam.
Penelitian ini bertujuan untuk membandingkan dua metode penggalian yaitu metode mekanis (breaker) dan metode peledakan (blasting) dinilai dari segi efisiensi waktu, biaya dan tenaga kerja, serta dampak lingkungan yang ditimbulkan.
Metode penelitian mix method digunakan dalam penelitian ini dengan menggabungkan metode kualitatif dan kuantitatif melalui teknik observasi lapangan, wawancara, dokumentasi, dan studi pustaka.
Hasil analisis menunjukkan bahwa metode blasting hanya membutuhkan waktu 129 hari (33,33%) dari total seluruh pekerjaan dibandingkan metode mekanis 194 hari (50,12%).
Hal ini berarti pengerjaan kegiatan lebih cepat dan efektif secara waktu.
Biaya total pekerjaan dengan menggunakan metode blasting sebesar Rp.
10.
947.
465.
448 (62%) lebih efisien dibanding metode mekanis sebesar Rp.
14.
585.
533.
097 (82,6%).
Dalam hal tenaga kerja, metode blasting membutuhkan 56 pekerja terutama tenaga ahli yang bersertifikasi, sementara metode mekanis membutuhkan 50 pekerja.
Dampak lingkungan yang ditimbukan dari metode blasting menghasilkan getaran yang signifikan dan memerlukan pengawasan ketat agar tidak berdampak pada struktur di sekitar lokasi serta menghasilkan polusi udara yang lebih tinggi, sementara metode mekanis menghasilkan getaran rendah dan bersifat lokal, sehingga lebih aman untuk lingkungan sekitar serta relatif lebih ramah lingkungan dengan polusi yang dapat dikendalikan.

Related Results

FAKTOR-FAKTOR YANG MEMPENGARUHI MORTALITAS PADA PASIEN DENGAN FRAKTUR COSTA: Literature Review
FAKTOR-FAKTOR YANG MEMPENGARUHI MORTALITAS PADA PASIEN DENGAN FRAKTUR COSTA: Literature Review
FAKTOR-FAKTOR YANG MEMPENGARUHI MORTALITAS PADA PASIEN DENGAN FRAKTUR COSTA: Literature  Review Anna Tri Wahyuni1), Masfuri2),  Liya Arista3)1,2,3 Fakultas Ilmu Keperawatan Univers...
ANALISIS ALTERNATIF PERENCANAAN DIMENSI TEROWONGAN PENGELAK BENDUNGAN SIDAN
ANALISIS ALTERNATIF PERENCANAAN DIMENSI TEROWONGAN PENGELAK BENDUNGAN SIDAN
Kekurangan pasokan air di Provinsi Bali menyebabkan adanya rencana pembangunan Bendungan Sidan. Bendungan ini direncanakan dengan inti tegak dan dilengkapi dengan terowongan pengel...
Implementasi Early Warning System Bencana Banjir berdasarkan Ketinggian Air Bendungan
Implementasi Early Warning System Bencana Banjir berdasarkan Ketinggian Air Bendungan
Bendungan Sampean Baru merupakan salah satu bendungan yang berada di Kabupaten Bondowoso Jawa Timur. Bendungan ini memiliki dua fungsi utama yaitu sebagai irigasi dan PLTM. Berdasa...
Refined Design and Optimization of Underground Medium and Long Hole Blasting Parameters—A Case Study of the Gaofeng Mine
Refined Design and Optimization of Underground Medium and Long Hole Blasting Parameters—A Case Study of the Gaofeng Mine
Previously conducted studies have established that the rationality of the parameters of medium-deep hole blasting is one of the main factors affecting the blasting effect. To solve...
A Numerical Simulation Study of Focused Hydraulic Blasting in Coal Seams of Open‐Pit Mines
A Numerical Simulation Study of Focused Hydraulic Blasting in Coal Seams of Open‐Pit Mines
In the process of open‐pit coal mining, traditional blasting methods often lead to issues such as uneven fragmentation, difficult vibration control, and significant dust pollution....
POLA ASUH IBU TERHADAP PERKEMBANGAN SOSIAL EMOSIONAL ANAK USIA DINI DI GAMPONG RUKOH KECAMATAN SYIAH KUALA
POLA ASUH IBU TERHADAP PERKEMBANGAN SOSIAL EMOSIONAL ANAK USIA DINI DI GAMPONG RUKOH KECAMATAN SYIAH KUALA
Kesalahan yang sering tidak disadari oleh orang tua dalam mengasuh anak-anaknya, kadang orang tua bersikap terlalu menekan, selalu memerintah, anak harus tunduk dan patuh kemauan o...
KECEMASAN SAAT PANDEMI COVID 19: LITERATUR REVIEW Hardiyati, Efri Widianti, Taty Hernawaty Departemen Keperawatan Jiwa Poltekkes Kemenkes Mamuju Sulbar, Universitas Pad...

Back to Top