Javascript must be enabled to continue!
The Application of PLC Distributed Input/Output Technology Offshore
View through CrossRef
ABSTRACT
The Programmable Logic Controller is becoming a familiar part of the Process Controls on Offshore Facilities. The current evolution of this expanding technology is Distributed 1/0 Blocks, and this paper is concerned with the benefits and applications this new technology brings to the Offshore Industry.
The advent of the Programmable Logic Controller to the Gulf of Mexico brought greater process control flexibility to Offshore facilities. The offshore control philosophy wentfrom independent pneumatic control of each skid unit to PLC distributed control with field panels that contained the local controls for several skid units and interfaced with control room based PLC visual display stations.
The Distributed 1/0 Block concept allows offshore control systems to eliminate the large field interface panel, along with the associated wiring and hardware cost. This is accomplished by installing Distributed l/O Blocks inside the individual skid control panels and then communicating back to the control room based PLC via redundant communication cables. The control wiring between each skid control panel and the control room is now reduced to one power cable and redundant communication cables.
PROJECT OVERVIEW
The PLC distributed 1/0 system discussed in this paper was installed on an existing semi-submersible drilling Modu modified to include first stage processing equipment for separation of water, oil and gas. " The vessel ';Enserch Garden Banks" is now classified as a Floating ProductionFacility and will be located in the Gulf of Mexico at Garden Banks Block 388.
The Garden Banks 388 Project used two separate PLC'S. The ESD or safety PLC was dedicated to the emergency shutdown system while the control PLC handled all process variable indications, special control applications, and production reports. The dedication of one PLC for the ESD system is part of the regulatory agencies requirementfor all ESD systems to be separate from other systems. The ESD PLC employed two CPU's in the "hot" standby configuration and communicated with the distributed l/O via redundant communication cables.
The separation of water, oil and gas is one of the simplest applications possible for process control and conventional pneumatic instrumentation was considered adequate forthis task. The programming flexibility and alarm logging make the PLC especially useful for offshore ESDapplications. Historically, ESD controls offshore have been extremely easy for operations personnel to disable due to bypass controls installed to allow government mandated testing. The Garden Banks 388 PLC logs each ESD bypass alarm on the printer and leaves an alarm banner on the visual display until the bypass is reset. This printed documentation and visual display makesoperations supervisors more aware of ESD bypass status, resulting in a safer facility.
The process skid panels housed both analog and discrete distributed 1/0 blocks. The analog distributed 1/0 blockscommunicated ESD alarms and bypass control status back to the safety PLC. Local alarms consisted of pilot lights on the panel front and were limited to ESD alarmsand shutdown valve status. These alarm lights were energized by end devices with two sets of contacts.
Title: The Application of PLC Distributed Input/Output Technology Offshore
Description:
ABSTRACT
The Programmable Logic Controller is becoming a familiar part of the Process Controls on Offshore Facilities.
The current evolution of this expanding technology is Distributed 1/0 Blocks, and this paper is concerned with the benefits and applications this new technology brings to the Offshore Industry.
The advent of the Programmable Logic Controller to the Gulf of Mexico brought greater process control flexibility to Offshore facilities.
The offshore control philosophy wentfrom independent pneumatic control of each skid unit to PLC distributed control with field panels that contained the local controls for several skid units and interfaced with control room based PLC visual display stations.
The Distributed 1/0 Block concept allows offshore control systems to eliminate the large field interface panel, along with the associated wiring and hardware cost.
This is accomplished by installing Distributed l/O Blocks inside the individual skid control panels and then communicating back to the control room based PLC via redundant communication cables.
The control wiring between each skid control panel and the control room is now reduced to one power cable and redundant communication cables.
PROJECT OVERVIEW
The PLC distributed 1/0 system discussed in this paper was installed on an existing semi-submersible drilling Modu modified to include first stage processing equipment for separation of water, oil and gas.
" The vessel ';Enserch Garden Banks" is now classified as a Floating ProductionFacility and will be located in the Gulf of Mexico at Garden Banks Block 388.
The Garden Banks 388 Project used two separate PLC'S.
The ESD or safety PLC was dedicated to the emergency shutdown system while the control PLC handled all process variable indications, special control applications, and production reports.
The dedication of one PLC for the ESD system is part of the regulatory agencies requirementfor all ESD systems to be separate from other systems.
The ESD PLC employed two CPU's in the "hot" standby configuration and communicated with the distributed l/O via redundant communication cables.
The separation of water, oil and gas is one of the simplest applications possible for process control and conventional pneumatic instrumentation was considered adequate forthis task.
The programming flexibility and alarm logging make the PLC especially useful for offshore ESDapplications.
Historically, ESD controls offshore have been extremely easy for operations personnel to disable due to bypass controls installed to allow government mandated testing.
The Garden Banks 388 PLC logs each ESD bypass alarm on the printer and leaves an alarm banner on the visual display until the bypass is reset.
This printed documentation and visual display makesoperations supervisors more aware of ESD bypass status, resulting in a safer facility.
The process skid panels housed both analog and discrete distributed 1/0 blocks.
The analog distributed 1/0 blockscommunicated ESD alarms and bypass control status back to the safety PLC.
Local alarms consisted of pilot lights on the panel front and were limited to ESD alarmsand shutdown valve status.
These alarm lights were energized by end devices with two sets of contacts.
Related Results
Alternative Offshore Foundation Installation Methods
Alternative Offshore Foundation Installation Methods
Abstract
According to the European Wind Energy Association (EWEA) in the first six months of 2012, Europe installed and fully grid connected 132 offshore wind tur...
Interpretable modelling of input-output computations in cortex
Interpretable modelling of input-output computations in cortex
AbstractNeurons receive input from thousands of synapses, which they transform into action potentials (APs) via their complex dendrites. How the dendritic location of these inputs,...
A Model for Optimal Economic Lockdown to Contain Epidemic
A Model for Optimal Economic Lockdown to Contain Epidemic
This paper is concerned with the application of operations research in defining the optimal lockdown of economic activities to contain epidemic. The problem of optimal lockdown con...
Offshore Giant Fields, 1950-1990
Offshore Giant Fields, 1950-1990
ABSTRACT
OFFSHORE GIANT FIELDS
1950 - 1990
During the past forty years...
Floating LNG: New Rule Note for the Classification of LNG FPSO
Floating LNG: New Rule Note for the Classification of LNG FPSO
Abstract
Offshore LNG terminals are today broadly considered by the industry to respond to the world thirst of energy in a rapid and efficient manner. In order to...
Offshore geotechnical challenges of the energy transition
Offshore geotechnical challenges of the energy transition
Offshore wind is the most mature of the offshore renewable energy technologies and has a significant role to play in the energy transition. 2000 GW of offshore wind capacity is ant...
The significance and factors leading to heteroploidy in pleural lavage cytology
The significance and factors leading to heteroploidy in pleural lavage cytology
Introduction: Positive intraoperative pleural lavage cytology (pre-resection PLC) is considered a prognostic risk factor of primary lung cancer surgery. Positive findings suggest s...
Offshore Exploration Potential
Offshore Exploration Potential
ABSTRACT
There are 799 indentified sedimentary provinces which possibly could contain hydrocarbons. Of these, 481 are located offshore or partly offshore. Eight o...


