Effects of Input Price Uncertainty on Asset Valuation

View through CrossRef
Abstract Most future input prices (unit costs) in the upstream petroleum industry are not known with certainty. This can have important effects on asset value and management. One criticism of most past petroleum industry applications of real options analysis (ROA) is that they have neglected to consider the effects of this type of uncertainty. This paper explores a few of the issues that arise in discounted cash-flow (DCF) and ROA asset valuations, if a specific type of input price uncertainty is considered. In particular, we look at the effects of the correlation of unit costs with output petroleum prices. Unit drilling costs, for example, tend to be high/low if petroleum prices are high/low or have gone up/down unexpectedly. The first "rent" effect occurs if the market for drilling services is not completely competitive. The second "quasi-rent" effect occurs if it takes time for the suppliers of these services to adjust the amounts they supply in the face of unexpected changes in demand. We first examine, using both ROA and DCF methods of analysis, some relatively simple assets where the asset cash-flow dependence on input and output prices, and of the input prices on the output prices, is linear. Two points are made. First, for a set of given input price expectations, DCF estimates of the value of these assets will be independent of the level of input price uncertainty, unless the discount rate is adjusted to reflect the change in risk. ROA estimates of value will automatically pick up the effects of different levels of risk. If the unit costs are generally correlated with the macro-economy (as will be the case with a rent effect and most quasirent effects, if the output prices are so correlated), for a set of given input price expectations, a greater level of input price uncertainty would decrease the estimate of the value of the costs in the asset cash-flows, because of the greater risk discounting that it induces. This would increase the ROA estimate of the value of the asset as a whole. Second, it has been conjectured that a greater similarity between revenue and cost uncertainty, by making revenue and cost discounting more similar in ROA analyses, will tend to mitigate some of the differences between the structure of ROA and DCF value estimates. This would decrease the benefits of a shift from the use of DCF methods of analysis to the use of ROA. We analyse variations of two previously published examples of analyses of assets with linear cash-flows to explore these matters. We then examine an asset where there are non-linearities in the dependence of asset cash-flows on prices. These may be due to non-linear price models, non-linear taxes or flexibility in project management. In the specific asset we analyse, which is also based on a previously published example, the non-linearities arise from flexibility. In this case, we find some similarities and some differences in structure of the effects of input price uncertainty on asset value. The example is of an oil field in the final year of its development lease, where there is an option to sanction development immediately, or to appraise or wait for another year and decide then between development or abandonment. At sanction, there is a production capacity choice to be made, and after sanction there is an annual abandonment option. Again, two points are made. First, if the input price expectations are roughly the same, input price uncertainty of the simplest kind (stemming from a linear "rent" effect) again increases ROA estimates of asset value and leaves the DCF value estimates roughly the same. Second, rather than mitigating the differences between DCF methods of analysis and ROA, cost uncertainty in this example accentuates the losses from using DCF methods if ROA should be used. Unit cost uncertainty interacts with the differences in the methods of value estimation to make the management policies suggested by DCF and ROA more different in the presence of this uncertainty. All of this suggests that the industry should keep track of the uncertainty in its input prices, and their correlation with output petroleum prices and with each other. This paper shows how this would be useful for project analysis. It would also be useful in the development of appropriate risk management policies.
Title: Effects of Input Price Uncertainty on Asset Valuation
Description:
Abstract Most future input prices (unit costs) in the upstream petroleum industry are not known with certainty.
This can have important effects on asset value and management.
One criticism of most past petroleum industry applications of real options analysis (ROA) is that they have neglected to consider the effects of this type of uncertainty.
This paper explores a few of the issues that arise in discounted cash-flow (DCF) and ROA asset valuations, if a specific type of input price uncertainty is considered.
In particular, we look at the effects of the correlation of unit costs with output petroleum prices.
Unit drilling costs, for example, tend to be high/low if petroleum prices are high/low or have gone up/down unexpectedly.
The first "rent" effect occurs if the market for drilling services is not completely competitive.
The second "quasi-rent" effect occurs if it takes time for the suppliers of these services to adjust the amounts they supply in the face of unexpected changes in demand.
We first examine, using both ROA and DCF methods of analysis, some relatively simple assets where the asset cash-flow dependence on input and output prices, and of the input prices on the output prices, is linear.
Two points are made.
First, for a set of given input price expectations, DCF estimates of the value of these assets will be independent of the level of input price uncertainty, unless the discount rate is adjusted to reflect the change in risk.
ROA estimates of value will automatically pick up the effects of different levels of risk.
If the unit costs are generally correlated with the macro-economy (as will be the case with a rent effect and most quasirent effects, if the output prices are so correlated), for a set of given input price expectations, a greater level of input price uncertainty would decrease the estimate of the value of the costs in the asset cash-flows, because of the greater risk discounting that it induces.
This would increase the ROA estimate of the value of the asset as a whole.
Second, it has been conjectured that a greater similarity between revenue and cost uncertainty, by making revenue and cost discounting more similar in ROA analyses, will tend to mitigate some of the differences between the structure of ROA and DCF value estimates.
This would decrease the benefits of a shift from the use of DCF methods of analysis to the use of ROA.
We analyse variations of two previously published examples of analyses of assets with linear cash-flows to explore these matters.
We then examine an asset where there are non-linearities in the dependence of asset cash-flows on prices.
These may be due to non-linear price models, non-linear taxes or flexibility in project management.
In the specific asset we analyse, which is also based on a previously published example, the non-linearities arise from flexibility.
In this case, we find some similarities and some differences in structure of the effects of input price uncertainty on asset value.
The example is of an oil field in the final year of its development lease, where there is an option to sanction development immediately, or to appraise or wait for another year and decide then between development or abandonment.
At sanction, there is a production capacity choice to be made, and after sanction there is an annual abandonment option.
Again, two points are made.
First, if the input price expectations are roughly the same, input price uncertainty of the simplest kind (stemming from a linear "rent" effect) again increases ROA estimates of asset value and leaves the DCF value estimates roughly the same.
Second, rather than mitigating the differences between DCF methods of analysis and ROA, cost uncertainty in this example accentuates the losses from using DCF methods if ROA should be used.
Unit cost uncertainty interacts with the differences in the methods of value estimation to make the management policies suggested by DCF and ROA more different in the presence of this uncertainty.
All of this suggests that the industry should keep track of the uncertainty in its input prices, and their correlation with output petroleum prices and with each other.
This paper shows how this would be useful for project analysis.
It would also be useful in the development of appropriate risk management policies.

Related Results

Reserves Uncertainty Calculation Accounting for Parameter Uncertainty
Reserves Uncertainty Calculation Accounting for Parameter Uncertainty
Abstract An important goal of geostatistical modeling is to assess output uncertainty after processing realizations through a transfer function, in particular, to...
The behavioral valuation apparatus
The behavioral valuation apparatus
Subject. The article discusses behavioral valuation tools and focuses on the creation of the behavioral valuation methodology. Objectives The study reveals mechanisms for setting b...
Designing a Digital Marketplace Platform for Optimizing the Exchange of Distressed Oilfield Assets in Emerging Markets
Designing a Digital Marketplace Platform for Optimizing the Exchange of Distressed Oilfield Assets in Emerging Markets
The efficient exchange of distressed oilfield assets in emerging markets is a critical challenge due to market inefficiencies, regulatory constraints, and valuation complexities. T...
Valuation Methods in Ecosystem Services: A Meta-analysis
Valuation Methods in Ecosystem Services: A Meta-analysis
Abstract Ecosystem services are the benefits people obtain from ecosystems, including provisioning, regulating, supporting, and cultural services. The Meta-analysis of this...
Studies on Sensitivity and Uncertainty Analyses for SCOPE and WAFT With Uncertainty Propagation Methods
Studies on Sensitivity and Uncertainty Analyses for SCOPE and WAFT With Uncertainty Propagation Methods
The purpose of Steam condensation on cold plate experiment facility (SCOPE) and Water film test (WAFT) is to verify the steam condensation and water film evaporation correlation wi...
The Intention of Bridge Asset Management Implementation in Indonesia
The Intention of Bridge Asset Management Implementation in Indonesia
The need for effective bridge asset management in Indonesia has become crucial. Currently, the number of bridge assets in Indonesia is continuously increasing, parallel to the risi...

Back to Top