Installation Of A Gravity Structure Over Predrilled Wells
View through CrossRef
Abstract
Experience has proved that gravity platforms could be installed with maximum accuracy with the help of tugs. The main objective is to improve this accuracy to more or less 2 inches, so as to allow installation of a structure over a template, comprising a certain number of predrilled wells.
Studies demonstrating the feasibility of such operations in complete reliability are progressing in this field.
This type of installation allows the drilling operations while the structure in under construction. When the structure is installed, the conductors connection and well completions can be achieved. The time gained by such a method in platform exploitation is about one year.
Introduction
The present techniques devised for the exploitation of undersea oil fields require huge investments and long time lags before starting production. It takes 2 to 3 years to build and production. It takes 2 to 3 years to build and equip a platform, notwithstanding the time spend in preliminary studies. preliminary studies. The platform must be installed in the location and fitted up with all relevant equipment before starting any drilling operations, which last an additional 2 years, during which time production is not possible.
The advantage of the new STC concept is that it allows both operations, building the platform and drilling the wells, to be carried out simultaneously, which means saving two years in the actual exploitation of a field.
SEA TANK CO have just completed the first stage of a study on the improvements of a gravity platform, the equipment needed and the procedure to allow the installation of such a structure on the sea bed, on predrilled wells not yet productive, with no risk of predrilled wells not yet productive, with no risk of deteriorating the wells themselves and so as to allow future connection with the surface equipment supported by the platform, specially the well-heads.
This procedure necessitates the checking of the behaviour cf the predrilled wells. Comprehensive studies show that the effect of subsequent settlements occuring after the emplacement of the platform does not induce overstressing of the conductor pipes.
CONTEMPLATED PROCEDURE
Observers have been quite impressed by the precisions with which a platform may be controlled precisions with which a platform may be controlled during immersion for the deck mating, and also by the accuracy displayed when placing some platforms with the only help of tugs.
The results published up to day, regarding the off target distance show an accuracy of less than 10 m, when a platform is installed alone in the field, and 1 to 2 m when it is installed in the neighbourhood of a preexisting platform.
This is mainly due to the good behaviour of the platforms under the action of waves and the reliability platforms under the action of waves and the reliability of the immersion system.
Some of the techniques now in use have to be adapted and improved for the installation of a gravity platform over drilled wells. platform over drilled wells.- the template, which is fixed on the sea bed and through which the wells are predrilled, has to be sufficiently protected so as to be able to withstand the contact with the platform and ensure its final centering.
P. 155
Title: Installation Of A Gravity Structure Over Predrilled Wells
Description:
Abstract
Experience has proved that gravity platforms could be installed with maximum accuracy with the help of tugs.
The main objective is to improve this accuracy to more or less 2 inches, so as to allow installation of a structure over a template, comprising a certain number of predrilled wells.
Studies demonstrating the feasibility of such operations in complete reliability are progressing in this field.
This type of installation allows the drilling operations while the structure in under construction.
When the structure is installed, the conductors connection and well completions can be achieved.
The time gained by such a method in platform exploitation is about one year.
Introduction
The present techniques devised for the exploitation of undersea oil fields require huge investments and long time lags before starting production.
It takes 2 to 3 years to build and production.
It takes 2 to 3 years to build and equip a platform, notwithstanding the time spend in preliminary studies.
preliminary studies.
The platform must be installed in the location and fitted up with all relevant equipment before starting any drilling operations, which last an additional 2 years, during which time production is not possible.
The advantage of the new STC concept is that it allows both operations, building the platform and drilling the wells, to be carried out simultaneously, which means saving two years in the actual exploitation of a field.
SEA TANK CO have just completed the first stage of a study on the improvements of a gravity platform, the equipment needed and the procedure to allow the installation of such a structure on the sea bed, on predrilled wells not yet productive, with no risk of predrilled wells not yet productive, with no risk of deteriorating the wells themselves and so as to allow future connection with the surface equipment supported by the platform, specially the well-heads.
This procedure necessitates the checking of the behaviour cf the predrilled wells.
Comprehensive studies show that the effect of subsequent settlements occuring after the emplacement of the platform does not induce overstressing of the conductor pipes.
CONTEMPLATED PROCEDURE
Observers have been quite impressed by the precisions with which a platform may be controlled precisions with which a platform may be controlled during immersion for the deck mating, and also by the accuracy displayed when placing some platforms with the only help of tugs.
The results published up to day, regarding the off target distance show an accuracy of less than 10 m, when a platform is installed alone in the field, and 1 to 2 m when it is installed in the neighbourhood of a preexisting platform.
This is mainly due to the good behaviour of the platforms under the action of waves and the reliability platforms under the action of waves and the reliability of the immersion system.
Some of the techniques now in use have to be adapted and improved for the installation of a gravity platform over drilled wells.
platform over drilled wells.
- the template, which is fixed on the sea bed and through which the wells are predrilled, has to be sufficiently protected so as to be able to withstand the contact with the platform and ensure its final centering.
P.
155.
Related Results
Gravity data reduction, Bouguer anomaly, and gravity disturbance
Gravity data reduction, Bouguer anomaly, and gravity disturbance
Each point on the earth has a gravity and gravity potential value. Surfaces formed by connecting points with equal gravity potential values are called equipotential surfaces or lev...
Survey Of Horizontal Gas Well Activity
Survey Of Horizontal Gas Well Activity
Abstract
This paper presents the results of a survey on horizontal gas well activity throughout the world. The survey was conducted for the Gas Research Institute...
Auger TLP Well System Challenges and Innovations
Auger TLP Well System Challenges and Innovations
ABSTRACT
The Auger TLP well system has successfully employed novel features to satisfy challenging design requirements of drilling, completing, and producing near...
Using spherical scaling functions in scalar and vector airborne gravimetry
Using spherical scaling functions in scalar and vector airborne gravimetry
<p>Airborne gravimetry is capable to provide Earth&#8217;s gravity data of high accuracy and spatial resolution for any area of interest, in particular for ha...
SS: Spar Technology- Developments in Deepwater spar installation
SS: Spar Technology- Developments in Deepwater spar installation
Abstract
During the last seven years Heerema Marine Contractors (HMC) has installed more than half of all Spars in the deep waters of the Gulf of Mexico. The dual...
The Absolute Gravity Reference Network of Italy
The Absolute Gravity Reference Network of Italy
The project for realizing the reference network for absolute gravity in the Italian area is presented. This fundamental infrastructure is the general frame for all the scientific a...
A Reservoir Assessment of The Geysers Geothermal Field
A Reservoir Assessment of The Geysers Geothermal Field
Summary
Big Sulphur Creek fault zone may be part of a deep-seated, wrench-style fault system through which hydrothermal fluids from deeper horizons rise to relati...
Water Cresting Behavior Under High Angle Wells: An Experimental Investigation
Water Cresting Behavior Under High Angle Wells: An Experimental Investigation
Abstract
Most of the published papers related to bottom water movement deal with vertical and horizontal wells. The behavior of water cresting under high angle we...