Installation of the Vityaz Production Complex
View through CrossRef
Abstract
This paper describes the summer 1998 offshore installation of the Sakhalin Energy Vityaz Production Complex. The paper details the various facilities installed, the marine equipment used, logistical obstacles and some of the unexpected developments during the installation. Key elements of the Vityaz Production Complex include the modified Molikpaq platform, a 2-km long by 324-mm diameter pipeline for oil export, the SALM base structure/pipeline end manifold, and SALM buoy for FSO tanker mooring.
Van Oord ACZ of the Netherlands was the main contractor for the installation, which included five very different activities: towing with multiple tugs, dredging, rock dumping, pipeline laying and traditional derrick barge activities of heavy lifting/diving/pile driving. Foundex, Ltd of Canada performed explosive densification of the approximately 350,000 metric tons of sand loaded into the core of the Molikpaq.
Each of the following activities covered here includes valuable lessons for future frontier projects in remote areas:Molikpaq tow from Korea to Sakhalin IslandBallasting and set down of the MolikpaqDredging activitiesScour protection activitiesSALM base and buoy installationPipeline installationCore fill explosive densificationLogistics of working in remote parts of Russia
The contractors relied on personnel from more than 20 countries to bring together the wide variety of skills required for this landmark project. The project management team required interpersonal skills to negotiate between the various cultures, languages and work practices in order to safely carry out the installation activities.
The installation of the Vityaz Production Complex has progressed smoothly and has helped to build confidence within the Russian Federation that the Sakhalin II production sharing agreement will bring long-term economic benefits to the country and region.
Introduction
The Vityaz Production Complex offshore Sakhalin Island (Russian Far East) centers around the permanent drilling and production unit Molikpaq and serves the Phase I development of the Piltun-Astokhskoye (PA) Field.
The Molikpaq (a modified existing steel Mobile Arctic Caisson) is an octagonal bottom founded steel annular structure over the Astokh feature of the PA Field. The facility will have an oil production and gas handling capacity of 4.5 million tonnes/year (90,000 B/D) and 0.74 billion m3/year (72 mmscf/D), respectively. The oil produced will be transferred by pipeline to a SALM Buoy, which forms the mooring point for a Floating Storage and Off loading tanker (FSO) for off loading to buyer tankers. The Phase I development scenario is shown in Figure 1.
The Molikpaq was constructed in 1983/1984 as a Mobile Arctic Caisson, offshore drilling unit, with a classification rating of ABS ice class 1AA. The Molikpaq has operated in this capacity in the Beaufort Sea (Canadian Arctic) as a drilling facility only. For its new application offshore Sakhalin a Process Module and other facilities were added. In addition, it was mated with a 15 meter high substructure, the so-called "Spacer", during a nine months refurbishment programme at the Daewoo Heavy Industries Shipyard at Okpo, South Korea. The Molikpaq was then towed from Korea to the installation location offshore Sakhalin Island. It was placed on an engineered foundation pad formed by dumping of dredged sand into an excavation which removed inferior seabed material. After set-down of the platform, the centre core of the Molikpaq was hydraulically filled with dredged sand. The foundation pad soil improvement and core filling was requi
Title: Installation of the Vityaz Production Complex
Description:
Abstract
This paper describes the summer 1998 offshore installation of the Sakhalin Energy Vityaz Production Complex.
The paper details the various facilities installed, the marine equipment used, logistical obstacles and some of the unexpected developments during the installation.
Key elements of the Vityaz Production Complex include the modified Molikpaq platform, a 2-km long by 324-mm diameter pipeline for oil export, the SALM base structure/pipeline end manifold, and SALM buoy for FSO tanker mooring.
Van Oord ACZ of the Netherlands was the main contractor for the installation, which included five very different activities: towing with multiple tugs, dredging, rock dumping, pipeline laying and traditional derrick barge activities of heavy lifting/diving/pile driving.
Foundex, Ltd of Canada performed explosive densification of the approximately 350,000 metric tons of sand loaded into the core of the Molikpaq.
Each of the following activities covered here includes valuable lessons for future frontier projects in remote areas:Molikpaq tow from Korea to Sakhalin IslandBallasting and set down of the MolikpaqDredging activitiesScour protection activitiesSALM base and buoy installationPipeline installationCore fill explosive densificationLogistics of working in remote parts of Russia
The contractors relied on personnel from more than 20 countries to bring together the wide variety of skills required for this landmark project.
The project management team required interpersonal skills to negotiate between the various cultures, languages and work practices in order to safely carry out the installation activities.
The installation of the Vityaz Production Complex has progressed smoothly and has helped to build confidence within the Russian Federation that the Sakhalin II production sharing agreement will bring long-term economic benefits to the country and region.
Introduction
The Vityaz Production Complex offshore Sakhalin Island (Russian Far East) centers around the permanent drilling and production unit Molikpaq and serves the Phase I development of the Piltun-Astokhskoye (PA) Field.
The Molikpaq (a modified existing steel Mobile Arctic Caisson) is an octagonal bottom founded steel annular structure over the Astokh feature of the PA Field.
The facility will have an oil production and gas handling capacity of 4.
5 million tonnes/year (90,000 B/D) and 0.
74 billion m3/year (72 mmscf/D), respectively.
The oil produced will be transferred by pipeline to a SALM Buoy, which forms the mooring point for a Floating Storage and Off loading tanker (FSO) for off loading to buyer tankers.
The Phase I development scenario is shown in Figure 1.
The Molikpaq was constructed in 1983/1984 as a Mobile Arctic Caisson, offshore drilling unit, with a classification rating of ABS ice class 1AA.
The Molikpaq has operated in this capacity in the Beaufort Sea (Canadian Arctic) as a drilling facility only.
For its new application offshore Sakhalin a Process Module and other facilities were added.
In addition, it was mated with a 15 meter high substructure, the so-called "Spacer", during a nine months refurbishment programme at the Daewoo Heavy Industries Shipyard at Okpo, South Korea.
The Molikpaq was then towed from Korea to the installation location offshore Sakhalin Island.
It was placed on an engineered foundation pad formed by dumping of dredged sand into an excavation which removed inferior seabed material.
After set-down of the platform, the centre core of the Molikpaq was hydraulically filled with dredged sand.
The foundation pad soil improvement and core filling was requi.
Related Results
Sakhalin II Project Overview
Sakhalin II Project Overview
Abstract
The Sakhalin Project overview discusses the origin of Sakhalin Energy, its participants, organization, supervision by Russian Federation--as guided by th...
SS: Spar Technology- Developments in Deepwater spar installation
SS: Spar Technology- Developments in Deepwater spar installation
Abstract
During the last seven years Heerema Marine Contractors (HMC) has installed more than half of all Spars in the deep waters of the Gulf of Mexico. The dual...
SS: MODU Anchor: Improved Predictions of MODU Fluke Anchors Increases the Confidence in Mooring System Design
SS: MODU Anchor: Improved Predictions of MODU Fluke Anchors Increases the Confidence in Mooring System Design
Abstract
An overview of the current Norwegian and international requirements for design and installation of fluke anchors is given. Important design and installat...
Independence Installation
Independence Installation
Abstract
This Session paper will review the planning, preparation, and execution of the installation of the Independence Hub facility in Mississippi Canyon Block ...
Neptune Project: Spar Hull, Mooring and Topsides Installation
Neptune Project: Spar Hull, Mooring and Topsides Installation
Abstract
This paper describes the installation of the Neptune Spar at Viosca Knoll Block 826, approximately 90 miles south of Mobile, Alabama in the Gulf of Mexic...
Challenges of TLP Installation Offshore Brazil
Challenges of TLP Installation Offshore Brazil
Abstract
Installation of a Tension Leg Platform comprises distinct phases, all of which can provide special challenges when considering locating a TLP in a fronti...
Offshore WTG Monopile Installation – Crane Vessel Preparation
Offshore WTG Monopile Installation – Crane Vessel Preparation
Abstract
Oil and Gas EPC contractors in the Middle East are gradually transitioning into the Wind farm development projects in Far East Asia and Europe. NPCC, one of...
Girassol Export Lines
Girassol Export Lines
Abstract
This paper will describe the development of a new pipeline concept for the export of oil from a large capacity FPSO to an offloading buoy. The installati...