Javascript must be enabled to continue!
Innovative Multilateral Well Construction System: Accelerated Development and Integrated Capabilities
View through CrossRef
Abstract
This paper discusses the development of an innovative multilateral well construction system, showcasing its swift progression from conceptualization to implementation. The system’s creation was characterized by an efficient and accelerated process, resulting in a solution that seamlessly integrates multiple customer-specified requirements with existing robust capabilities.
The system was specifically developed for use on the AkerBP operated KEG (Kobra East Gekko) field development in the Alvheim area, offshore Norway. Historically, individual branch control multilateral systems have not been installed in tri-lateral wells within the Alvheim area, with one previous attempt resulting in only partial success – hence a new system was required.
The system development commenced with a comprehensive analysis of existing multilateral well construction methodologies, identifying gaps and inefficiencies. Leveraging this insight, an interdisciplinary team of operator, service company, and third-party personnel collaborated to define system requirements resulting in a forward-thinking multilateral well construction system. The emphasis was on expediting the development lifecycle without compromising quality, reliability, or safety standards.
Through meticulous testing and simulation processes, the system’s components were refined to optimize performance as defined in the initial stages of the development. This iterative testing phase, including an extensive System Integration Test (SIT) not only ensured the robustness of the system but also facilitated the integration of an extensive number of intelligent upper completion configurations. These new capabilities, collectively elevate the efficiency and precision of the multilateral well construction process.
A collaborative approach ensured flawless project execution all the way from definition, through complete design and development, detailed operations planning, and finally field execution. An accelerated definition phase was completed, and in the following 12 months a complete level 5 pressure-isolated multilateral system was developed, including rigorous testing and validation of several new components.
The extensive System Integration Test (SIT) was conducted in several stages – both in test facilities in the USA and Norway – to ensure both the multilateral system itself met requirements, but also confirmed compatibility with many different intelligent upper completion configurations, including zonal isolation packers, inflow control valves and gauge carriers.
The first KEG tri-lateral well was successfully completed in Q1 2023, including installation of the upper completion being run through both junction systems. This was followed by successful installation of the system on the remaining three KEG tri-lateral wells by Q4 2023. A significant reduction in installation times and associated NPT has also been observed when installing the new system.
The successful deployment of this multilateral well construction system marks a milestone in the industry, presenting a scalable and adaptable solution for new and existing wells. The accelerated development process, combined with the integration of multiple innovative capabilities, positions this system as an example for adapting existing technology to well construction requirements bringing the benefits of multilateral field development to new applications.
Title: Innovative Multilateral Well Construction System: Accelerated Development and Integrated Capabilities
Description:
Abstract
This paper discusses the development of an innovative multilateral well construction system, showcasing its swift progression from conceptualization to implementation.
The system’s creation was characterized by an efficient and accelerated process, resulting in a solution that seamlessly integrates multiple customer-specified requirements with existing robust capabilities.
The system was specifically developed for use on the AkerBP operated KEG (Kobra East Gekko) field development in the Alvheim area, offshore Norway.
Historically, individual branch control multilateral systems have not been installed in tri-lateral wells within the Alvheim area, with one previous attempt resulting in only partial success – hence a new system was required.
The system development commenced with a comprehensive analysis of existing multilateral well construction methodologies, identifying gaps and inefficiencies.
Leveraging this insight, an interdisciplinary team of operator, service company, and third-party personnel collaborated to define system requirements resulting in a forward-thinking multilateral well construction system.
The emphasis was on expediting the development lifecycle without compromising quality, reliability, or safety standards.
Through meticulous testing and simulation processes, the system’s components were refined to optimize performance as defined in the initial stages of the development.
This iterative testing phase, including an extensive System Integration Test (SIT) not only ensured the robustness of the system but also facilitated the integration of an extensive number of intelligent upper completion configurations.
These new capabilities, collectively elevate the efficiency and precision of the multilateral well construction process.
A collaborative approach ensured flawless project execution all the way from definition, through complete design and development, detailed operations planning, and finally field execution.
An accelerated definition phase was completed, and in the following 12 months a complete level 5 pressure-isolated multilateral system was developed, including rigorous testing and validation of several new components.
The extensive System Integration Test (SIT) was conducted in several stages – both in test facilities in the USA and Norway – to ensure both the multilateral system itself met requirements, but also confirmed compatibility with many different intelligent upper completion configurations, including zonal isolation packers, inflow control valves and gauge carriers.
The first KEG tri-lateral well was successfully completed in Q1 2023, including installation of the upper completion being run through both junction systems.
This was followed by successful installation of the system on the remaining three KEG tri-lateral wells by Q4 2023.
A significant reduction in installation times and associated NPT has also been observed when installing the new system.
The successful deployment of this multilateral well construction system marks a milestone in the industry, presenting a scalable and adaptable solution for new and existing wells.
The accelerated development process, combined with the integration of multiple innovative capabilities, positions this system as an example for adapting existing technology to well construction requirements bringing the benefits of multilateral field development to new applications.
Related Results
Economical Multilateral Well Technology for Canadian Heavy Oil
Economical Multilateral Well Technology for Canadian Heavy Oil
Abstract
In the last two years there has been a dramatic increase in the pace of the evolution of multilateral systems. Many systems with new features and improve...
Development, Testing, and Field Case Histories of Multilateral Well Completion Systems
Development, Testing, and Field Case Histories of Multilateral Well Completion Systems
Abstract
Many enhancements have recently been made to multilateral completion systems, not only as a result of advances in technology but also because of changes ...
Multilateral Technology Innovations Ready to Maximize Field Development
Multilateral Technology Innovations Ready to Maximize Field Development
Abstract
For a quarter of a century sustained technological advances in multilateral technology have enhanced economics and extended the production life of fields in...
Screening Variables for Multilateral Technology
Screening Variables for Multilateral Technology
Abstract
The multilateral well was one of the leading technologies of 1999, and it will continue to be one of the leading technologies for the next 5-10 years. It...
Drilling and Completing Multilateral Horizontal Wells in the Middle East
Drilling and Completing Multilateral Horizontal Wells in the Middle East
Abstract
Multilateral completions provide unique systems that mechanically connect horizontal laterals to parent wellbores and allow selective or commingled produ...
Multilateral Wells Evaluation Utilizing Artificial Intelligence
Multilateral Wells Evaluation Utilizing Artificial Intelligence
Abstract
Multilateral wells are considered to be an advancement revolution in the petroleum industry. The employment of multilateral wells ensured higher drainage an...
Case Histories: Drilling and Completing Multilateral Horizontal Wells in the Middle East
Case Histories: Drilling and Completing Multilateral Horizontal Wells in the Middle East
Abstract
The changing economics of oilfield development has resulted in operators, and therefore, service companies, being challenged to produce greater quantitie...
Inflow Performance of a Stacked Multilateral Well
Inflow Performance of a Stacked Multilateral Well
Abstract
The use of multilateral well is becoming an emerging method to improve oilrecovery efficiently. A stacked multilateral well can produce fluids from twoor...

