Timely roof breaking and pressure relief technology by hard roof staged fracturing
View through CrossRef
Hard roofs in longwall mining often generate large roof caving steps during initial weighting and form extended hanging roofs during periodic weighting. These phenomena can lead to sudden cave-ins, rock bursts, and mine seismicity. This study proposes a staged hydraulic fracturing technique, characterized by advanced hydraulic fracturing and delayed roof caving, to achieve effective roof collapse and pressure relief while mitigating secondary disasters associated with conventional blasting methods. A fracture mechanics model was developed to analyze the ultimate span, bending moment, and roof caving interval of hard roofs under varying stress conditions. The mechanical relationship between fixed-end beams and cantilever beams was established, revealing that the ultimate roof caving interval of a cantilever beam is 0.4082 times that of a fixed-end beam. Formulas were derived to determine the reasonable hanging roof length during periodic weighting, as well as the required fracture depth during both initial mining and periodic weighting. A comparative analysis was conducted between the proposed staged hydraulic fracturing technique and conventional timely blasting. The staged hydraulic fracturing approach reduced engineering workload by more than 28% compared to timely blasting while achieving equivalent roof-hydraulic fracturing and pressure-relief results. Field application at a longwall face with a hard sandstone roof demonstrated fracture distances of 24.04 m during initial mining and 20.73 m during periodic weighting from the working face, with optimal fracture depths of 9.3 and 5.1 m, respectively. The proposed staged hydraulic fracturing technology effectively enables controlled roof hydraulic fracturing and pressure relief under hard roof conditions. It significantly reduces project workload and provides theoretical and practical guidance for the safe and efficient management of hard roofs in longwall mining.
Title: Timely roof breaking and pressure relief technology by hard roof staged fracturing
Description:
Hard roofs in longwall mining often generate large roof caving steps during initial weighting and form extended hanging roofs during periodic weighting.
These phenomena can lead to sudden cave-ins, rock bursts, and mine seismicity.
This study proposes a staged hydraulic fracturing technique, characterized by advanced hydraulic fracturing and delayed roof caving, to achieve effective roof collapse and pressure relief while mitigating secondary disasters associated with conventional blasting methods.
A fracture mechanics model was developed to analyze the ultimate span, bending moment, and roof caving interval of hard roofs under varying stress conditions.
The mechanical relationship between fixed-end beams and cantilever beams was established, revealing that the ultimate roof caving interval of a cantilever beam is 0.
4082 times that of a fixed-end beam.
Formulas were derived to determine the reasonable hanging roof length during periodic weighting, as well as the required fracture depth during both initial mining and periodic weighting.
A comparative analysis was conducted between the proposed staged hydraulic fracturing technique and conventional timely blasting.
The staged hydraulic fracturing approach reduced engineering workload by more than 28% compared to timely blasting while achieving equivalent roof-hydraulic fracturing and pressure-relief results.
Field application at a longwall face with a hard sandstone roof demonstrated fracture distances of 24.
04 m during initial mining and 20.
73 m during periodic weighting from the working face, with optimal fracture depths of 9.
3 and 5.
1 m, respectively.
The proposed staged hydraulic fracturing technology effectively enables controlled roof hydraulic fracturing and pressure relief under hard roof conditions.
It significantly reduces project workload and provides theoretical and practical guidance for the safe and efficient management of hard roofs in longwall mining.
Related Results
Sequential Propagation of Multiple Fractures in Horizontal Wells
Sequential Propagation of Multiple Fractures in Horizontal Wells
ABSTRACT:
Simultaneous fracturing and zipper fracturing of horizontal wells has rapidly evolved to the development of unconventional oil and gas. The fracture int...
Study of Damage Evaluation of Hydraulic Fracturing to Reservoirs
Study of Damage Evaluation of Hydraulic Fracturing to Reservoirs
Abstract
Classic hydraulic fracturing analysis is based on tensile strength of rock, failure criteria of fracture mechanics or Mohr-Coulomb criteria. The existing...
Perspectives of Unconventional Water Sources Implementation in Hydraulic Fracturing
Perspectives of Unconventional Water Sources Implementation in Hydraulic Fracturing
Abstract
Currently, Russia experienced a rapid growth in horizontal wells drilling. The most popular method of completion is hydraulic fracturing. About 99% of hydra...
Development status and Prospect of directional hydraulic fracturing technology for coal mine roof
Development status and Prospect of directional hydraulic fracturing technology for coal mine roof
Aiming at the harm and control methods of thick and hard roof in coal mine, the paper firstly analyzes the advanced control methods of thick and hard roof, such as directional shap...
Three-Dimensional Geomechanical Modeling and Well Spacing Optimization Application in Sichuan Shale Gas Block
Three-Dimensional Geomechanical Modeling and Well Spacing Optimization Application in Sichuan Shale Gas Block
ABSTRACT:
At present, unconventional reservoirs require horizontal drilling and large-scale hydraulic fracturing technology to increase artificial fracture networ...
Research on Environment-Friendly Fracturing Technologies and Practices for Shale Gas Plays in China
Research on Environment-Friendly Fracturing Technologies and Practices for Shale Gas Plays in China
Abstract
At present, shale gas development mainly relies on hydraulic fracturing. However, hydraulic fracturing is associated with significant drawbacks, includin...
Hydraulic Fracturing in Low Temperature Horizontal Wells
Hydraulic Fracturing in Low Temperature Horizontal Wells
Abstract
For shallow burying, the temperature is less than 30°C and low pressure in Putaohua formations in Chaoyanggou area in Daqing oilfield. Eight horizontal well...
Reduced Polymer Loaded Fracturing Fluid For Extreme Temperature Proppant Fracturing
Reduced Polymer Loaded Fracturing Fluid For Extreme Temperature Proppant Fracturing
Abstract
Guar gum and its derivatives based fracturing fluids are most commonly used in hydraulic fracturing. For high temperature wells, guar-based fracturing fluid...